This is a Scope of Work document for the National Park Service Intermountain Region outlining the replacement of electrical components and exposed fuel line infrastructure at Ok-a-Beh Marina in Bighorn Canyon National Recreation Area, located in Fort Smith, Montana. The project (PMIS 308539) addresses repeated failures and safety concerns with the existing fuel system that serves as the only fueling capability on Bighorn Reservoir.
The contractor shall furnish all labor, supervision, materials, equipment, and tools necessary to complete the following primary tasks: mobilization and coordination with the NPS Project Manager and Crow Tribe concession operator; removal and decommissioning of existing electrical components and approximately 75 linear feet of flexible fuel piping; installation of new fuel system electrical components including an Automatic Tank Gauge (ATG), leak detection probe, remote communication unit, and electrical disconnect sleeve; installation of approximately 130 linear feet of marina-grade, UL-listed fuel piping with two fuel line disconnects; and testing and commissioning of all systems for proper functionality. Deliverables include a fully operational fuel system with installed components, successful system testing and commissioning, and final NPS acceptance. All work must comply with National Park Service standards, OSHA requirements, applicable federal and state electrical and fuel system codes, manufacturer specifications, and DOI safety and environmental requirements. Work scheduling shall minimize disruption to marina operations and visitor access, with site restoration to original or improved condition required upon completion.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P1426Q0050_Amd_0001.pdf | ||
| Attachment_3_-_Limitations_on_Subcontracting_Report.xlsx | XLSX spreadsheet | |
| Sol_140P1426Q0050.pdf | ||
| Attachment_2_-_DOL_Wage_Determination.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BIGHORN CANYON
NATIONAL RECREATION AREA
ELECTRICAL COMPONETS AND FUEL LINE REPLACEMENT
OK-A-BEH MARINA
BICA
PMIS NO.
PROJECT SCOPE OF WORK
NATIONAL PARK SERVICE
INTERMOUNTAIN REGION
JANUARY 2026
THIS PAGE INTENTIONALLY LEFT BLANK
ELECTRICAL COMPONETS AND FUEL LINE REPLACEMENT
Bighorn Canyon National Recreational Area
PMIS 308539
1. Project Title Replacement of Electrical Components and Exposed Fuel Line – Ok-a-Beh Marina Fuel System
2. Location Ok-a-Beh Marina Bighorn Canyon National Recreation Area County Road 313 Fort Smith Montana 59035
3. Background The Ok-a-Beh Marina fuel system provides the only fueling capability on Bighorn Reservoir, which is the park’s primary recreational and operational resource. The existing fuel system infrastructure has experienced repeated failures, degraded performance, and non-compliance concerns, resulting in unreliable service to visitors, concession operations, and park staff.
4. Purpose The purpose of this project is to replace critical electrical monitoring components and above-ground fuel piping to restore reliable fuel delivery, improve safety, and bring the system into compliance with applicable codes and standards.
5. Scope of Work The contractor shall furnish all labor, supervision, materials, equipment, tools, transportation, and incidentals necessary to complete the following tasks:
5.1 Mobilization and Coordination
· Coordinate work activities with the NPS Project Manager and the Crow Tribe concession operator.
· Develop a work schedule that minimizes disruption to marina operations and visitor access.
· Conduct a pre-work site visit and safety briefing.
5.2 Removal and Decommissioning
· Safely decommission existing fuel system electrical components.
· Remove approximately 75 linear feet of existing flexible fuel piping from the sump to the fuel dispenser.
· Properly dispose of removed materials in accordance with environmental regulations.
5.3 Installation of Electrical Components
· Install new fuel system electrical components, including:
· Automatic Tank Gauge (ATG)
· Leak detection probe
· Remote communication unit
· Install an electrical disconnect sleeve to meet current electrical and safety code requirements.
5.4 Fuel Piping Installation
· Install approximately 130 linear feet of marina-grade, UL-listed fuel piping.
· Install two fuel line disconnects:
· One at the fuel sump
· One at the bottom of the access stairs
· Ensure all piping and fittings are properly supported, protected, and labeled.
5.5 Testing and Commissioning
· Test the fuel system for:
· Leak detection functionality
· Electrical and communication system performance
· Proper fuel flow and system operation
· Correct any deficiencies identified during testing.
5.6 Site Restoration
· Restore disturbed areas to original or improved condition.
· Remove all debris, excess materials, and equipment from the site.
6. Deliverables
· Fully installed and operational fuel system electrical components
· Installed marina-grade UL-listed fuel piping and disconnects
· Successful system testing and commissioning
· Final inspection and acceptance by the NPS Project Manager
7. Performance Standards and Acceptance
· All work shall comply with:
· National Park Service standards and policies
· OSHA requirements
· Applicable federal, state, and local electrical and fuel system codes
· Manufacturer specifications
· Work will be accepted upon successful completion of testing and final inspection by NPS.
8. Safety and Environmental Requirements
· Contractor shall comply with all DOI, NPS, and OSHA safety requirements.
· Appropriate PPE shall be worn at all times.
· Any fuel spills, releases, or hazardous conditions shall be reported immediately to NPS staff.