This document is a Statement of Work (SOW) for a federal contract opportunity to repair the automatic underground fuel tank monitoring system at the East Entrance of Yellowstone National Park.

The SOW requires the replacement of a Veeder Root TLS-350 tank monitoring system with a new EVO400 ATG (or equivalent) system, including the installation of new interstitial sensors and probes, a printer, and an overfill alarm. The contractor must ensure compatibility with the existing government fuel monitoring system and provide detailed specifications if proposing an equivalent product. The contractor is responsible for proper disposal of any waste generated during the repairs. The work must comply with NFPA fire codes, OSHA regulations, and National Park Service rules. The related federal contract opportunity, Solicitation Number 140P1424Q0113, is for the "YELL AUTOMATIC TANK GUAGE REPAIRS" project with the Department of the Interior National Park Service Intermountain Region.

View the file

Other files

File Type Posted
Sol_140P1424Q0113_Amd_0001.pdf PDF
B09_-_Amendment_Q_A_0001.docx DOCX document
Sol_140P1424Q0113.pdf PDF
Attachment_2_-_WD.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Yellowstone National Park Automatic Underground Fuel Tank Monitoring system repairs

East Entrance Fuel Tank Service Projects

Requirements:

Repair the fuel tank monitoring system to operational standards.

• Remove a Veeder Root TLS-350

• Install a new EVO400 ATG (or equivalent) with printer.

• Install all new interstitial sensors and probes.

Scope:

All replacement components shall be compatible with the already installed government fuel monitoring system located at the East Entrance of Yellowstone National Park. Current system (Veeder Root).

If proposing an equivalent product to the EVO400 ATG a detailed spec sheet and explanation must be submitted with the quote. The proposed product must be compatible with all other components needed to ensure it functions the same or better than an EVO400 ATG (and the explanation/ spec sheet must clearly demonstrate this).

• Remove TLS-350 and install an EVO400 ATG (or equivalent) (install in same location).

Direct replacement.

• Install a printer compatible with the EVO400 (or proposed equivalent).

• Remove existing tank probe and gas float kits.

• Install new 4" Gas/Diesel Float Kits and new 10' tank inventory/leak detection probes.

• Remove 1 interstitial sensor and replace with new compatible sensor.

• Install an overfill alarm.

• Service Provider shall provide specific records to tanks, piping, and other information required to perform this work.

• The Service Provider shall be responsible for the proper disposal of all waste generated while conducting repairs. A Waste Manifest shall be provided for any waste that is generated, including Universal Waste, Hazardous Waste, Used Oil, etc.

Special Instructions:

Smoking, vaping, and smokeless tobacco are prohibited on the grounds of the National Park Service facilities. This Directive applies to all Service providers and their employees.

The Service provider shall confine all operations (including storage of materials) on government premises to areas authorized or approved by the NPS Contracting Officer Representative (COR).

The Service provider shall hold and save the government, its officers, and agents, free and harmless from liability of any nature occasioned by the Service provider’s performance. Working space and space available for storing materials shall be as determined by the COR. Workers are subject to the rules of the National Park Service applicable to their conduct. Execute work in such a manner as to reduce impacts with work being done by others.

Safety Codes / Certification / Licensing:

Environmental abatement work, if necessary, is to be performed by Service Provider under supervision and monitoring for the NPS COR.

The Service Provider shall comply with all codes as described above, as well as NFPA fire codes, and OSHA.

Contractor shall demonstrate their corporate experience and approach to meet all requirements.

Contractor shall provide all current and relevant licenses and/or certifications for the State of service if applicable.

If you are planning to sub-contract some or all of this work, please provide the name and address(s) of all subcontractors(s) (if applicable) and a description of their planned subcontracting effort.

Contractor shall state and/or demonstrate their ability to meet all requirements and deliverables stated in this solicitation and Statement of Work. Any additional information to further identify how the company is experienced and capable of performing the requested work is welcome.

File details come from the government source that posted it. Updated .