Schedule of Items Region 9 Phase 1 ESA’s in Support of S.111 Leases (With Options)

Deliverable
Time Frame
To COR and Forest POC
Totals
Cost
Preliminary meeting or conference call with FS
Week of July 26th, 2023

1x Phase One ESA Camp Horseshoe & Horseshoe Recreation Area

Draft

Final

August 7th, 2023

Aug 21th, 2023

1 electronic (.doc or .docx)

1 electronic (.pdf)

1x Phase One ESA Twin Lakes Recreation Area

1x Phase One ESA Lake Vesuvius Recreation Area

Contract Options (If agency has funding) – ACM and LBP Testing

Deliverable
Time Frame
To COR and Forest POC
Totals
Cost

Option 1 ACM and LBP Sampling, Testing, and Report of Findings for:

Camp Horseshoe & Horseshoe Recreation Area

Final (Include in ESA Report for specific site)

Option 2

Twin Lakes Recreation Area

Option 3

Lake Vesuvius Recreation Area