This document is a Statement of Work (SOW) for the construction of a Ghana Contingent-Owned Equipment (COE) Warehouse, Maintenance, and Motor Pool Facility. The overarching purpose is to build the Ghanaian Armed Forces' (GAF) capacity to prepare, deploy, and sustain effective enablers of peacekeeping forces in support of UN, AU, and ECOWAS mandated tasks.
The SOW defines requirements for a multifunctional facility that includes a two-story warehouse administration building with maintenance bay, offices, and training classrooms, as well as two large 50-vehicle warehouse sheds, a motor pool surface and container yards, and a perimeter wall with guard shack. The contractor shall plan, resource, design, supervise, and facilitate the construction of these facilities at Camp Michel in Ghana. The period of performance is 11 months from the issuance of the Notice to Proceed following a 30-day pre-construction survey. This SOW is associated with a federal contract opportunity solicitation number 19AQMM24R0160 issued by the Department of State Office of Acquisition Management.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW) Ghana Contingent-Owned Equipment (COE) Warehouse, Maintenance, and Motor Pool
Facility Construction Project June 24, 2024
1. GENERAL.
1.1. Background. The Global Peace Operations Initiative (GPOI) is a U.S. Department of State security assistance program focused on building international peacekeeping capacity worldwide in close collaboration with the U.S. Department of Defense (DOD). The GPOI program’s mission is to strengthen the effectiveness of UN and regional peace operations by enhancing partner countries’ capacities to prepare, deploy, and sustain peacekeepers and reinforcing UN and regional organizations’ performance and accountability frameworks.
State’s Bureau of Political Military Affairs, Office of Global Programs and Initiatives, Peace Operations Capacity Building Division (PM/GPI/POCB) serves as the GPOI Program Office.
1.2. GPOI Program Objectives.
▪ Support partner countries’ development of critical mission capabilities
▪ Enhance partner countries’ peace operations planning, training, and readiness competencies
▪ Enable partner countries to conduct effective operations and sustainment
▪ Reinforce United Nations (UN) and regional organizations’ performance and accountability frameworks
1.3. Project Context. This Statement of Work (SOW) defines requirements for a multifunctional facility that serves as a warehouse with maintenance bay, classrooms, and a motor pool that will provide the Ghanaian Armed Forces (GAF) with operational and sustainable infrastructure to support classroom training; vehicle maintenance, storage, and familiarization for Ghanaian leaders and soldiers; and storage large enough to account all key peacekeeping equipment used for pre-deployment training, in-mission support, and retrograde maintenance throughout the equipment’s life cycle. The GAF currently supports several United Nations peacekeeping missions with a total of over 2700 personnel to include troops, experts, staff officers, formed police units and police individuals to MINUSCA, UNIFIL, UNMISS, MINURSO, MINUSMA, MONUSCO, UNDOF, UNFICYP, and/or UNISFA. This multifunctional warehouse, maintenance bay, and motor pool facility construction project is in support of these peacekeepers.
1.4. Project Purpose. The overarching purpose of this project is to build the GAF’s capacity to prepare, deploy, and sustain effective enablers of peacekeeping forces in support of UN, AU, and ECOWAS mandated tasks. The site will facilitate training and familiarization on deployed equipment, storage, accountability, and maintenance of equipment (including in-mission equipment sustainment), and depot-level maintenance on equipment retrograded from mission areas. The activities in this SOW shall complement broader GPOI programming efforts and support U.S. Government (USG) peacekeeping policy priorities for Ghana and the region.
2. REQUIREMENTS.
2.1. Summary of Requirements. The Contractor shall plan, resource, design, supervise, and facilitate the construction of a multifunctional facility that serves as a warehouse and maintenance bay (with classrooms, offices, and training spaces, and an external motor pool,) at Camp Michel, the base of the First Battalion of Infantry of the Ghana Army, which is located at Tema in the Greater Accra Region of Ghana. The location the GAF has identified for this project is in the vicinity of 5◦43’51.4”N 0◦01’37.9”W. This specific location is currently an open field one street behind the base school and close to perimeter fencing. It is reachable by paved road which will facilitate transport of any equipment; location was selected for its proximity to the port which will facilitate shipping of deploying and re-deploying equipment.
2.2. Required Tasks. Required tasks under this SOW are as follows, with additional detail provided under the Scope of Work section below.
REQUIRED TASKS
TASK A.
Construct a two-story Warehouse Administration Building with maintenance bay, offices, and training classrooms (see drawings).
Location is at Camp Michel.
TASK B.
(Optional)
Construct two large 50-vehicle warehouse sheds (see drawings).
Location is at Camp Michel.
TASK C.
(Optional)
Construct motor pool surface, grading, and container yards, including two small overheads to house 20-foot containers (see drawings). Location is at Camp Michel.
TASK D.
(Optional)
Construct Facility Perimeter Walls and Guard Shack (see drawings).
Location is at Camp Michel.
2.2.1. Coordinate with Ghanaian officials and facilitate the procurement and delivery of equipment and supplies as required to complete all tasks and subtasks.
2.2.2. Minimize the use of wood in all construction projects due to the extreme termite problem. The use of metal is preferred for the structural component of each building.
2.2.3. All constructed buildings under this task order shall have electrical and internal installations (as specified by the site design), doors, door hardware, and paint finishes as indicated in the attached drawings. The building shall comply with the current standards of the country building codes and regulations. Doors shall be made of metal. There shall be proper ventilation and air flow to prevent dust build up on equipment.
2.2.4. Perform the clearing, grubbing, excavation, compacting and removal needed to carry out all works regarding the projects specified. The Contractor shall be responsible for any damage to the site during the execution of these activities. The excavation works shall include minor tools, machinery, dump truck transportation to authorized sites in the region, and labor.
2.2.5. Conduct tasks and subtasks concurrently and coordinate the sequencing of the enhancements with the Camp Michel Commander or the GAF’s designated representative.
2.2.6. The Contractor is responsible for providing all power requirements for construction power. However, the Contractor may coordinate with the Camp Michel Commander or the designated representatives for electricity requirements for the specified enhancements. The Contractor may utilize any existing sources of power at location if able to support the new power requirements and run electrical lines from this power source to each facility constructed by the contractor requiring electrical power.
2.2.7. The Contractor is responsible for providing all construction water requirements for construction. However, the Contractor may coordinate with the International Peace Support Operations at the General Headquarters (IPSO) Commander or the designated representatives to access base water for the construction site since there is not a reliable source nearby. This water requirement should be included in their technical proposal.
2.2.8. Provide recommended solutions for all tasks and subtasks in their technical proposal.
2.2.9. The Contractor should include all the costs of the materials, labor, transportation, and materials testing that will be needed to complete the project and comply with all the specifications stated in this document.
2.3. General Specifications. All work shall be carried out in strict compliance with all contract clauses and these technical specifications. In the event the Contractor discovers discrepancies contained in the various design/ technical documents, the Contractor must immediately notify the Contracting Officer Representative (COR) before taking any other action.
2.3.1. Quantities. This contract is based on a lump sum priced solicitation. Any quantities indicated in the specifications and drawings are for reference only and the Contractor is responsible for providing quantities needed to complete the work, without any price adjustment after award.
2.3.2. Trials and Tests.
2.3.2.1. Materials, permanent equipment, its accessories, and other elements destined to the work, shall be subject to trials and tests necessary to verify their compliance with specifications, properties, and characteristics, in accordance with permitted requirements and tolerances, in line with the use for which they have been intended. Materials, equipment, accessories, or elements that have not been accepted by the COR, shall be withdrawn from the work site or replaced, at Contractor’s cost.
2.3.2.2. Laboratory tests can be carried out, according to the specific case, at the work site or in laboratories previously authorized by the COR. Materials that bear quality certificates issued by ISO or its equivalent do not need to be routinely tested.
Costs of laboratory trials and tests shall be the responsibility of the Contractor. The COR shall be able to direct special trials and tests at any time if needed to clarify the quality of any item.
2.3.3. Work Execution.
2.3.3.1. The construction program shall be carried out in a planned and progressive manner. Activities shall be sequentially planned by the Contractor, and that plan shall be approved by the COR prior to commencement of the project. No work shall be initiated that contradicts the project plan. No work shall be performed without necessary protection from the elements. No work shall be performed that creates a safety hazard or creates unnecessary risk of damage to other work elements. Any change to the work plan must be approved by the COR.
2.3.3.2. Contractor shall be responsible for maintaining quality of work by following proper operation procedures in construction.
2.3.3.3. Throughout the different stages of construction work, Contractor may be required to obtain approval from the COR to continue with subsequent stages of construction based on their work plan. Before receiving approval to continue through various stages of work, as directed, samples of completed work may be inspected or tested to verify the quality of the work.
2.3.3.4. All work shall be detailed with the date of performance and delivery. The Contractor shall submit a baseline schedule for approval by the COR prior to the Notice to Proceed. Progress schedule updates shall be submitted monthly as part of the pay requisition by the contractor to the Government. All schedules will be subjected to review by the COR and by Government technical staff.
2.3.4. Cost of the Project. The Contractor should include all costs of the materials, labor, transportation, and materials testing that will be needed to complete the project and comply with all the specifications stated in this document.
2.3.5. Industrial Safety, Occupational Health, and Environmental Management.
2.3.5.1. The Contractor shall maintain a safe and healthy work environment during all work shifts in all construction areas and in construction yard. In addition, the contractor will observe all current local workforce safety laws and regulations as published by “Ministry of Labor” for the protection of employees and the general public on or near the work site who could be affected by the execution of the job directly or indirectly. For any work executed on heights its mandatory to comply with the proper Ghanaian standard or regulation. All vertical construction platforms and scaffolds shall be constructed and maintained in accordance with standards which all required kick plates, safety rails and tie off points. All construction personnel working at elevations more than 2 meters above the floor or ground shall be tied off to structural members and/or to properly anchored and rated safety lines. All electrical equipment shall be locked and tagged in the off position prior to working in potentially energized enclosures and on potentially energized electrical transmission systems.
2.3.5.2. For all confined space entrances installed (e.g. sewer manholes, electrical manholes, etc.) the contractor shall conduct services in accordance with regulations.
The contractor shall provide training for staff on confined space entrance/exit procedures along with all retrieval, ventilation and personal protective equipment required.
2.3.5.3. Respective to all projects, the Contractor shall adhere to safe environmental protection operations in the performance of this contract. All Contractor and Sub-contractor provided vehicles and equipment shall follow the safety requirements and shall be maintained in good working order and shall be used only in those construction activities for which they were designed in accordance with manufacturer recommendations.
2.3.6. Subcontractors.
2.3.6.1. Subcontractors shall be able to demonstrate proper training, experience and knowledge of the proper designs/drawings and building techniques to satisfy the United States Government or its representative. The contractor is responsible for any substandard or improper construction done by a subcontractor. It is incumbent on the Contractor to lay out specifications and job site rules and to properly supervise the subcontractors and to make whatever arrangements for indemnification are suitable between the parties concerning faulty work. The Contractor shall provide the following information:
2.3.6.1.1. A list of the names, addresses, and telephone numbers of all subcontractors and all principal materials suppliers to be used on the project, clearly indicating what portions of the work shall be performed by them. This list shall be presented in sufficient detail to indicate which work shall be performed by the Contractor work force and equipment, and the work which shall be performed by subcontractor work force and equipment. For the Sub-contractors identified, provide documentation that demonstrates their experience relevant to the works planned to be assigned to them under the respective subcontracts.
2.3.6.1.2. In accordance with DOSAR 652.242-73 AUTHORIZATION AND PERFORMANCE (AUG 1999) provide written certification that authorization to operate and do business in the country in which this contract shall be performed, has been obtained.
2.3.7. Security.
2.3.7.1. The Contractor shall maintain continuous coordination and constant communication with the COR. The Contractor shall observe all rules and follow all directions given by the End User (Ghanaian Armed Forces) pertaining to security. The Contractor shall protect and retain responsibility for all work, workers, and secure all materials until such work and/or materials have been accepted by the Government and handed over to the end user. Materials and equipment not needed for the current day’s work shall be safely stored in the Contractor's secured construction yard located inside facility secured area and shall plan on receiving permission from the end use to locate their storage and life support areas inside the perimeter of the base. The Contractor shall ensure security and safety is maintained throughout construction process, and that the end user’s operations continue with as little impact as possible.
2.3.7.2. The Contractor shall provide all required documentation and identification for all personnel, materials, tools, equipment, and vehicles entering or exiting the area to complete all work delineated herein. All construction personnel and vehicles/equipment shall be vetted and approved per end user’s security requirements prior to entering or exiting the Project Facilities. All personnel shall wear readily visible identification and clothing that allows them to be readily distinguished as construction personnel. The Contractor shall coordinate with the End User to arrange access to all facilities by construction personnel prior to the construction period.
3. SCOPE OF WORK.
3.1. Task A. Construct a two-story Warehouse Administration Building with maintenance bay, offices, and training classrooms (see drawings in the Appendix).
3.1.1. The Contractor shall construct a two-story warehouse administration building with maintenance bay, offices, and classrooms at Camp Michel. Construction shall be located on designated Ghana government property within the perimeter of the GAF’s Camp Michel. The center of the warehouse site shall be located at 5◦43’51.4”N 0◦01’37.9”W on a large parcel of open land (see FIGURE 1). The exact location of roads and structures shall be based on the terrain and topographic analysis completed during the design survey.
3.1.2. The Contractor shall design and construct the warehouse in accordance with the layout in APPENDIX 1.2. The warehouse shall be a double-story structure with storage areas, a maintenance bay, workshop/welding room, communications workshop/storage, secure armory/storage space, climate-controlled rooms 1-2, hazardous materials storage space, break area with kitchen, classrooms/ staging rooms 1-4, offices/workstations 1-6 with break room, and latrines 1-2.
3.1.3. Per APPENDIX 1.2, the ground level of the double-story structure will have the maintenance bay and packing/inventory workspace, two large storage areas (communications, heavy engineering equipment), workshop/welding room, secure armory/storage space, climate-controlled rooms 1-2, hazardous materials storage space, reception area, and break area with kitchen and WC.
3.1.4. The upper level of the double-story structure will have classrooms 1-2, a computer laboratory, an executive conference room, offices/workstations 1-17, male and female water closets 1-2, individual office latrines 1-2, and storage closet.
3.1.5. Foundation. Building foundation, skirt, and floor will be per specifications described in APPENDIX 1 and the Space Schedule described in FIGURE 2. The building foundation shall be continuous beam type and be made of reinforced 25MPa concrete in size of 25 cm x 60 cm in sectional dimensions. The contractor shall also
3.1.6. Building Site Drainage. The Contractor shall construct a drainage channel around the entire warehouse perimeter. The channel shall be trapezoidal, with interior channel dimensions measuring approximately 300m at the top and 250mm at the base with depth of no less than 350 mm. Concrete shall be a minimum thickness of 100 mm at all points of the channel. The concrete channel shall be sealed on all surfaces with a high-quality water proofing material to prevent sun and rain deterioration over time. The total length of channel shall be approximately 250m. The channel shall drain to a discreet drywell near the building.
3.1.7. Floors. The floors shall be per the Space Schedule described in FIGURE 2. The Contractor shall install a vapor barrier directly below the foundation slab.
3.1.8. Walls. Walls shall be constructed with solid CMU concrete blocks (reinforced with rebar, as necessary) with a minimum strength of 13.8 MPa (2,000 PSI) throughout the main office and classroom areas, including the first story of the warehouse area. Those walls shall be plastered, primed, and painted with water-based acrylic paint. Interior surfaces shall also be plastered, primed, and painted with water-based acrylic paint unless other specified. The walls of the second story open area of the warehouse and maintenance bays shall be constructed with an insulated metal or polymer-based panel design that will maximize cooling efficiency for Accra’s hot tropical climate.
3.1.9. Latrine walls shall be tiled and sealed up to the ceiling. The Contractor shall provide a solution in their technical proposal for the latrines using standard stall dimensions which provide an adequate quantity of stalls within the building and room dimensions.
The solution shall ensure separate male and female rooms are designated. The female latrine does not need to include male urinals.
3.1.10. Door and Window schedule is described in FIGURE 3.
3.1.11. Roof Design. The roof shall be corrugated CI galvanized steel sheet metal and pre-painted with a minimum thickness of the 28 gauges with a roof slope as depicted. The contractor shall propose a roof support system like a King Post Truss or Fink Truss system designed to support a sloped roof and flat interior ceiling. Trusses and purlins shall be steel and welded with minimum strength and dimensions required to support the roof design depicted. Details on truss strength and dimensions shall be included in Contractors technical proposal. Metal rain gutters shall be installed along the long side of the roof with downspouts leading to open containers (provided by the Contractor) to collect rainwater. The Contractor shall provide a ventilation plan with at least (1) turbine type ventilator in each roof section. The roof shall be properly sealed to ensure birds, small critters and rodents are kept out.
3.1.12. Interior Ceiling. Interior ceiling shall be a flat design and constructed to enable interior climate control of the partitioned spaces. The warehouse areas shall be open.
Contractor shall propose a detailed ceiling plan as part of their technical proposal.
Contractor shall provide and connect ceiling fans throughout the interior. The warehouse and maintenance area shall have a series of large industrial fans like the big ass fans described here (https://bigassfans.com/powerfoil-x4/).
3.1.13. Doors. The warehouse shall have a series of exterior entrances as depicted in APPENDIX 1. Each entrance shall have a large, grated floor mat and well just outside the door to clean and collect mud prior to entry. Door schedule is described in FIGURE 3.
3.1.14. Roll-Up Doors. As depicted in Appendix 1, the contractor shall install galvanized steel (20-gauge) roll up doors throughout the facility on the ground level. The main exterior RUD shall be no less than 500 cm wide and no less 375 cm in height. The interior RUDs for each workshop shall be no less than 225 cm wide and no less than 250 cm in height.
RUDs shall be manually operated.
3.1.15. Septic System. The Contractor shall design and install a septic system. Septic tank design shall be determined by BS. Code of Practice CP302 100 (p. 56). The formula for determining the size of tank as: C=30N+400 where “C” =Capacity of tank in meters, N =Number of people in full time residence. The system shall have a capacity to accommodate the level of use based on 850 personnel. A system is depicted in Figure 4 below; however, it does not have to be as large. The contractor shall propose the liter capacity for the septic system in their technical proposal.
3.1.16. The Contractor shall provide fifteen (15) ductless wall mounted heat pump air conditioners with a minimum of 20,000 BTUs. The air conditioners shall be installed throughout the facility as follows and as depicted in red on APPENDIX 1:
3.1.16.1. Seven (7) on ground level – Workshop Welding Room, Communications Workshop, Break Area, HAZMAT storage, Climate Control Staging Room #1, Climate Control Staging Room #2, and Reception.
3.1.16.2. Eight (8) on second level – Conference rooms (x2), classrooms (x2), computer lab, planning/operations areas (x2), Commandant office.
3.1.17. Facility shall be fully lighted and automated to enable advanced internet, audio, and visual functionality in appropriate locations. At a minimum, this shall include the following core capabilities listed below. Additional details on required end-use items are included in ANNEX 1. Contractor is responsible for delivering and installing all items and capabilities to full functionality that are specified in APPENDIX 2 and included below.
3.1.17.1. High-speed wireless internet capability throughout the facility. Wireless internet shall include two separate networks: one for public/guest use and one for internal GAF staff use.
3.1.17.2. Overhead LED lighting with separate zones.
3.1.17.3. High quality central sound and speakers for projecting high quality audio in both classrooms and all conference rooms. Sound system should include separate zones.
3.1.17.4. High quality overhead projectors and screens system integrated into the design of classrooms and conference rooms.
3.1.18. The contractor shall provide dry fire protection throughout the building which includes dry powder extinguishers, CO2 extinguishers, smoke detectors, and a fire alarm.
3.1.19. The Contractor shall provide and install all furniture items specified in ANNEX 1. Chairs shall be high quality but portable style to facilitate folding/stacking for storage during more open-space events. All chairs shall be constructed with durable metal or composite materials. Folding tables shall be provided to support table seating in classrooms.
3.1.20. The contractor shall connect water for the latrines to the camp water source approximately fifty (50) meters away. Contractor shall also provide and connect two
(2) 10,000-liter water containers to back up to the main water supply supporting each ground level male and female latrines. Containers shall be mounted on a raised steel support structure.
3.1.21. The Contractor shall provide floodlights in the vicinity of the building’s exterior. To the extent possible, Contractor shall procure the lights locally so that bulbs (or bulb assemblies) can be easily repaired or replaced locally.
3.1.22. The Contractor shall propose a power solution to supply the building and its support functions. The power solution shall connect to the main camp electrical supply, but contractor shall also provide two (2) standby 150 kw three (3) phases, stationary, encased generators suitable for the size of the building which may be manually started in case of power failure. Generator package shall also include one (1) external fuel tank capable of running back-up electricity continuously to the building in the event of a main camp power outage. Generators shall also be covered by metal roofing assembly to protect them from exposure to sun and rain.
3.1.23. The Contractor shall install a power transformer in the vicinity of the site to connect to the main Camp Michel power source and main distribution box. The power transformer shall have adequate capacity to also power the Task B. Install additional distribution boxes, as required, with all applicable controllers/switches in the structure wired for electricity. Contractor shall provide recommendations for use of solar energy.
3.1.24. The Contractor shall clear the areas where the new building is to be sited and shall conduct additional building foundation preparation as required to support the new structure.
3.1.25. The Contractor shall ensure more mature, existing trees throughout the area are retained where possible and incorporated into the overall site plan. Ground vegetation may be removed, as required, to efficiently complete construction and achieve site plan requirements.
3.1.26. The Contractor shall ensure the site is well drained with final grading. Existing natural drainage should be incorporated into the overall site plan design when possible.
Additional drainage fabrication requirements (dry wells, French drains, etc.) shall be assessed during the design survey and as required, incorporated into the final site plan.
3.1.27. The Contractor shall provide heavy duty steel shelving throughout the main warehouse area and in each separate storage/workshop room. The main warehouse area will have approximately 1000 ft of shelving. Each individual room shall have approximately 20- 25 feet of shelving. Each separate storage room shall also have 2 heavy duty work benches. See Appendix 2.2 for additional shelf and workbench furnishing requirements. All workbenches and shelves shall be fully assembled (as appropriate) and installed. Contractor may fabricate shelves on site provided they meet all technical requirements in Appendix 2.2
3.1.28. The Contractor shall ensure all requirements necessary for the functionality of the maintenance bay, such as air compressor hoses lines running throughout the bay, vehicle lift, diagnostic machine area (in ground), vehicle under carriage maintenance (fluid drainage, inspection), etc.
3.1.29. The Contractor shall provide a final hard copy “Building Maintenance Handbook” in English which includes all technical specifications on equipment warranties, sources of supply, spare parts, equipment operation/maintenance, and tips for partner-nation sustainment of the site over the long term.
3.1.30. The Contractor shall design and install a prominent entry/identification sign or signs which thoughtfully describes the site’s purpose, pays tribute to the GAF, and explicitly recognizes the longstanding U.S.-Ghana peacekeeping partnership. The contractor shall work with the GAF and COR for approval of the final location(s) and design.
3.2. Task B. Construct two large 50-vehicle warehouse sheds (see drawings in the Appendix; this is an optional task).
3.2.1. The Contractor shall construct two large warehouse sheds with capacity to accommodate approximately 50 vehicles that is part of the facility at Camp Michel.
Construction shall be located on designated Ghana government property within the perimeter of the GAF’s Camp Michel. The sheds shall be located outside the warehouse which shall be located at 5◦43’51.4”N 0◦01’37.9”W, on a large parcel of open land (see FIGURE 1). The exact location shall be based on the terrain and topographic analysis completed during the design survey.
3.2.2. The Contractor shall design and construct the sheds in accordance with the layout in APPENDIX 1.3. The structure of the sheds shall be a cement slab with anchored awning/shelter and include space to shade 50 vehicles from the elements.
3.2.3. Foundation. Foundation, shelter, and floor will be per specifications described in APPENDIX 2 and the Space Schedule described in FIGURE 2. The office and tool room foundation shall be continuous beam type and be made of reinforced 25MPa concrete in size of 25 cm x 60 cm in sectional dimensions. The columns shall sit on cement posts.
3.2.4. Floors. The floors shall be per the Space Schedule described in Figure 2. The Contractor shall install a vapor barrier directly below the foundation slab.
3.2.5. Walls. There will be no walls on the two shelters.
3.2.6. Door and Window schedule for sheds is not applicable.
3.2.7. Roof Design. The roof of the shelters shall be corrugated CI galvanized steel sheet metal and pre-painted with a minimum thickness of the 28 gauges with a roof slope as depicted. The contractor shall propose a roof support system like a King Post Truss or Fink Truss system designed to support a sloped roof and flat interior ceiling. Trusses and purlins shall be steel and welded with minimum strength and dimensions required to support the roof design depicted. Details on truss strength and dimensions shall be included in Contractors technical proposal. Metal rain gutters shall be installed along the long side of the roof with downspouts leading to open containers (provided by the
Contractor) to collect rainwater. The contractor shall propose a ventilation plan and install at least one (1) turbine type ventilator in each roof section. The roof shall be properly sealed to ensure birds, small critters and rodents are kept out.
3.2.8. The Contractor shall install overhead LED lighting with separate zones.
3.2.9. The contractor shall provide dry fire protection throughout the shelters which includes dry powder extinguishers, CO2 extinguishers, smoke detectors, and a fire alarm.
3.2.10. The Contractor shall propose a power solution to supply the shelters within it and its support functions. The power solution shall connect to the main camp electrical supply, but contractor shall also provide (2) standby 150 kw three (3) phases, stationary, encased generators suitable for the size of the building which may be manually started in case of power failure. Generator package shall also include one (1) external fuel tank capable of running back-up electricity continuously to the building in the event of a main camp power outage. Generators shall also be covered by metal roofing assembly to protect them from exposure to sun and rain.
3.2.11. The Contractor shall connect to the power transformer installed in Section 3.1.23 above and connected to the main Camp Michel power source and main distribution box. Install additional distribution boxes, as required, with all applicable controllers/switches in the structure wired for electricity.
3.2.12. The Contractor shall clear the areas where the new shelters are to be sited and shall conduct additional building foundation preparation as required to support the new structure.
3.2.13. The Contractor shall provide floodlights in the vicinity of the building’s exterior. To the extent possible, Contractor shall procure the lights locally so that bulbs (or bulb assemblies) can be easily repaired or replaced locally.
3.2.14. The Contractor shall ensure the site is well drained with final grading. Existing natural drainage should be incorporated into the overall site plan design when possible.
Additional drainage fabrication requirements (dry wells, French drains, etc.) shall be assessed during the design survey and as required, incorporated into the final site plan.
3.2.15. The Contractor shall ensure more mature, existing trees throughout the area are retained where possible and incorporated into the overall site plan when possible.
Ground vegetation may be removed, as required, to efficiently complete construction and achieve site plan requirements.
3.2.16. The Contractor shall provide a final hard copy “Vehicle Warehouse Shed Handbook” which includes all technical specifications on equipment warranties, sources of supply, spare parts, equipment operation/maintenance, and tips for partner-nation sustainment of the site over the long term.
3.2.17. The Contractor shall design and install a prominent entry/identification sign or signs which thoughtfully describes the site’s purpose, pays tribute to the GAF, and explicitly recognizes the longstanding U.S.-Ghana peacekeeping partnership. The contractor shall work with the GAF and COR for approval of the final location(s) and design.
3.3. Task C. Construct motor pool surface, grading, and container yards, including two small overheads to house 20-foot containers (see drawings in Appendix; this is an optional task).
3.3.1. The Contractor shall construct a motor pool that is part of the multipurpose warehouse facility at Camp Michel. Construction shall be located on designated Ghana government property within the perimeter of the GAF’s Camp Michel. The motor pool shall be located outside the warehouse which shall be located at 5◦43’51.4”N 0◦01’37.9”W, on a large parcel of open land (see FIGURE 1). The exact location shall be based on the terrain and topographic analysis completed during the design survey.
3.3.2. The Contractor shall design and construct the motor pool in accordance with the layout in APPENDIX 2. The structure of the motor pool surface, container yard, and two overhead shelters shall be cement slabs with anchored awnings/shelters.
3.3.3. Foundation. Building foundation, shelter, and floor will be per specifications described in APPENDIX 2 and the Space Schedule described in FIGURE 2. The two small shelter foundations shall be continuous beam type and be made of reinforced 25MPa concrete in size of 25 cm x 60 cm in sectional dimensions. The columns shall sit on cement posts.
3.3.4. Floors. The floors shall be per the Space Schedule described in Figure 2. The Contractor shall install a vapor barrier directly below the foundation slab.
3.3.5. Roof Design. The roof of the two small shelters shall be corrugated CI galvanized steel sheet metal and pre-painted with a minimum thickness of the 28 gauges with a roof slope as depicted. The contractor shall propose a roof support system like a King Post Truss or Fink Truss system designed to support a sloped roof and flat interior ceiling. Trusses and purlins shall be steel and welded with minimum strength and dimensions required to support the roof design depicted. Details on truss strength and dimensions shall be included in Contractors technical proposal. Metal rain gutters shall be installed along the long side of the roof with downspouts leading to open containers (provided by the Contractor) to collect rainwater. The contractor shall propose a ventilation plan and install at least one (1) turbine type ventilator in each roof section.
The roof shall be properly sealed to ensure birds, small critters and rodents are kept out.
3.3.6. The Contractor shall install overhead LED lighting with separate zones.
3.3.7. The contractor shall provide dry fire protection throughout the building which includes dry powder extinguishers, CO2 extinguishers, smoke detectors, and a fire alarm.
3.3.8. The Contractor shall clear the areas where the new motor pool, container yard, and small shelters are to be sited and shall conduct additional building foundation preparation as required to support the new structures.
3.3.9. The Contractor shall provide floodlights in the vicinity of the shelters’ exterior.
To the extent possible, Contractor shall procure the lights locally so that bulbs (or bulb assemblies) can be easily repaired or replaced locally.
3.3.10. The Contractor shall ensure the site is well drained with final grading. Existing natural drainage should be incorporated into the overall site plan design when possible.
Additional drainage fabrication requirements (dry wells, French drains, etc.) shall be assessed during the design survey and as required, incorporated into the final site plan.
3.3.11. The Contractor shall ensure more mature, existing trees throughout the area are retained where possible and incorporated into the overall site plan when possible.
Ground vegetation may be removed, as required, to efficiently complete construction and achieve site plan requirements.
3.3.12. The Contractor shall provide a final hard copy “Motor Pool Handbook” which includes all technical specifications on equipment warranties, sources of supply, spare parts, equipment operation/maintenance, and tips for partner-nation sustainment of the site over the long term.
3.4. T ask D. Construct Facility Perimeter Walls and Guard Shack (see drawings in the Appendix;
this is an optional task).
3.4.1. The Contractor shall construct a perimeter wall that runs the perimeter of the facility and a guard shack that facilitates a 360-degree view of the facility at Camp Michel. Construction shall be located on designated Ghana government property within the perimeter of the GAF’s Camp Michel. The wall will circle the center of the warehouse site located at 5◦43’51.4”N 0◦01’37.9”W on a large parcel of open land (see FIGURE 1).
The exact location of roads and structures shall be based on the terrain and topographic analysis completed during the design survey.
3.4.2. The Contractor shall design and construct the wall and guard shack in accordance with the layout in APPENDIX 1.1.
3.4.3. Foundation. Guard shack foundation, skirt, and floor will be per specifications described in APPENDIX 1 and the Space Schedule described in FIGURE 2. The building foundation shall be continuous beam type and be made of reinforced 25MPa concrete in size of 25 cm x 60 cm in sectional dimensions. The contractor shall also
3.4.4. Building Site Drainage. The Contractor shall construct a drainage channel around the entire wall perimeter. The channel shall be trapezoidal, with interior channel dimensions measuring approximately 300m at the top and 250mm at the base with depth of no less than 350 mm. Concrete shall be a minimum thickness of 100 mm at all points of the channel. The concrete channel shall be sealed on all surfaces with a high-quality water proofing material to prevent sun and rain deterioration over time. The total length of channel shall be approximately 250m. The channel shall drain to a discreet drywell near the building.
3.4.5. Floors. The floors shall be per the Space Schedule described in FIGURE 2. The Contractor shall install a vapor barrier directly below the foundation slab.
3.4.6. Walls. Walls shall be constructed with solid CMU concrete blocks (reinforced with rebar, as necessary) with a minimum strength of 13.8 MPa (2,000 PSI) throughout the main office and classroom areas, including the first story of the warehouse area.
Those walls shall be plastered, primed, and painted with water-based acrylic paint.
Interior surfaces shall also be plastered, primed, and painted with water-based acrylic paint unless other specified. The walls of the second story open area of the warehouse and maintenance bays shall be constructed with an insulated metal or polymer-based panel design that will maximize cooling efficiency for Accra’s hot tropical climate.
3.4.7. Door and Window schedule of guard shack is described in FIGURE 3.
3.4.8. Roof Design. The roof of guard shack shall be corrugated CI galvanized steel sheet metal and pre-painted with a minimum thickness of the 28 gauges with a roof slope as depicted. The contractor shall propose a roof support system like a King Post Truss or Fink Truss system designed to support a sloped roof and flat interior ceiling.
Trusses and purlins shall be steel and welded with minimum strength and dimensions required to support the roof design depicted. Details on truss strength and dimensions shall be included in Contractors technical proposal. Metal rain gutters shall be installed along the long side of the roof with downspouts leading to open containers (provided by the Contractor) to collect rainwater. The Contractor shall provide a ventilation plan with at least (1) turbine type ventilator in each roof section. The roof shall be properly sealed to ensure birds, small critters and rodents are kept out.
3.4.9. Interior Ceiling. Interior ceiling shall be a flat design and constructed to enable interior climate control of the partitioned spaces. Contractor shall propose a detailed ceiling plan as part of their technical proposal. Contractor shall provide and connect ceiling fans throughout the interior. The guard shack shall be climate controlled.
3.4.10. Doors. The guard shack shall have a series of exterior entrances as depicted in APPENDIX 1. Each entrance shall have a large, grated floor mat and well just outside the door to clean and collect mud prior to entry. Door schedule is described in FIGURE 3.
3.4.11. The Contractor shall provide two ductless wall mounted heat pump air conditioners with a minimum of 20,000 BTUs. The air conditioners shall be installed throughout the facility as follows and as depicted in red on APPENDIX 1:
3.4.12. Guard shack shall be fully lighted and automated to enable internet, audio, and visual functionality in appropriate locations. At a minimum, this shall include the following core capabilities listed below.
3.4.13. The contractor shall provide dry fire protection throughout the guard shack which includes dry powder extinguishers, CO2 extinguishers, smoke detectors, and a fire alarm.
3.4.14. The Contractor shall provide floodlights in the vicinity of the building’s exterior.
To the extent possible, Contractor shall procure the lights locally so that bulbs (or bulb assemblies) can be easily repaired or replaced locally.
3.4.15. The Contractor shall propose a power solution to supply the building and its support functions. The power solution shall connect to the main camp electrical supply, but contractor shall also provide two (2) standby 150 kw three (3) phases, stationary, encased generators suitable for the size of the building which may be manually started in case of power failure. Generator package shall also include one (1) external fuel tank capable of running back-up electricity continuously to the building in the event of a main camp power outage. Generators shall also be covered by metal roofing assembly to protect them from exposure to sun and rain.
3.4.16. The Contractor shall install a power transformer in the vicinity of the site to connect to the main Camp Michel power source and main distribution box. The power transformer shall have adequate capacity to also power the Task B. Install additional distribution boxes, as required, with all applicable controllers/switches in the structure wired for electricity. Contractor shall provide recommendations for use of solar energy.
3.4.17. The Contractor shall clear the areas where the new guard shack and wall are to be sited and shall conduct additional building foundation preparation as required to support the new structure.
3.4.18. The Contractor shall ensure more mature, existing trees throughout the area are retained where possible and incorporated into the overall site plan. Ground vegetation may be removed, as required, to efficiently complete construction and achieve site plan requirements.
3.4.19. The Contractor shall ensure the site is well drained with final grading. Existing natural drainage should be incorporated into the overall site plan design when possible.
Additional drainage fabrication requirements (dry wells, French drains, etc.) shall be assessed during the design survey and as required, incorporated into the final site plan.
3.4.20. The Contractor shall provide a final hard copy “Guard Shack Handbook” in English which includes all technical specifications on equipment warranties, sources of supply, spare parts, equipment operation/maintenance, and tips for partner-nation sustainment of the site over the long term.
3.4.21. The Contractor shall design and install a prominent entry/identification sign or signs which thoughtfully describes the site’s purpose, pays tribute to the GAF, and explicitly recognizes the longstanding U.S.-Ghana peacekeeping partnership. The contractor shall work with the GAF and COR for approval of the final location(s) and design.
4. EQUIPMENT AND SUPPLIES.
4.1. The Contractor shall procure and deliver all required equipment and supplies to accomplish the work as specified in each task. See Appendix 2 of SOW.
4.2. The Contractor shall obtain all required licenses to acquire, ship and deliver the supplies and equipment as specified in each task.
5. PERIOD OF PERFORMANCE.
5.1. Pre-construction Survey: 30 calendar days from the Task Order Award.
5.2. Actual Construction: 11 months from the issuance of the Notice to Proceed (NTP).
6. PLACE OF PERFORMANCE. The place of performance for Task A and Task B shall be Ghana’s Camp Michel, town of Tema, Ghana.
7. DELIVERABLES. The contractor shall provide records and reports as stated below.
7.1. Tentative Project Schedule. The contractor shall provide a tentative project schedule indicating the number of days work for each sub-task and the cumulative total days of work for projects in the Technical Proposal. This shall be submitted in a graphic or matrix format which clearly delineates the sequencing and simultaneous execution of the project sub-tasks.
7.2. Final Project Schedule. The contractor shall provide the COR and the GPOI Country Manager a Final Project Schedule stating the number of days work for each sub-task, the start and completion dates of each sub-task, and the cumulative total days of work for projects within twenty-one (21) days of completing the coordination visit/ site survey of that country.
7.3. Required Documents Prior to Issuing Notice to Proceed.
7.3.1. COR/AQM
7.3.2. Issued for Construction (IFC) drawings and specifications
7.4. Revised Project Execution Schedule. The contractor shall provide any revisions to the project execution schedule on the last day of the preceding month for the next month’s work.
7.5. Recovery Schedule. The contractor shall provide the COR with a recovery schedule if the contractor behind more than 10% on the Final Project schedule.
7.6. Receiving and Inspection Report. The Contractor shall submit a complete Receiving and Inspection Report (DS-127) for equipment and materials upon receipt. The DS-127 shall be submitted along with the invoice in which the items are billed.
7.7. Issued for Construction (IFC) Drawings and Specifications. The contractor shall furnish the COR and the CO the IFC drawings and specifications on or before the record date of Mobilization.
7.8. Weekly Construction Progress Report. The contractor shall provide a written Construction Progress Report to the COR and GPOI Country Manager regarding the status of each Subtask each week. Construction Progress Reports shall be submitted electronically no later than 1200 hours on the last business day of each week.
7.9. Serious Incident Reports (SIRs). The contractor shall submit a SIR to the COR within 24 hours of the incident’s occurrence. The criteria for SIRs shall include injury or death of any member of the labor force, injury or death of any individual due to work associated with this SOW, unscheduled or unexpected work stoppages, issues with the host nation military or law enforcement agencies, and loss or damage to equipment, materials, or supplies associated with the work of this SOW.
7.10. Property Book Report. The contractor shall submit a property inventory report to AQM, the COR, the GPOI Country Manager, each month following the award of the contract. The report shall be submitted on the last business day of each month.
7.11. Site Manager Maintenance Manual. The contractor shall provide a final hard copy “Multifunctional Building and Warehouse Handbook” as part of the request for a Certificate of Completion. Additional requirements on the content of the handbook are included in the Statement of Work.
7.12. Certificate of Completion. The contractor shall submit a request to the COR for a Certificate of Completion upon completion of all work. Upon receipt of the request, the.
contractor and COR shall schedule a date/ time for the work to be inspected. If the work has been completed in accordance with the requirements of the Statement of Work, the Department shall provide a Certificate of Completion.
7.13. Deliverables Schedule.
Description Due Date Submitted To
Contractor Inspection System No later than 21 days from award. CO & COR
Final Project Schedule No later than 21 days from completing coordination / design site survey after contract award.
CO & COR
DS-127 Receiving and Inspection Report
Upon equipment delivery and with invoicing.
Description Due Date Submitted To
Weekly Construction Progress Report.
Weekly (during construction) CO & COR
Final Project Schedule No later than 21 days from completing coordination / design site survey after contract award.
CO & COR
Revised Project Execution Schedule(s)
On the last day of the preceding month for the next months’ work
CO & COR
Recovery Schedule Weekly, when contractor is behind schedule more than…