attachment-1-rfp-dot-2027-01.xlsx
XLSX spreadsheet 35 KB Posted
- Attached to
- National Electric Vehicle Infrastructure (NEVI) - Phase II State and local contract opportunity
- Solicitation number
- RFP DOT 2027-01
- Issued by
- Rockingham County, New Hampshire
About this file
This file is a Design and Installation Schedule Template for the National Electric Vehicle Infrastructure (NEVI) Phase II project administered by the New Hampshire Department of Transportation (NHDOT). The template outlines a comprehensive 19-month design and construction timeline for EV charging station installation, followed by five years of operations and maintenance. Key deliverables include utility design confirmation, construction drawings at 50%, 90%, and 100% completion stages (CD50, CD90, CD100), utility coordination, permitting, equipment procurement, construction tasks, testing and commissioning, and as-built documentation. The project is structured with clearly defined responsibilities distributed between NHDOT and the Developer/Vendor, with milestone checkpoints and approval gates throughout the process.
The schedule template incorporates four milestone payments tied to project progression: Milestone Payment 1 (10% of Design & Construction Amount) upon NHDOT design review and approval, Milestone Payment 2 upon equipment procurement completion, Milestone Payment 3 upon final acceptance, and Milestone Payment 4 (2% quarterly over five years) contingent upon meeting uptime requirements during the operations and maintenance phase. The template is presented as an example with adjustable task durations and sequencing, explicitly encouraging proposers to modify task definitions and timelines according to their specific proposals. Construction tasks outlined include standard EV infrastructure installation components such as permitting, utility transformer procurement, charging equipment procurement, electrical switchgear procurement, excavation, concrete work, electrical service installation, equipment setup, inspections, and commissioning.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| rfp-dot-2027-01.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NEVI Phase II NHDOT - NEVI Phase II Design and Installation Schedule Template <Site Address Here>
| NEVI Tasks | Task Owner | Month - 1 | Month - 2 | Month - 3 | Month - 4 | Month - 5 | Month - 6 | Month - 7 | Month - 8 | Month - 9 | Month - 10 | Month - 11 | Month - 12 | ||||||||||||||||||||||||||||||||||||
| W1 | W2 | W3 | W4 | W1 | W2 | W3 | W4 | W1 | W2 | W3 | W4 | W1 | W2 | W3 | W4 | W1 | W2 | W3 | W4 | W1 | W2 | W3 | W4 | W1 | W2 | W3 | W4 | W1 | W2 | W3 | W4 | W1 | W2 | W3 | W4 | W1 | W2 | W3 | W4 | W1 | W2 | W3 | W4 | W1 | W2 | W3 | W4 | ||
| DESIGN SCHEDULE ITEMS | |||||||||||||||||||||||||||||||||||||||||||||||||
| Receive Notice to Proceed from NHDOT | NHDOT | N | |||||||||||||||||||||||||||||||||||||||||||||||
| Delivering Project Timeline to NHDOT | Developer | D | D | D | |||||||||||||||||||||||||||||||||||||||||||||
| Utility Design to be confirmed for Primary scope of work | Developer | D | D | D | D | D | D | D | D | D | D | D | D | ||||||||||||||||||||||||||||||||||||
| Issue Subcontracts | Developer | D | |||||||||||||||||||||||||||||||||||||||||||||||
| Review & Execute Subcontracts | Developer | D | D | ||||||||||||||||||||||||||||||||||||||||||||||
| Preconstruction Tasks | Developer | D | D | D | D | D | D | D | D | D | D | D | D | D | D | D | D | D | D | D | D | ||||||||||||||||||||||||||||
| CD50 Drawings Created | Developer | D | D | D | D | D | D | D | D | D | D | D | D | D | |||||||||||||||||||||||||||||||||||
| Utility Coordination/Design | Developer | D | D | D | D | D | D | D | D | D | D | D | D | D | D | ||||||||||||||||||||||||||||||||||
| Minor Amendment/Zoning (if necessary) | Developer | D | D | D | D | D | D | D | D | D | D | D | D | D | D | ||||||||||||||||||||||||||||||||||
| NHDOT CD50 Review/Comments | NHDOT | N | N | N | |||||||||||||||||||||||||||||||||||||||||||||
| CD90 Drawings Created | Developer | D | D | ||||||||||||||||||||||||||||||||||||||||||||||
| NHDOT CD90 Review/Comments | Developer | N | N | ||||||||||||||||||||||||||||||||||||||||||||||
| CD100 Drawings Created | Developer | D | |||||||||||||||||||||||||||||||||||||||||||||||
| NHDOT Design Review/Approval | NHDOT | N | N | ||||||||||||||||||||||||||||||||||||||||||||||
| Milestone Payment 1 (10% of Design & Construction Amount ) | NHDOT | ◊ | |||||||||||||||||||||||||||||||||||||||||||||||
| Submit Long Lead Equipment List | Developer | D | |||||||||||||||||||||||||||||||||||||||||||||||
| Review Long Lead Equipment List | NHDOT | N | N | ◊ | |||||||||||||||||||||||||||||||||||||||||||||
| CONSTRUCTION SCHEDULE ITEMS | |||||||||||||||||||||||||||||||||||||||||||||||||
| Building/Electrical Permits | Developer | D | D | D | D | ||||||||||||||||||||||||||||||||||||||||||||
| Procure Utility Transformer | Developer | D | D | D | D | D | D | D | D | D | D | D | D | D | D | D | D | D | |||||||||||||||||||||||||||||||
| Procure EV Charging Equipment | Developer | D | D | D | D | D | D | D | D | D | D | D | D | D | D | D | D | ||||||||||||||||||||||||||||||||
| Procure Electrical Switchgear | Developer | D | D | D | D | D | D | D | D | D | D | D | |||||||||||||||||||||||||||||||||||||
| Review equipment invoices | NHDOT | ||||||||||||||||||||||||||||||||||||||||||||||||
| Milestone Payment 2 (Equipment Cost) | NHDOT | ||||||||||||||||||||||||||||||||||||||||||||||||
| Draft Test Plan (acceptance and integration) | Developer | D | D | ||||||||||||||||||||||||||||||||||||||||||||||
| Review Draft Test Plan (acceptance and integration) | NHDOT | N | N | ||||||||||||||||||||||||||||||||||||||||||||||
| Finalize Test Plan | Developer | D | |||||||||||||||||||||||||||||||||||||||||||||||
| Finalize Test Plan Review | NHDOT | N | |||||||||||||||||||||||||||||||||||||||||||||||
| Draft O&M plan | Developer | D | D | ||||||||||||||||||||||||||||||||||||||||||||||
| Draft O&M plan Review | NHDOT | N | N | ||||||||||||||||||||||||||||||||||||||||||||||
| Final O&M Plan | Developer | D | |||||||||||||||||||||||||||||||||||||||||||||||
| Final O&M plan review | NHDOT | N | |||||||||||||||||||||||||||||||||||||||||||||||
| Construction Tasks | Developer | ||||||||||||||||||||||||||||||||||||||||||||||||
| Mobilization | Developer | ||||||||||||||||||||||||||||||||||||||||||||||||
| Excavation/Underground Conduit Install | Developer | ||||||||||||||||||||||||||||||||||||||||||||||||
| Underground Inspections | Developer | ||||||||||||||||||||||||||||||||||||||||||||||||
| Concrete Foundations Install | Developer | ||||||||||||||||||||||||||||||||||||||||||||||||
| Backfill/Restore Site | Developer | ||||||||||||||||||||||||||||||||||||||||||||||||
| Finished Landscaping | Developer | ||||||||||||||||||||||||||||||||||||||||||||||||
| Install Electrical Service | Developer | ||||||||||||||||||||||||||||||||||||||||||||||||
| Install service conductors | Developer | ||||||||||||||||||||||||||||||||||||||||||||||||
| Set EV Charging Equipment | Developer | ||||||||||||||||||||||||||||||||||||||||||||||||
| Final Inspections | Developer | ||||||||||||||||||||||||||||||||||||||||||||||||
| Punchlist Creation | NHDOT | ||||||||||||||||||||||||||||||||||||||||||||||||
| Punchlist Completion | Developer | ||||||||||||||||||||||||||||||||||||||||||||||||
| Partial Acceptance | NHDOT | ||||||||||||||||||||||||||||||||||||||||||||||||
| EV Commissioning | Developer | ||||||||||||||||||||||||||||||||||||||||||||||||
| Draft As Built Plans | Developer | ||||||||||||||||||||||||||||||||||||||||||||||||
| Draft As Built Plans Review | NHDOT | ||||||||||||||||||||||||||||||||||||||||||||||||
| Finalize As Built Plans | Developer | ||||||||||||||||||||||||||||||||||||||||||||||||
| Finalized As Built Plans Review | NHDOT | ||||||||||||||||||||||||||||||||||||||||||||||||
| Notice of Acceptance (Final Acceptance) | NHDOT | ||||||||||||||||||||||||||||||||||||||||||||||||
| Milestone Payment 3 | NHDOT | ||||||||||||||||||||||||||||||||||||||||||||||||
| Continued Operations and Maintenance | Developer | ||||||||||||||||||||||||||||||||||||||||||||||||
| Milestone Payment 4 (2% Q4 every year when uptime requirements are met) | NHDOT |
| Legend: | |
| Milestone Payment | ◊ |
| NHDOT - NHDOT Responsibility | N |
| Developer/Vendor - Developer/Vendor Responsibility | D |
| Schedule Template Notes: |
| CD50: 50% Construction Drawings |
| CD90: 90% Construction Drawings |
| CD100: 100% Construction Drawings |
| All Design tasks included are as outlined in the RFP. Construction tasks are typical to EV installations. Proposers are encouraged to adjust task and durations per their proposal |
| All Task durations are provided as an example. Proposers are encouraged to adjust task duration per their proposal |
| End of the worksheet |