This Statement of Work (SOW) details a contract for Stage 1 filter change maintenance at the Corrosion Control Facility on Kirtland Air Force Base. The primary objective is to replace specific air filtration components, including AIS filter blankets and panel filters with various part numbers and dimensions. The vendor is required to provide supervision, personnel, maintenance equipment, transportation, tools, and labor to remove old Stage 1 filters and install new filters in accordance with permit #1770-RV3 and manufacturer recommendations.
Key contractual requirements include adhering to specific timelines (7 days for filter replacement, 1 day for decontamination, 2 days of housekeeping), comprehensive safety protocols, and strict check-in/check-out procedures with base supervision. Work will be performed during normal duty hours (0700-1500, Monday-Friday), excluding federal holidays. The contractor must comply with base regulations, obtain necessary passes, provide safety equipment, and ensure all work meets environmental and safety standards. The contract involves performing final operational checks and potentially addressing any over-and-above repair actions as authorized by the Contracting Officer.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
status for technician repairs, or building maintenance during the scheduled filter change, the filter change will be completed at another scheduled time. This agency will schedule the filter change with the vendor when equipment is serviceable. There will be no costs to the government if no filter change is accomplished during that period.
Disposal of all old filters containing hazardous waste will be the responsibility of the government. All other parts will be removed immediately from the job site by the vendor and will be disposed of at no cost to the government.
The use of dumpsters on Kirtland AFB by the vendor is prohibited unless otherwise stated in this SOW.
Basic Services. The vendor will provide the basic services as described in this SOW.
Performance Assurance. This agency will contact Bioenvironmental once the Stage 1 filter change has been accomplished to assess the control efficiency for TSP and particulate emissions and ensure tests are within or below permitted levels as stated in permit #1770-RV3.
Vendor Check-in. Prior to the start of any filter change maintenance, part installation, parts deliveries, or site inspections, the vendor must check in with element or section supervision where maintenance is being performed.
Due to USAF mission requirements and needs of the government, there may be a delay for supervision availability. No work will be accomplished until checked in with element or section supervision. There will be no additional costs to the government.
Vendor actions at worksite. Vendor technicians will maintain control of all vendor tools and equipment at the jobsite. At no time should the government be responsible for lost, damaged, or missing tools, equipment, or parts that are property of the vendor on the jobsite. Lost tools and equipment will immediately be brought to the attention of section supervision. Any debris or trash created by the vendor or replaced parts on the jobsite will be disposed of in accordance with this SOW. Contractor personnel are only to be in their assigned areas and are not allowed in other aircraft maintenance areas without section supervision approval and/or escort.
Vendor Checkout. After finishing any filter change maintenance, part installations, part deliveries, or site inspections, the vendor must check out with section supervision. Section supervision will inspect all work performed and will ensure work has been accomplished IAW this SOW and meets requirements necessary for the government.
Any dust, dirt, debris on floor that is caused by the vendor will be swept up and cleaned before the vendor leaves and will be disposed of. Unless otherwise stated in this SOW, the contractor will remove all debris from area and will not dispose of items in the section’s trash or trash dumpsters unless inspected by section supervision. The areas will be checked at vendor checkout and vendor will not be released until area is clean.
Cardboard boxes may be disposed of in section cardboard dumpster once inspected by section supervision.
The vendor is still required to invoice through Wide Area Workflow, this receipt will assist the Sq RA to sign off WAWF invoices quickly.
The section supervisor may either require immediate rework or schedule an appointment to re accomplish any work accomplished that is not up to the standards of this SOW. This rework will be documented and sent to the squadron resource advisor and will be elevated to vendor management. There will be no additional costs to the government as any related costs will be the vendor’s responsibility.
OVER AND ABOVE (O&A). O&A is defined as work discovered during the course of the filter change maintenance, repair, or overhaul efforts that are within the scope of the contract and necessary in order to satisfactorily complete the contract. The Contractor shall complete O&A requirements In Accordance With (IAW) Defense Federal Acquisition Regulation Supplement (DFARS) 252.217-7028. PGI 217. O&A work is normally determined by the Contracting Officer as additional work within scope of the contract, but not originally listed in the contract as a defined and funded deliverable.
Authorizations for Over and Above Repair. Actions: Only the Contracting Officer (CO) can authorize over and above repair actions. The GPOC will coordinate any repair actions with the SME and the CO in order to obtain the approval to proceed. The Contractor shall submit to the CO all appropriate price justification with O&A requests, which shall include but is not limited to all estimates for each part and service effort. The Contractor shall ensure all repair actions have the documented CO approval, in writing, before initiating any repair or ordering parts. Once the authorization for repair action has been received from the CO, the Contractor shall order any required parts within two (2) business days and notify the GPOC, in writing, of the estimated arrival date of the parts. Upon the receipt of the parts, the Contractor shall perform the repair within five (5) business days. The GPOC will verify the receipt of the parts with the Contractor to ensure the repair is performed in a timely manner. Upon completion of Over and Above work, the Contractor shall demonstrate to the SME that the repairs have been completed.
The vendor will provide a list of recommended parts for future purchase. CCF will have the right to request additional quotes or request to remove items as they wish.
Stage 1 Filter Change maintenance includes final operational checks of all equipment items and booth operation.
GOVERNMENT FURNISHED PROPERTY AND SERVICE. The Government will provide electricity, water and sewer, utilities, police protection, fire protection, and emergency medical services. Any medical expenses incurred by contractor personnel shall be the responsibility of the contractor.
Damages. The contractor shall repair or replace any Government property that is properly marked, and damaged by the contractor at no additional expense to the Government.
Emergencies. In the case of an extreme emergency, safety of life or limb, the Installation Fire Chief, or the Contracting Officer, shall have the authority to order the contractor to terminate work and clear the area of personnel and equipment until further notice.
Hours of Operations. Work hours shall be during normal CCF duty hours (0700 to 1500), Monday thru Friday, excluding: Federal Holidays. Vehicles and personal are subjected to vehicle search at any time for any reason by Air Force Security Forces on duty and operating in an official capacity.
Location of Work:
Work will be performed on Kirtland AFB.
Recognized Holidays: The following holidays are recognized as Federal holidays and Government offices will not be open.
New Year’s Day Labor Day Martin Luther King Jr.’s Birthday Columbus Day President’s Day Veteran’s Day Memorial Day Thanksgiving Day Independence Day Christmas Day
Security Requirements. The contractor shall conform to all Base Regulations and Directives that pertain to security, safety, traffic, fire, and personnel clearances. To obtain passes for all work on Kirtland AFB, NM the
File details come from the government source that posted it. Updated .