Attachment 1 - SOW Luna Fire Recovery Road Work.docx

DOCX document 55 KB Posted

Attached to
1120116 - Luna Fire Recovery Road Work
Solicitation number
127EAX24R0012
Issued by

About this file

This document is a Statement of Work (SOW) for the Luna Fire Recovery Road Work project, a federal contract opportunity solicited by the USDA Forest Service for the Camino Real District of the Carson National Forest in Taos County, New Mexico.

The SOW outlines the base contract and two option items for road construction and maintenance activities across four National Forest System Roads (NFSRs) totaling approximately 46 miles. The work includes road grading, ditch/drainage maintenance, culvert removal/replacement, new culvert and gate installation, cattleguard maintenance and replacement, and aggregate spot surfacing. The base contract must be completed within 120 days of the initial Notice to Proceed, and the option items within 60 days of their respective Notices to Proceed. Key contractor requirements include a Traffic Control Plan, Safety Plan, Hazardous Spill Plan, Fire Plan, and Construction Schedule to be submitted within 10 days of contract award. The contractor must have a Project Manager as key personnel. The government will conduct inspections within 5 days of notification by the contractor for each NFSR before the contractor can proceed to the next.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Statement of Work

Contents

Project3
General Information3
1.0 Scope of Work3
2.0 Background3
3.0 Technical Requirements / Tasks4
4.0 Government Furnished4
5.0 Deliverables / Schedule5
6.0 Travel5
7.0 Contractor’s Key Personnel5

Project Luna Fire Recovery Road Work

General Information

1.0 Scope of Work

This Project includes a base contract in addition to two option items. The base contract involves construction and maintenance activities such as road grading with ditch/drainage maintenance; drainage dip construction; culvert removal and replacement; new culvert installation; new gate installation; cattle guard maintenance and wingwall replacement; and cattleguard removal and replacement. The base contract involves four National Forest Service System Roads (NFSRs). The road details are as follows:

· NFSR 76

· 29.7 miles total

· Maintenance level 3, double lane: miles 0.00-9.65

· Maintenance level 2, single lane: miles 9.65-29.70

· Road needs include reconditioning (with ditch and drainage structure maintenance), cattle guard removal/replacement, cattleguard maintain and replace wingwalls, culvert installation.

· NFSR 17

· 4 miles total

· Maintenance level 2, single lane: miles 0.00-4.00

· Road needs include reconditioning (with ditch and drainage structure maintenance), culvert/fish barrier installation.

· NFSR 440

· 10.55 miles total

· Maintenance level 3, single lane: miles 0.00-10.55

· Road needs include reconditioning (with ditch and drainage structure maintenance), culvert removal and replacement.

· NFSR 440M

· 1.94 miles total

· Maintenance level 2, single lane: miles 0.00-1.94

· Road needs include reconditioning (with ditch and drainage structure maintenance), excavation and embankment (drain dip construction).

Option items #1 and #2 contain furnishing, hauling, and placing with compaction of aggregate spot surfacing along the routes listed in the base contract. Spot surfacing sections will be flagged by Forest Service representatives. All culverts, gates, and cattleguards to be removed are to be disposed of off forest land.

The contractor shall have a Traffic Control Plan submitted to the CO for approval a minimum ten (10) days prior to commencing operations. A Traffic Control Plan shall be approved prior to beginning any work, see Specifications for more details. If road closure is needed, coordination with COR is required fourteen (14) days before intended closure.

The contractor is responsible for utility locates. Damages to any utilities shall be the responsibility of the contractor. Locates are available by calling 811.

The contractor for this work shall furnish all materials, supplies, equipment, transportation, labor, quality control, and supervision necessary to complete these tasks.

2.0 Background

N/A

Contractor Requirements

3.0 Technical Requirements

All equipment shall be pressure washed prior to entering Forest Service land to ensure it is clean of seeds and other debris for weed control, subject to inspection. A 48 hour notice shall be given to COR to inspect equipment prior to mobilization onto NFS lands. No fuel storage on site is permitted. Fuel trucks must be equipped with spill containment kits and portable berms that meet all state and federal regulations.

The following video may be viewed to enhance the contractor’s knowledge of Forest Service roads and expectations for this contract.

https://www.youtube.com/watch?v=nTEfXsDqdUg.

All work in the base contract shall be accomplished within one-hundred twenty (120) days of the issuance of the initial base contract Notice-to-Proceed.

All work in the option item(s) shall be completed within 60 days of the issuance of the option item Notice-to-Proceed.

The contractor should receive CO approval of work schedule at least fourteen (14) days prior to starting work. Contractor shall notify CO seven (7) days prior to work commencing and pre-construction meeting is required.

TRAFFIC CONTROL

The Contractor shall provide, erect and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.

The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagman and operators and equipment, and other protective devices, except for special devices, shall conform with Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.

4.0 Government Furnished

None

5.0 Deliverables / Schedule

LIST OF SUBMITTALS

Submittals
Referenced by Specification No.
Objective
Due
Traffic Control Plan
FSSS 156 & Traffic Control Clause

No later than ten (10) business days after contract award

Safety Plan
H-1 Safety Clause

No later than ten (10) business days after contract award

Hazardous Spill Plan
FAR 52.223-3 & FSSS 107

No later than ten (10) business days after contract award

Fire Plan
List of Attachments

No later than ten (10) business days after contract award

Construction Schedule
52.236-15

No later than ten (10) business days after contract award

Overload Permits
Contractor’s use of Existing Roads

No later than ten (10) business days after contract award

Material Certifications
Referenced by Specification No.
Time of Government Approval After Submittal
Number of Sets
Material Certifications for Corrugated Metal Pipes
707.02
2 Weeks
1
Aggregate Degradation
703
2 weeks
1

6.0 Travel/Inspection

Mobilization/Demobilization shall be paid once for cost to mobilize and demobilize equipment to and from work site within Carson NF. Costs incurred while performing the work or traveling between locations on the Carson NF will not be paid. If a road has not been accepted by the COR prior to Contractor moving equipment to another road; the Contractor will incur any cost associated with returning equipment to road for additional items that may be required for acceptance.

The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements.

The Contractor will notify the Government when each of the four (4) NFSRs are complete and request the Government inspection. The Contractor will not move to the next NFSR until the Government is complete with their inspection. Once inspection is complete, the Government will approve or disapprove completed work. Once approved the Contractor then can move to the next NFSR. The Government will complete inspections within 5 days after notification by the Contractor. The Government shall perform all inspections in a manner that will not unnecessarily delay the work.

7.0 Contractor’s Key Personnel

452.237-74 Key Personnel (FEB 1988)

(a) The Contractor shall assign to this contract the following key personnel:

Project Manager image1.png