Attachment_1_-_SOW_3-7-2025.pdf
PDF 229 KB Posted
- Attached to
- Delivery and Installation of 8 Office Cubicles
- Solicitation number
- 140G0125Q0094
About this file
This Statement of Work (SOW) details the U.S. Geological Survey Wetland and Aquatic Research Center's (WARC) requirement for eight modular office cubicles to be installed in Gainesville, Florida. Each 7' x 7' cubicle must be configured with specific features, including a 36" sliding glass door, two overhead locking storage units with LED lights, one 3-drawer file unit, one 2-drawer file unit, two integrated duplex receptacles, data jack faceplates, and hidden data and power raceways. The cubicle walls will be 85" high and constructed of fabric panels, with the color to be determined.
The project is governed by multiple industry and safety standards, including the Uniform Federal Accessibility Standards, National Electrical Code, NFPA Life Safety Code, and OSHA regulations. The cubicles will be installed in a 28'4" x 19'4" room constructed of CMU block at the USGS Wetland and Aquatic Research Center located at 7920 NW 71st Street in Gainesville, Florida. The contractor will be responsible for delivery and installation, and must notify the Contracting Officer of any potential delays or performance challenges.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Modular Office Cubicles
I. GENERAL INFORMATION
A. Introduction.
Our mission statement at the USGS Wetland and Aquatic Research Center (WARC) is to provide
USGS science to Florida, the Southeastern States, the U.S. Caribbean, and elsewhere in the world.
We are also leaders in seeking new and innovative ways to meet the critical need for sound, objective scientific information that can be applied to issues of local to international concern.
USGS wishes to purchase 8 modular cubicle office spaces. Each cubicle should be approximately
7’ x 7’ in size. All eight cubicles need to fit into a 28’4” x 19’4” room constructed of CMU block.
II. WORK REQUIREMENTS
A. Technical requirements (See attached Figure 1)
B. Walls between cubicles shall be 85” in height and constructed of fabric panel. Color TBD.
C. Contractor is responsible for delivery and installation.
D. Workstation Requirements:
Each workstation/cubicle shall contain one 36” sliding glass door.
2 overhead locking storage units with LED lights
1 box 3 drawer file unit
1 2 drawer file unit
2 integrated duplex receptacles per station
Data jack faceplates
Hidden data and power raceways.
III. SUPPORTING INFORMATION
A. Place of Performance:
U.S. Geological Survey
Wetland and Aquatic Research Center
7920 NW 71st Street
Gainesville, Florida 32653
B. In the event the contractor encounters difficulty in meeting performance requirements, or when it anticipates difficulty in complying with the contract delivery schedule or date, or whenever the contractor has knowledge that any actual or potential situation is delaying or threatens to delay the timely performance of this contract, the contractor shall immediately notify the Contracting Officer and Technical Liaison (to be identified in the award) in writing, giving pertinent details. This data shall be informational only in character.
C. CODES, STANDARDS, AND DEPARTMENTAL PUBLICATIONS. The following manuals, handbooks, industry standards and codes are incorporated by reference.
Uniform Federal Accessibility Standards
National Electrical Code
ICBO Uniform Building Code
NFPA, National Fire Codes
NFPA, 101 LIFE SAFETY CODE
NFPA 45
Uniform Plumbing Code
Uniform Mechanical Code
Underwriters Laboratories Fire Resistance Directory
Underwriters Laboratories Building Materials Directory
DOE Energy Conservation Standards 10 CFR Part 435
Construction Specifications Institute Standards
ANSI/AIHA Z9.5 2003
DOE Energy Conservation Standards 10 CFR Part 435
OSHA 29CFR 1910
All state, Federal and local building codes and requirements
Figure 1. Floor plan rough layout.
Figure 2. Conceptual design.