This is a Special Provision for Maintaining Traffic issued by the Michigan Department of Transportation (MDOT) for a construction project on M-29 in Utica and Shelby Township, Macomb County. The provision establishes requirements and restrictions to maintain traffic on M-29 from approximately 0.5 miles west of Sierra Drive to 0.5 miles east of Baker Road, with the Construction Influence Area extending to intersecting roads including I-94, M-3, 23 Mile Road, Altman Road, and Baker Road. The contractor must maintain a minimum of one lane of traffic in each direction at all times on M-29, utilize specified Maintaining Traffic Typicals, and comply with defined traffic restriction schedules. Lane closures are prohibited during holiday periods (Independence Day and Labor Day) and special local events (Bay Rama Fish Fly Festival, Anchor Bay Triathlon, and Bay Area Sports Show). The contractor must develop and submit an Internal Traffic Control Plan (Type A) for Engineer approval at the preconstruction meeting, with the Engineer having seven calendar days for review. All lane closure requests must be submitted seven calendar days in advance using the Lane Closure Notification/Request Form, with the Engineer allowing four calendar days for approval before implementation.

Traffic control devices must comply with the Michigan Manual on Uniform Traffic Control Devices and ATSSA Quality Guidelines, with channelizing devices spaced at 25 feet for tapers and 50 feet for tangents. The contractor is responsible for obtaining necessary permits from local governments and coordinating with emergency services, transit agencies, law enforcement, and schools, with all coordination costs included in the "Traffic Control Inclusive" pay item. Hot mix asphalt milled areas must be resurfaced the same day as the cold milling operation, and transverse and longitudinal tapers must be properly marked with appropriate warning signs. Portable Changeable Message Signs must be installed and operational a minimum of seven calendar days prior to work start and messages must be updated at the end of each work period. All costs associated with traffic control requirements, including transporting traffic control items, providing vehicles and staff for changes and removals, and obtaining an approved Internal Traffic Control Plan, are included in the "Traffic Control Inclusive" pay item with no additional payment available to the contractor.

View the file

Other files

File Type Posted
PW.Macomb County.pdf PDF
Schedule C- Aerial Map.pdf PDF
Schedule B - Pricing.Mastic M29.xlsx XLSX spreadsheet
RFP 25.2608-Mastic Repair M29.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

V4.0

MICHIGAN

DEPARTMENT OF TRANSPORTATION

SPECIAL PROVISION

FOR

MAINTAINING TRAFFIC

Macomb TSC:KRK 1 of 6 APPR:MAC:KRK 6-3-25

a. Description. This special provision consists of requirements and restrictions to maintain traffic on M-29 in the city of (Utica and Shelby Township), Macomb County.

b. General. Maintain traffic throughout the project in accordance with the standard specifications, typicals, and supplemental specifications in the contract and as described on the plans for this project.

c. Construction Influence Area (CIA). The CIA includes the right-of-way of the following roadways, within the approximate limits described below:

1. On M-29 from approximately 0.5 miles west of Sierra Dr. to 0.5 miles east of Baker Rd.

2. In addition, the CIA includes the right-of-way of any designated detour route or alternate route, intersecting roads and ramps adjacent to the work zone for a distance of approximately 1/4 mile in advance of the work zone or as far as the construction or detour signing extends. The roads include but are not limited to I-94, M-3, 23 Mile, Altman Rd and Baker Rd.

d. Traffic Restrictions. Maintain traffic in accordance with the Maintaining Traffic Typicals contained herein, except as noted below. Changes or adjustments to the Maintaining Traffic Typicals may be necessary to fit field conditions, subject to approval of the Engineer or as determined by the Engineer.

1. Utilize the following Maintaining Traffic Typicals:

A. 100-GEN-KEY

B. 101-GEN-SPACING-CHARTS

C. 102-GEN-NOTES

D. 103-GEN-SIGN

E. 104-GEN-AB

F. 105-GEN-SPEED-FW

G. 106-GEN-SPEED-NFW

H. 107-GEN-SPEED

Macomb TSC:KRK 2 of 6 6/3/25

I. 133-CLT-1LC-(L)

J. 135-CLT-2(R+L)LC-SHIFT

K. 203-FW-1LC-(R)

L. 204-FW-1LC-(L)

M. WZD-100-A - 8in

N. WZD-125-E - 8in

2. Do not work, deliver material, or close lanes (other than approved stage closures) during the holiday periods as defined in Table 1. Cover or remove “45 where workers present” signing during the holiday periods as defined in Table 1.

Table 1: 2024 Holiday Periods

Holiday Start Date and Time End Date and Time

Independence Day 3:00 p.m. Thursday, July 3rd 6:00 a.m. Monday, July 7th

Labor Day 3:00 p.m. Friday, August 29th 6:00 a.m. Tuesday, September 2nd

3. Do not work, deliver material, or close lanes (other than approved stage closures) during the Special Events as defined in Table 2. Cover or remove “45 where workers present” signing during the holiday periods as defined in Table 2.

Table 2: 2024 Special Events

Local Event Start Dates and Time End Date and Time

Bay Rama Fish Fly Festival 3:00 p.m. Wednesday, June 18th 6:00 a.m. Monday, June 23rd

Anchor Bay Triathlon 3:00 p.m. Friday July 11th 6:00 a.m. Sunday July 13th

Bay Area Sports Show 3:00 p.m. Wednesday July 30th 6:00 a.m. Monday August 4th

4. Perform work and lane closures within the allowable time frames as shown in Tables

3 and 4, unless otherwise approved by the Engineer. Traffic switch operations on freeways may take place within the allowable times listed below in the traffic restriction tables and/or as otherwise approved by the Engineer. Additional lane, ramp, and/or roadway closures and shifts may be implemented during maintaining traffic stage and traffic switch operations with prior Engineer approval.

5. Traffic switch operations are exempt from lane rental assessments or liquidated damage assessments for 8 hours for each traffic switch. Perform traffic switch operations within the allowable “traffic restriction tables” as shown below.

A. A traffic switch is defined as a change in the existing (original or staged) traffic configuration which requires multiple (more than one) lane lines and/or edge lines to be relocated in a new location and the old lines to be removed either between construction stages, or maintenance of traffic stages.

Macomb TSC:KRK 3 of 6 6/3/25

Table 4: M-29 West and Eastbound Traffic Restrictions

Closure Type Start Time

End Time

M Tu W Th F Sa Su

Shoulder Closures 00:00 24:00 ∞ ∞ ∞ ∞ ∞ ∞ ∞

Single Lane Closures

00:00 05:00 ∞ ∞ ∞ ∞ ∞ ∞ ∞

05:00 21:00 0 0 0 0 0 0 0

21:00 24:00 ∞ ∞ ∞ ∞ ∞ ∞ ∞

Double Lane Closures

00:00 05:00 14 14 14 14 14 14 14

05:00 21:00 0 0 0 0 0 0 0

21:00 24:00 14 14 14 14 14 14 14

∞ = Closure is allowed, and the frequency is not limited during the project timeframe # = The number of times closures can take place during the project timeframe.

6. Maintain a minimum of one lane of traffic in each direction at all times on M-29. (And all intersecting roads and ramps, except where detoured.)

7. No more than 1 lane closure is allowed on M-29 at a time on all signalized side roads.

A. The maximum closure length is one mile unless otherwise approved by the Engineer.

8. Left turns may need to be restricted at intersections based on the engineer’s discretion.

9. Coordinate with MDOT approved lane closures, detours, and projects on M-29. If you need the project engineer’s contact to coordinate, please contact Kevin Klucens (Klucensk1@michigan.gov)

e. Traffic General.

1. For any lane open to traffic, provide a minimum lane width of 11 feet with 2 feet of shy distance on both sides unless identified otherwise on plans.

2. Do not close lanes or utilize traffic regulation sequences where work can be accomplished with a shoulder closure. Do not occupy any part of the active traffic lane with personnel or equipment when utilizing a shoulder closure. Place lane closures and traffic regulation operations only in areas as show on the plans unless otherwise directed by the Engineer.

3. Prior to shifting traffic onto shoulders or opening any lanes/shoulders and/or ramps, remove, by sweeping all accumulated debris that has collected within the shoulder and/or within the closed lane/shoulder.

4. A speed reduction will not be used.

5. Develop and submit to the Engineer an Internal Traffic Control Plan (ITCP) per subsection 104.11.B of the Standard Specifications for Construction. The requirements listed herein are the requirements for a Type A ITCP. Submit the Type A ITCP at the preconstruction mailto:Klucensk1@michigan.gov

Macomb TSC:KRK 4 of 6 6/3/25 meeting. The Engineer will have 7 calendar days to review the ITCP for approval or provide comments for revisions required to obtain approval. Include in the ITCP, at a minimum, the proposed ingress/egress locations for construction equipment and vehicles, traffic control devices that will be utilized to warn the motoring public of ingress/egress locations, and measures that will be taken to ensure compliance with the ITCP. Ensure that the ITCP minimizes conflicts between construction vehicles and motorists and maintains overall safety and mobility within the work zone. No work may begin prior to approval of the ITCP. Additional time required to obtain an approved ITCP will not be cause for delay or impact claims. All costs associated with obtaining an approved ITCP, providing and executing all parts of the approved ITCP including required traffic control devices, or resolving an incomplete or unacceptable ITCP will be borne by the Contractor.

6. Upon approval of the ITCP, complete and submit the “Lane Closure

Notification/Request Form or approved equal” to the Engineer for approval prior to the actual closure date. Submit the lane closure request 7 calendar days in advance of the lane closure for approval. This includes all shifts/shoulder/lane/ramp closures as stated per the proposal or any new lane closure requests submitted by the Contractor. The Engineer will have 4 calendar days to review the lane closure request for approval or provide comments for revisions required to obtain approval. Do not implement a lane closure prior to approval by the Engineer. In addition, notify the Engineer when the lane closure is removed or cancelled.

See Lane Closure Notification/Request Form contained in the proposal.

7. The Engineer will be responsible for notifying emergency services, transit agencies, law enforcement and schools prior to any lane closures, detours or major traffic shifts. In addition, the Contractor will be responsible for working with and complying with any coordination that is necessary with the Department and emergency services, transit agencies, law enforcement and schools. All costs associated with these coordination efforts will be considered included in the pay item “Traffic Control Inclusive”.

8. Obtain all necessary permits from local governments within areas of local jurisdiction, including noise/dust ordinance waivers when required, prior to placing construction signing on local roads.

A. The Department will reimburse permit costs in accordance with subsection

107.02.A of the Standard Specification for Construction. Adhere to all requirements made by local maintaining agencies regarding placement of traffic control devices prior to closing lanes on roadways not under MDOT jurisdiction.

9. Remove all temporary traffic control devices from MDOT right-of-way during any shut down periods unless needed for directly maintaining or channelizing traffic. No additional payment will be made for removal and/or redeployment of these devices except for in the case of an approved extension of time.

10. Cover or remove construction signing that refers to work zone speed when work at a location is planned to be inactive for a period greater than 2 days, unless otherwise specified on the plans or as directed by the Engineer.

11. Once work is initiated that includes any lane restrictions, that work must be continued daily until completed. A lack of work activity for more than 3 days will require the removal of lane closures at no expense to the Department.

Macomb TSC:KRK 5 of 6 6/3/25

f. Hot Mix Asphalt (HMA) Work.

1. Resurface all HMA milled areas the same day as the HMA cold milling operation.

2. No traffic is allowed on the HMA milled or freshly crack sealed surface, unless directed by the Engineer.

3. Provide transverse and longitudinal HMA tapers at all grade changes greater than 2 inches caused by cold milling and overlay. Place W8-1 (“BUMP”) signs in advance of transverse HMA tapers. Place W8-11 (“UNEVEN LANES”) signs in advance of longitudinal HMA tapers. Place W8-9 (“LOW SHOULDER”) signs in advance of and every mile within the shoulder drop off.

g. Traffic Control Devices. Ensure all traffic control devices are in accordance with the

MMUTCD and must meet the “acceptable” criteria as defined in the ATSSA publication entitled “Quality Guidelines for Temporary Traffic Control Devices and Features” at the time of initial deployment and after each major stage change.

1. During non-working periods, place applicable advance signs and channelizing devices at specific locations, as directed by the Engineer, at no additional cost to the Department.

2. Notify the Engineer 24 hours in advance of when traffic control devices are being delivered to the project site, to allow for initial inspection of devices to take place.

3. Remove from the project site all traffic control devices (including detour signing) no longer needed for a particular operation and equipment for construction within 14 calendar days of reopening the shoulder/lane/roadway.

4. Channelizing Devices.

A. Ensure all devices have sufficient ballast to prevent moving or tipping. If moving or tipping occurs, place additional ballast, as directed by the Engineer, at no additional cost to the Department. No more than two ballasts are allowed on each channelizing device.

B. Do not use caution tape on channelizing devices for traffic control and/or pedestrian traffic control on this project.

C. Space channelizing devices at 25 feet for tapers and 50 feet for tangents or tighter as directed by the Engineer.

5. Temporary Signs.

A. Additional W20-1 (ROAD WORK AHEAD) signs are included in the quantities to be placed on all intersecting or adjacent roads where construction activities may be encountered.

B. Fabricate, install, and remove temporary sign overlays on existing signs with the pay item for Sign, Type B, Temp, Prismatic, Furn. Attach the overlay in accordance with subsection 812.03.D.2 of the Standard Specifications for Construction.

Macomb TSC:KRK 6 of 6 6/3/25

6. Portable Changeable Message Signs (PCMS’s). Use PCMS’s to warn traffic of upcoming and changing traffic control during the life of the project. Obtain approval from the Engineer for all sign locations.

A. Install PCMS’s and make them operational a minimum of 7 calendar days prior to the start of work, unless otherwise directed by the Engineer. Messages displayed on the PCMS’s must conform to MDOT’s policy on PCMS’s. Notify the Engineer if displaying a different message than those listed below for the project.

B. Do not leave PCMS’s with a blank screen within the clear zone of any roadway at any time. Remove the PCMS or display flashing dots in each corner of the screen when there is no message to display. Update the PCMS messages at the end of each work period to reflect current traffic lane restrictions.

C. Display the following two messages greater than /within 6 days prior to work/during work/other.

D. Display the following during work/other.

h. Measurement and Payment. Payment will be in accordance with the standard specifications unless otherwise specified. No additional payment will be made for the following activities:

1. Transporting traffic control items from site to site.

2. Providing sufficient vehicles and staff to make changes as-needed on site during work.

3. Providing sufficient vehicles and staff to remove closures from the roadway.

Note: All costs associated with traffic control requirements stated herein shall be included in the pay item “Traffic Control Inclusive”.