This solicitation is for rubber removal and airfield maintenance services at Kelly Airfield at Joint Base San Antonio-Lackland. Services include paint removal and application, rubber removal, crack and spall repairs, and pavement marking. The work must be performed in accordance with all applicable regulations and specifications while coordinating with airfield operations to minimize impacts. The contractor will submit schedules and plans for approval and coordinate all work, including any required airfield closures. The performance period is from September 2020 through March 2021. The solicitation closes on July 15, 2020, and the contract will be awarded on a fixed-price basis to the responsible offeror with the lowest price. The federal agency is the Department of the Air Force Air Education and Training Command.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JBSA AIRFIELD MAINTENANCE KELL201914
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00.00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 33 00 SUBMITTAL PROCEDURES
01 35 13.00 PROJECT PROCEDURES FOR AIRFIELDS
01 35 13.10 00 SPECIAL PROCEDURES-SURVEYING
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 35 35 ENVIRONMENTAL PROTECTION
01 78 00 CLOSEOUT SUBMITTALS
01 78 36.00 WARRANTY OF CONSTRUCTION
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
DIVISION 09 - FINISHES
09 90 00 PAINTS AND COATINGS
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 11.51 RUBBER AND PAINT REMOVAL FROM AIRFIELD PAVEMENTS
32 17 23 PAVEMENT MARKINGS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
Attachment 1 dated 15 Jun 2020
SECTION 01 11 00.00
SUMMARY OF WORK
08/15
PART 1 GENERAL
1.1 [Enter Appropriate Subpart Title Here]GENERAL
1.2 1.2 Project Objective: The objective of this project is performing annual maintenance including but not limited to: paint, repaint, remove paint, and rubber removal.
1.2.1 Project Description
1.2.1 All work shall follow standards defined by UFC 3-260-01 Airfield and Heliport Planning and Design, UFC 3-260-04 Airfield and Heliport Marking, AFI 32-1042 Standards for Marking Airfields, as well as Joint Base San Antonio (JBSA) regulations, local, state, and federal codes, regulations, and requirements.
1.2.2 All work shall be performed in strict accordance with the provided contract specifications, drawings, JBSA regulations, local, State, Federal codes, regulations, and contract requirements as applicable. It is the contractor's responsibility to secure access to specific governing criteria as required. The Government relies on the contractor to follow and implement the necessary codes as the expert General Contractor (GC).
Contractor shall perform construction in accordance with the specifications (UFGS) within this solicitation and shall add additional Unified Facilities Guide Specifications as required. The contractor shall follow and abide by the UFC and referenced industry code within the Unified Facilities Criteria UFC. It is the contractor's responsibility to secure access to specific codes as required.
1.2.3 The contractor must maintain the airfield construction area and all airfield areas impacted or travelled by the contractor free of Foreign Object Damage (FOD), by sweeping, vacuuming, and/or other approved methods means.
1.2.4 Contractor's access to the airfield shall be restricted to those areas where work is on-going.
1.2.5 The contractor shall take adequate protective measures to ensure that existing pavement, facilities, and resources are not damaged in the construction efforts.
1.2.6 Three weeks prior to the start of work the contractor shall submit to the Contracting Officer the names, dates of birth, and driver's license numbers/states of issue for each person working on this project. These names will be submitted to security for a background check and once they are approved they will be put onto an Entry Authorization List (EAL). This is separate from the base pass. One EAL must be requested for each airfield.
1.2.7 Contractor shall install a backflow preventer when connecting to a water supply on any of the Joint Base San Antonio Installation. Contact San Antonio Water System for access, procedures and approval for connection to the water system.
SECTION 01 11 00.00 Page 1
1.2.8 Three weeks prior to the start of work the contractor shall request an Airfield Drivers Class. Class size is limited to 4 to 6 people. An airfield driver's license is required for all personnel who will be driving on the airfield. Contractors shall bring a contractor owned vehicle to the class for the driving test. Contractor shall provide names, dates of birth, driver's license numbers/states of issue, and driver's license restrictions of each person taking the class. Drivers with color blindness will not be permitted to drive on the airfield. Color vision proof shall be provided in written form, and signed by a Doctor. FAA regulations require the control tower to speak English. The driver shall understand and speak English well enough to communicate to the control tower and take a written test. The driver shall have a current driver's license.
1.2.9 A minimum of two contractor personnel shall have an airfield driver's license and a current AF Form 483 and they shall remain on site at all times. One airfield licensed driver is required for every 5 people on the EAL.
1.2.10 Radio communication with the base operations/tower operations must be maintained at all times that work is conducted on the airfield.
1.2.11 Lackland Kelly airfield is open 24 hours day 7 days per week. All runway work shall be done during a soft closure. A soft closure for this SOW is defined as; planes will be restricted from work zones with the exception of a rare mission essential plane that may be required to land or take?off. During a soft closure the contractor, if required, shall open the runway safe for landing and within regulation with a minimum of 10 minutes notice. The contractor will be given a minimum of 10 shifts per month. Monday through Friday work will be permitted on the runway from 11:00 pm to 7:00 am. Saturday and Sunday work 5:00 pm to 8:00 am.
Contractor shall be ready to work nights, weekends and holidays. These shifts will be determined by the airfield manager. All work on the Lackland (Kelly) airfield shall be accomplished during airfield pre?coordinated dates and closure times.
1.2.12 All work shall be in accordance with the contract specifications and applicable documents referenced in this SOW. Striping of each Runway shall be subject to the guidelines listed in the painting section below.
1.2.13 All airfield work shall be accomplished in coordination with the respective 502 CES Project manager to eliminate conflicts with the active airfield operation.
1.2.14 The contractor shall provide copies of all material delivery tickets. All demolished materials shall be recycled to the greatest extent possible and the recycle and dumpster haul offs shall be provided to the government in a monthly summary spreadsheet.
1.2.15 The contractor shall take the necessary actions to prevent utility breaks or other facility damages in addition to the work clearance permit.
Examples include but are not limited to metal detection, reviewing of as?built drawings, etc.
1.2.16 All recycle material shall be documented on a manifest and submitted to the Government. All material removed from the installation as debris shall be documented on a manifest and submitted to the Government.
SECTION 01 11 00.00 Page 2
1.2.17 A radio for tower communication will be made available by Airfield Operations.
1.2.18 Hard hats and ball caps are not normally permitted on the airfield, but may be allowed as required if they tied to the head under the chin with a manufacturer's attachment.
2.0 Taskers: The contractor is responsible to acquire all information to address the items annotated within this Statement of Work (SOW) and referenced regulations, codes and guides. In addition, contractor shall abide by section "2.0 Applicable documents" of this SOW.
2.1 General:
2.1.1 This shall be done in a manner that maintains the operational status of the Kelly Airfield, (It is open 24 hours a day seven (7) days per week. All runway work shall be done during a soft closure).
2.1.2 Before any new paint is applied, the pavement surface much be prepared to ensure the paint adheres in accordance with the specifications.
This should be done in such a manner that the airfield pavement and appurtenances are not damaged.
2.1.3 The contractor shall provide water pressure impact upon the indicated pavement areas sufficient to remove the designated paint without damaging the existing pavement, joint sealant, and other airfield appurtenances. The contractor shall be responsible for repairing any damage caused by the removal work.
2.1.4 Contractor shall phase the paint schedule and plan accordingly. For all retroreflective markings a life cycle cost analysis was completed for JBSA by the 502d Civil Engineering Squadron (CENMP-LAK). Use glass beads available under Federal Specification TT-B-1325, Beads, Retroreflective, Type I, Gradation A or better.
2.1.5 Lackland's Kelly airfield is open 24 hours day 7 days per week.
Contractor shall strictly adhere to the pre-approved schedule so that normal airfield operations are not interrupted. The following is the recommended rubber removal schedule.
1. LAK North End - 4,000 feet in length by 75 feet wide and 37.5 ft wide down CL (Sep 2020, Nov 2020, Jan 2021, Mar 2021)
2. LAK North End repaint were rubber was removed (Sep 2020, Nov 2020, Jan 2021, Mar 2021)
3. LAK South End - 4,000 feet in length by 75 feet wide (Sep 2020, Mar 2021)
4. LAK South End - repaint were rubber was removed (Sep 2020, Mar 2021)
The Government relies on the contractor to follow and implement the necessary codes as the expert General Contractor (GC). Contractor shall perform construction in accordance with (IAW) the specifications within the contract and shall submit for approval, modified Unified Facilities Guide Specifications (UFGS) as required. The contractor shall follow and abide by, but not limited to the Unified Facility Criteria (UFC) 4-022-03, other
SECTION 01 11 00.00 Page 3
UFCs as referenced or applicable, and referenced industry code. The reference website for UFGS and UFC documents is www.wbdg.org.1.2.2
1.2.3
2.1.7 Work Elements
The contractor shall furnish all labor, material, personnel, equipment, tools, supervision, inspection/quality control, and other items and services necessary to manage, and accomplish airfield maintenance requirements. Airfield maintenance will include a broad range of repair, alteration, and/or new construction work on real property incidental to airfield projects. The contract work elements represented listed below are included, but are not limited to, the below listed items/tasks:1.2.3.1
[Enter Appropriate Subpart Title Here]1.2.3.1.1 [Enter Appropriate Subpart Title Here]
2.1.8 Paint
Airfield paint markings shall conform to the requirements of Air Force Instructions 32-1042, STANDARDS FOR MARKING AIRFIELDS and Engineering Technical Letter (ETL) 04-02 (change 2).
3. Airfield Markings, Non-reflective Paint 6 inches wide (LF)
4. Paint (LF)
5. Paint Beading (LF)
1.3 2.1.9. AIRFIELD REQUIREMENTS
1.3.1
2.1.9.1 Temporary Construction Waiver
Airfield maintenance work such as joint seal, spall repairs, crack repairs, paint removal and repainting, slab demo and replacement, replacing old/missing tie-downs and ground points, and other work elements included in this contract pose a hazard on the airfield and shall require a Temp Construction Waiver. Temporary Construction Waiver packages shall include the AETC Form 82, a risk assessment, and a Phasing Plan.
2.1.9.2 Schedule 1.3.2 [Enter Appropriate Subpart Title Here]
The Contractor will submit a projected work schedule at least fourteen (14) working days in advance for work on or near the flight line, taxiway, runway or apron areas. The projected work schedule shall be thoroughly coordinated with Base Operations and approved by the Contracting Officer prior to starting work.
2.1.9.3 The Government shall use the progress schedule to measure the progress of the work and aid in evaluating all progress payments. The contractor shall submit an AF Form 3065 every month which is derived from the progress updated IMS and commensurate with work performed.
2.1.9.4 The Contractor shall provide for weather delays that prohibit productive construction in their construction schedule.
2.1.9.5 The project schedule shall define the time line of all major activities required to implement the contractor's action for the project.
Phasing of the contractor's action shall be based upon the coordination and approval of the government. The project schedule shall define all equipment shutdown and re-activation dates. Also, the Contractor shall
SECTION 01 11 00.00 Page 4 define the use of any temporary equipment necessary to perform equipment shutdowns.
2.2 Plans, Reports, Deliverables
2.2.1 Submittal Register
2.2.1.1 The Submittal Register shall list all drawings, manufacturer's data, operation and maintenance manuals, etc. as required by the Statement of Work, or Specifications, which will be submitted subsequent to the Work Plan. Each submittal listed shall indicate by section and paragraph, the mode of requirement, (i.e. Statement of Work section and paragraph, Specification section and paragraph, etc.) Each submittal listed shall have all information filled out in its entirety, for each of the data columns on the Submittal Register Form.
2.3 Site work
2.3.1 Final Inspection
The Contractor shall attend a final inspection and publish the findings in a final inspection report in accordance with the format approved by the Contracting Officer. At the final inspection, the Contractor shall present a completed DD Form 1354, Transfer and Acceptance of Real Property to the Base Civil Engineer (BCE) or other appropriate organization for signature and acceptance. The final inspection report shall: (1) certify that the construction is complete, and (2) provide for one year warranty letter for all tasks performed under the contract.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00.00 Page 5
SECTION 01 14 00
WORK RESTRICTIONS
11/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. AIR FORCE (USAF)
AFI 40-201 (Incorporating Change 1, 17 December 2015) Radioactive Materials (RAM) Management
AFI 48-148 (20 NOVEMBER 2014) Ionizing Radiation Protection
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval and for informational/record use only as part of the project file.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals list of Contract Personnel; G
Installation Access
1.3 SPECIAL SCHEDULING REQUIREMENTS
All medical and mission critical areas will remain in operation during the entire construction period. The contractor shall conduct his operations so as to cause the least possible interference with normal operations of the activity.
Permission to interrupt any Activity roads, railroads, and/or utility service must be requested in writing a minimum of 30 calendar days prior to the desired date of interruption.
1.4 CONTRACTOR ACCESS AND USE OF PREMISES
1.4.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter restricted areas unless required to do so and cleared for such entry. Mark all Contractor equipment for identification
SECTION 01 14 00 Page 1
1.4.1.1 Subcontractors and Personnel Contacts
Provide a list of contract personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency, As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.4.1.2 Installation Access
Non DOD persons (Contractors, vendors, etc) requiring entry to JBSA installations shall be sponsored by an authorized DBIDS registered DOD ID card holder.
Sponsors must notify the Security Forces Visitor Control Center for the installation that access is required no later than 10 days prior to the requested entry date. Sponsors or Authorizing Official must request the permit in writing or via email from a .mil address to the Visitor Control Center. An Application forthe Installation Access Credential form (see Appendix D) will be submitted by the Sponsor or Official to the Pass and Registration Office. Contractor and vendor companies requiring access to Joint Base San Antonio shall provide the credential information for their employees to the sponsor in order to process the access.
All construction contractor employees shall have:
a. One form of picture identification
b. Provide personal (full name, date of birth, home address, and driver license number) and vehicle information.
c. A memorandum from the construction company on company letterhead stating the reason for entry, contract number, project start and end date, and the location at the JBSA installation where the jobsite is located.
1.4.1.3 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.4.1.4 Government Housing Areas
a. Haul routes to and from constructions sites cannot go throught the housing, residential areas.
b. When working inside a housing area, working hours are limited to 0800 (8 am) to 1600 (4 pm) unless otherwise approved by the Contracting Officer.
1.4.2 Emergency Response Requirement
Contractors reporting an emergency should provide the 9-1-1 dispatcher with the following information:
a. Building number, address or general location
SECTION 01 14 00 Page 2
b. Name
c. Phone number
d. Emergency information (cause of fire, explosion, natural gas leak, injuries, etc.)
e. Please, do not hang up the phone until directed by the 9-1-1 dispatcher.
IMPORTANT: If calling 9-1-1 from a mobile phone on any JBSA location you will be directed to the local 9-1-1 dispatcher. Advise the local dispatcher of your location (JBSA-Fort Sam Houston, JBSA-Lackland or JBSA-Randolph).
Immediately the local dispatcher will transfer the 9-1-1 phone call to a JBSA emergency dispatcher.
1.4.3 Radioactive Materials and Equipment (Use and Storage)
a. Non-Air Force agencies, including contractors, who intend to use, or store, radiation sources on Joint Base San Antonio, Fort Sam Houston and Camp Bullis must obtain proper authorization in accordance with the above references AFI 40-201 and AFI 48-148. Non-Air Force agencies will not use radiation sources on referenced locations without an approved Department of the Air Force Radiation Permit. Such equipment typically includes equipment for Soil Density Testing, Lead-Based Paint Analysis (X-Ray fluorescent analyzer), etc.
b. Non-Army agencies (including civilian contractors) require an Air Force Radiation Permit(s)(AFRP) to use or possess ionizing radiation sources on an Air Force installation. For the purpose of this paragraph, ionizing radiation source means any source that, if held or owned by an Air Force organization, would require a specific NRC license or Air Force radiation authorization - ARA.
c. The non-Air Force applicant will apply by letter with supporting documentation through the Installation Radiation Safety Officer (RSO).
Submit the letter so that the installation representative receives the application at least thirty (30) days before the requested start date of the permit.
d. The Air Force radiation permit (AFRP) application will specify start and stop dates for the AFRP and describe for what purposes the applicant needs the AFRP. See the document in Appendix A for AFRP requirements and instructions to apply for a permit. The following information shall be submitted to the RSO for the AFRP request.
1) Brief Description of Proposed Activities
2) The applicant possesses a valid U.S. Nuclear Regulatory Commission (NRC) Form 347 material license that allows the applicant to use the source as specified in the AFRP application.
3) The applicant possesses a valid Agreement State or Radioactive Material License (Texas Department of Health, Bureau of Radiation Control) license that allows the applicant to use radioactive material (RAM) as specified in the AFRP application and the applicant has filed NRC Form 241, Report of Proposed Activities in Non-Agreement States, with the NRC in accordance with 10 CFR
150.20. A copy of the NRC Rom 241, must accompany the TRC Form 12-1. An AFRP issued under this circumstance will be valid for no more than 180 days in any calendar year.
4) Project Local Point of Contact: Name, Address, and Phone.
SECTION 01 14 00 Page 3
5) Company Radiation Safety Officer: Name, Address, and Phone.
6) Copy of Contractual Clause of the Air Force/Army Contract describing work to be performed and inclusive dates (from the contract)
7) Provide log of actual equipment usage to the 59th Medical Wing
RSO.
8) Leak test documentation for the equipment with the radioactive source(s).
9) Site map defining area where radioactive materials/equipment is to be used.
10) Radiation Safety Program to include standard operating procedures (SOP), training program and designation of Radiation Protection/Safety Officer.
11) Written confirmation that the 59th Medical Wing RSO can conduct periodic assessments and has authority to suspend contractor operations believed to be unsafe.
12) For naturally occurring or accelerator produce radioactive material (NORM/NARM) and machine-produced ionizing radiation sources, the applicant has an appropriate State authorization that allows the applicant to use the source as specified in the AFRP application or has in place a radiation safety program that complies with Air Force requirements.
e. All AFRPs will require applicants to remove all permitted sources from Air Force property by the end of the work day. (Ft. Sam Houston policy, no radiation producing equipment will be stored on Ft. Sam Houston and Camp Bullis property overnight).
f. Disposal of radioactive material (RAM) by non-Air Force agencies on Air Force property is strictly prohibited. 3.2.3 Review, Approval/Disapproval. Review of the permit request and subsequent approval/disapproval requires approximately 30 days.
g. Submission of Application. Submit three copies of the application with the required supporting documentation to 59th Medical Wing Office, Point of Contact:
JBSA Installation Radiation Protection Officer (RSO) Capt Eduardo Artiga 59th Medical Wing/SGPB 559 MDW Office Telephone No: 210.671-7205 E-mail: eduardo.artiga.1@us.af.mil
1.4.4 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 14 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving
SECTION 01 14 00 Page 4 the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours..
1.4.5 Permits and Requests
All permit requests must include at minimum the following:
a. Site Map (8" x 11" or 8" x 14") 5 complete copies
b. 100% Construction Drawings 5 complete copies (11x17)
c. Project Name and Number
d. Contractor & Subcontractor Name
e. Brief Description of Work - Identify all buildings and/or facilities possibly affected.
f. Desired Date for Work to Begin
g. Estimated Duration of Work
h. 14 Day Advance Notice minimum, unless otherwise noted.
i. Contractor's Representative Contact Information
1.4.5.1 Digging Permits / Utility Locate
a. Digging permits must be obtained prior to prior to any digging, drilling or any excavation work.
b. Digging permit /utility locates are available by submitting the completed US Air Force Form 103 located in Appendix A to the 502 CES Construction Manager.
c. Contractor to allow (14) calendar days for Government review of digging permit requests. A digging permit for a specified area of excavation expires 30 days after the issue date; the contractor shall re-apply for a new permit to perform excavation in the area if the excavation was not started within the 30-day period.
d. Permits will identify all underground utilities within 5 feet of the designated area. Contractor shall be responsible for all repairs, costs, and damages due to excavating without permit or damaging an identified utility.
1.4.5.2 Utility Outage Permit
a. Contractor shall complete and submit a written request 14 days in advance of the requested utility outage to CES Utility Manager through the 502 CES Construction Manager. The request shall include the utility service to be affected, proposed date, proposed time, and outage duration. Form 103 included in Appendix A can also be used for the request.
b. Contractor shall be responsible to coordinate with CPS Energy about any energy or gas outage request. This coordination is separate than the
SECTION 01 14 00 Page 5 government coordination.
c. Provide CES Construction Manager a copy of the written Utility Outage request.
d. After submitting the request to the government, the contractor shall received approval from the government prior to schedule a utility outage.
1.4.5.3 Hot Work Permits
Under no circumstances shall hot work operations start without a hot work permit.
All welding and cutting operations shall be performed in accordance with National Fire Protection Association NFPA Standard 5lB Fire Prevention during Welding, Cutting, and Other Hot Work. Contact the site specific JBSA fire department to request an AF Form 592 USAF Welding, Cutting and Brazing Permit. Ensure a copy of the AF Form 592 is located on site. Phone numbers are:
JBSA-Ft Sam Houston Fire Prevention
(210) 221-2727
JBSA-Lackland Fire Prevention
(210) 671-2921
JBSA-Randolph Fire Prevention
(210) 652-6915
Permits expire in 30 days. If work will extend beyond 30 day period the contractor shall contact JBSA Fire and Emergency Services to re-issue a new permit.
1.4.5.4 Road Closure Approval Requests
a. Road closings will not be permitted without approval. To get approval for a proposed road closure contractor shall submit a traffic control plan to the 502 CES Construction manger prior to anticipated need for closure
b. The Contractor traffic control plan will include each section of road that will be worked on or impacted as a result of this contract. The traffic control plan shall be in accordance with "Traffic Controls for Street and Highway Construction and Maintenance Operations" of the latest edition of the "Texas Manual on Uniform Traffic Control Devices."
c. Contractor will provide traffic control signs and barricades for all street widening and extensions. At least one lane of traffic must be maintained at all times.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
-- End of Section --
SECTION 01 14 00 Page 6
SECTION 01 33 00
SUBMITTAL PROCEDURES
05/11
PART 1 GENERAL
1.1 DEFINITIONS
1.1.1 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections.
Submittals are identified by Submittal Description (SD) numbers and titles as follows:
SD-01 Preconstruction Submittals
Submittals which are required prior to start of construction (work).
Certificates of insurance
Surety bonds
List of proposed Subcontractors
List of proposed products
Construction progress schedule
Network Analysis Schedule (NAS)
Submittal register
Schedule of prices or Earned Value Report
Health and safety plan
Work plan
Quality Control(QC) plan
Environmental protection plan
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, SECTION 01 33 00 Page 1 instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-04 Samples
Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.
Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a Canmaterial, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.
Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports.
Daily logs and checklists.
Final acceptance test and operational test procedure.
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.
SECTION 01 33 00 Page 2
Confined space entry permits.
Text of posted operating instructions.
SD-08 Manufacturer's Instructions
Preprinted material describing installation of a product, system or material, including special notices and (SDS) concerning impedances, hazards and safety precautions.
SD-10 Operation and Maintenance Data
Data that is furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel, including manufacturer's help and product line documentation necessary to maintain and install equipment. This data is needed by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.
This data is intended to be incorporated in an operations and maintenance manual or control system.
1.1.2 Approving Authority
Office or designated person authorized to approve submittal.
1.1.3 Work
As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with this section.
SD-01 Preconstruction Submittals
Submittal Register; G
1.3 SUBMITTAL CLASSIFICATION
Submittals are classified as follows:
1.3.1 Designer of Record Approved (DA)
Designer of Record (DOR) approval is required for extensions of design, critical materials, any deviations from the solicitation, the accepted proposal, or the completed design, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer. Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are considered to be "shop drawings." Contractor to provide the Government with the number of copies designated hereinafter of all DOR approved submittals. The
SECTION 01 33 00 Page 3
Government may review any or all Designer of Record approved submittals for conformance to the Solicitation, Accepted Proposal and the completed design. The Government will review all submittals designated as deviating from the Solicitation or Accepted Proposal, as described below. Design submittals to be in accordance with Section 01 33 16.00 10 DESIGN DATA (DESIGN AFTER AWARD). Generally, design submittals should be identified as SD-05 Design Data submittals.
1.3.2 Government Approved (G)
Government approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer.
Government approval is required for any deviations from the Solicitation or Accepted Proposal and other items as designated by the Contracting Officer. Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are considered to be "shop drawings."
1.3.3 Sustainability Reporting Submittals (S)
Submittals for Guiding Principle Validation (GPV) or Third Party Certification (TPC) are indicated with an "S" designation. Submit the information required by the technical sections that demonstrates compliance with the sustainable requirement, and for inclusion in the Sustainability eNotebook as required by Section 01 33 29 SUSTAINABILITY REPORTING. A full submittal for an item may be provided under another SD; however, for the "S" submittal, only provide that portion of the submittal that demonstrates compliance with the sustainable requirement. If the sustainable submittal does require Government Approval, it may be tagged under another SD with a "G."
Schedule submittals for these items throughout the course of construction as provided; do not wait until closeout.
1.4 PREPARATION
1.4.1 Transmittal Form
1.4.2 Source Drawings for Shop Drawings
The entire set of Source Drawing files (DWG) will not be provided to the Contractor. Only those requested by the Contractor to prepare shop drawings may be provided. Request the specific Drawing Number only for the preparation of Shop Drawings. These drawings may only be provided after award.
1.4.2.1 Terms and Conditions
Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government.
The Contractor must make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use
SECTION 01 33 00 Page 4 of these electronic files.
These electronic Source Drawing files are not construction documents.
Differences may exist between the Source Drawing files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic Source Drawing files, nor does it make representation to the compatibility of these files with the Contractor hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished Source Drawing files, the signed and sealed construction documents govern. The Contractor is responsible for determining if any conflict exists. Use of these Source Drawing files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project.
If the Contractor uses, duplicates or modifies these electronic Source Drawing files for use in producing construction data related to this contract, remove all previous indicia of ownership (seals, logos, signatures, initials and dates).
1.4.3 Electronic File Format
Provide submittals in electronic format, with the exception of material samples required for SD-04 Samples items. Compile the submittal file as a single, complete document, to include the Transmittal Form described within. Name the electronic submittal file specifically according to its contents, coordinate the file naming convention with the Contracting Officer. Electronic files must be of sufficient quality that all information is legible. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer. Generate PDF files from original documents with bookmarks so that the text included in the PDF file is both searchable and can be copied. If documents are scanned, Optical Character Resolution (OCR) routines are required. Index and bookmark files exceeding 30 pages to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature, or scan of a signature.
Provide electronic documents on an optical disc, or through an electronic file sharing system such as the AMRDEC SAFE Web Application located at the following website: https://safe.amrdec.army.mil/safe/.
1.4.4 Hard Copy Submittals
In addition to the electronic submittal, provide two hard copies of all submittals.
1.5 QUANTITY OF SUBMITTALS
1.5.1 Number of Copies of SD-02 Shop Drawings
Submit three copies of submittals of shop drawings requiring review and approval only by QC organization and four copies of shop drawings requiring review and approval by Contracting Officer.
1.5.2 Number of Copies of SD-03 Product Data and SD-08 Manufacturer's Instructions
Submit in compliance with quantity requirements specified for shop drawings.
SECTION 01 33 00 Page 5
1.5.3 Number of Samples SD-04 Samples
a. Submit two samples, or two sets of samples showing range of variation, of each required item. One approved sample or set of samples will be retained by approving authority and one will be returned to Contractor.
b. Submit one sample panel or provide one sample installation where directed. Include components listed in technical section or as directed.
c. Submit one sample installation, where directed.
d. Submit one sample of non-solid materials.
1.5.4 Number of Copies SD-05 Design Data and SD-07 Certificates
Submit in compliance with quantity requirements specified for shop drawings.
1.5.5 Number of Copies SD-06 Test Reports and SD-09 Manufacturer's Field Reports
Submit in compliance with quantity and quality requirements specified for shop drawings other than field test results that will be submitted with QC reports.
1.5.6 Number of Copies of SD-10 Operation and Maintenance Data
Submit three copies of O&M Data to the Contracting Officer for review and approval.
1.5.7 Number of Copies of SD-01 Preconstruction Submittals and SD-11 Closeout Submittals
Unless otherwise specified, submit two sets of administrative submittals.
1.6 INFORMATION ONLY SUBMITTALS
Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals.
The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work;
and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe. For design-build construction the Government will retain two copies of information only submittals.
1.7 SUBMITTAL REGISTER
Prepare and maintain submittal register, as the work progresses. Do not change data which is output in columns (c), (d), (e), and (f) as delivered by Government; retain data which is output in columns (a), (g), (h), and
(i) as approved. A submittal register showing typical items of equipment and materials for which submittals are required by the specifications is provided as an attachment. This list may not be all inclusive and
SECTION 01 33 00 Page 6 additional submittals may be required. The Government will provide the initial submittal register in electronic format with the following fields completed, to the extent that will be required by the Government during subsequent usage.
Column (c): Lists specification section in which submittal is required.
Column (d): Lists each submittal description (SD No. and type, e.g. SD-02 Shop Drawings) required in each specification section.
Column (e): Lists one principal paragraph in specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting project requirements.
1.7.1 Use of Submittal Register
Submit submittal register. Submit with QC plan and project schedule.
Government provided submittal register lists only typical items. Contractor shall verify that all submittals required for project are listed and add missing submittals. Coordinate and complete the following fields on the register submitted with the QC plan and the project schedule:
Column (a) Activity Number: Activity number from the project schedule.
Column (g) Contractor Submit Date: Scheduled date for approving authority to receive submittals.
Column (h) Contractor Approval Date: Date Contractor needs approval of submittal.
Column (i) Contractor Material: Date that Contractor needs material delivered to Contractor control.
1.7.2 Contractor Use of Submittal Register
Update the following fields in the Government-furnished submittal register program or equivalent fields in program utilized by Contractor with each submittal throughout contract.
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.
Column (l) List date of submittal transmission.
Column (q) List date approval received.
1.7.3 Approving Authority Use of Submittal Register
Update the following fields in the Government-furnished submittal register program or equivalent fields in program utilized by Contractor.
Column (b) Transmittal Number: Contractor assigned list of
SECTION 01 33 00 Page 7 consecutive numbers.
Column (l) List date of submittal receipt.
Column (m) through (p) List Date related to review actions.
Column (q) List date returned to Contractor.
1.7.4 Copies Delivered to the Government
Deliver one copy of submittal register updated by Contractor to Government with each invoice request.
1.8 VARIATIONS
Variations from contract requirements require both Designer of Record (DOR) and Government approval pursuant to contract Clause FAR 52.236-21 and will be considered where advantageous to Government.
1.8.1 Considering Variations
Discussion with Contracting Officer prior to submission, after consulting with the DOR, will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).
Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government.
1.8.2 Proposing Variations
When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government, including the DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item.
Clearly mark the proposed variation in all documentation.
1.8.3 Warranting that Variations are Compatible
When delivering a variation for approval, Contractor, including its Designer(s) of Record, warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
1.8.4 Review Schedule Extension
In addition to normal submittal review period, a period of 21 working days will be allowed for consideration by the Government of submittals with variations.
1.9 SCHEDULING
Schedule and submit concurrent submittals covering component items forming a system or items that are interrelated. Include certifications to be
SECTION 01 33 00 Page 8 submitted with the pertinent drawings at the same time. No delay damages or time extensions will be allowed for time lost in late submittals.
a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential resubmittal of requirements.
b. Submittals called for by the contract documents will be listed on the contractor submitted and approved register. If a submittal is called for but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but which have been omitted from the register or marked "N/A."
c. Re-submit register and annotate monthly by the Contractor with actual submission and approval dates. When all items on the register have been fully approved, no further re-submittal is required.
d. Carefully control procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."
1.9.1 Government Reviewed Design
The Government will review design submittals for conformance with the technical requirements of the solicitation. Section 01 33 16.00 10 DESIGN DATA (DESIGN AFTER AWARD) covers the design submittal and review process in detail. Government review is required for deviation from the completed design. Review will be only for conformance with the contract requirements. Included are only those construction submittals for which the Designer of Record design documents do not include enough detail to ascertain contract compliance. The Government may, but is not required, to review extensions of design such as structural steel or reinforcement shop drawings.
1.10 GOVERNMENT APPROVING AUTHORITY
When approving authority is Contracting Officer, the Government will:
a. Note date on which submittal was received.
b. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.
c. Identify returned submittals with one of the actions defined in paragraph REVIEW NOTATIONS and with markings appropriate for action indicated.
Upon completion of review of submittals requiring Government approval, sign and date submittals. Two copies of the submittal will be retained by the Contracting Officer and elctronic copies of the approved AF 3000 will be returned to the Contractor. If the Government performs a conformance review of other Designer of Record approved submittals, the submittals will be so identified and returned, as described above.
SECTION 01 33 00 Page 9
1.10.1 Review Notations
Submittals will be returned to the Contractor with the following notations:
a. Submittals marked "approved" or "accepted" authorize the Contractor to proceed with the work covered.
b. Submittals marked "approved as noted" or "approved, except as noted, resubmittal not required," authorize the Contractor to proceed with the work covered provided he takes no exception to the corrections.
c. Submittals marked "not approved" or "disapproved," or "revise and resubmit," indicate noncompliance with the contract requirements or design concept, or that submittal is incomplete. Resubmit with appropriate changes. No work shall proceed for this item until resubmittal is approved.
d. Submittals marked "not reviewed" will indicate submittal has been previously reviewed and approved, is not required, does not have evidence of being reviewed and approved by Contractor, or is not complete. A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed. Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change.
1.11 DISAPPROVED SUBMITTALS
Make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the FAR clause entitled CHANGES, is to be given to the Contracting Officer. Contractor is responsible for the dimensions and design of connection details and construction of work. Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense.
If changes are necessary to submittals, make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.
1.12…