attachment-1-rfp-dot-2027-01.xlsx

XLSX spreadsheet 35 KB Posted

Attached to
National Electric Vehicle Infrastructure (NEVI) - Phase II State and local contract opportunity
Solicitation number
RFP DOT 2027-01
Issued by
Rockingham County, New Hampshire

About this file

This file is a Design and Installation Schedule Template for the National Electric Vehicle Infrastructure (NEVI) Phase II project administered by the New Hampshire Department of Transportation (NHDOT). The template outlines a comprehensive 19-month design and construction timeline for EV charging station installation, followed by five years of operations and maintenance. Key deliverables include utility design confirmation, construction drawings at 50%, 90%, and 100% completion stages (CD50, CD90, CD100), utility coordination, permitting, equipment procurement, construction tasks, testing and commissioning, and as-built documentation. The project is structured with clearly defined responsibilities distributed between NHDOT and the Developer/Vendor, with milestone checkpoints and approval gates throughout the process.

The schedule template incorporates four milestone payments tied to project progression: Milestone Payment 1 (10% of Design & Construction Amount) upon NHDOT design review and approval, Milestone Payment 2 upon equipment procurement completion, Milestone Payment 3 upon final acceptance, and Milestone Payment 4 (2% quarterly over five years) contingent upon meeting uptime requirements during the operations and maintenance phase. The template is presented as an example with adjustable task durations and sequencing, explicitly encouraging proposers to modify task definitions and timelines according to their specific proposals. Construction tasks outlined include standard EV infrastructure installation components such as permitting, utility transformer procurement, charging equipment procurement, electrical switchgear procurement, excavation, concrete work, electrical service installation, equipment setup, inspections, and commissioning.

View the file

Other files for this state and local contract opportunity

Other files attached to National Electric Vehicle Infrastructure (NEVI) - Phase II, newest first.
File Type Posted
rfp-dot-2027-01.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NEVI Phase II NHDOT - NEVI Phase II Design and Installation Schedule Template <Site Address Here>

NEVI TasksTask OwnerMonth - 1Month - 2Month - 3Month - 4Month - 5Month - 6Month - 7Month - 8Month - 9Month - 10Month - 11Month - 12
W1W2W3W4W1W2W3W4W1W2W3W4W1W2W3W4W1W2W3W4W1W2W3W4W1W2W3W4W1W2W3W4W1W2W3W4W1W2W3W4W1W2W3W4W1W2W3W4
DESIGN SCHEDULE ITEMS
Receive Notice to Proceed from NHDOTNHDOTN
Delivering Project Timeline to NHDOTDeveloperDDD
Utility Design to be confirmed for Primary scope of workDeveloperDDDDDDDDDDDD
Issue SubcontractsDeveloperD
Review & Execute SubcontractsDeveloperDD
Preconstruction TasksDeveloperDDDDDDDDDDDDDDDDDDDD
CD50 Drawings CreatedDeveloperDDDDDDDDDDDDD
Utility Coordination/DesignDeveloperDDDDDDDDDDDDDD
Minor Amendment/Zoning (if necessary)DeveloperDDDDDDDDDDDDDD
NHDOT CD50 Review/CommentsNHDOTNNN
CD90 Drawings CreatedDeveloperDD
NHDOT CD90 Review/CommentsDeveloperNN
CD100 Drawings CreatedDeveloperD
NHDOT Design Review/ApprovalNHDOTNN
Milestone Payment 1 (10% of Design & Construction Amount )NHDOT◊
Submit Long Lead Equipment ListDeveloperD
Review Long Lead Equipment ListNHDOTNN◊
CONSTRUCTION SCHEDULE ITEMS
Building/Electrical PermitsDeveloperDDDD
Procure Utility TransformerDeveloperDDDDDDDDDDDDDDDDD
Procure EV Charging EquipmentDeveloperDDDDDDDDDDDDDDDD
Procure Electrical SwitchgearDeveloperDDDDDDDDDDD
Review equipment invoicesNHDOT
Milestone Payment 2 (Equipment Cost)NHDOT
Draft Test Plan (acceptance and integration)DeveloperDD
Review Draft Test Plan (acceptance and integration)NHDOTNN
Finalize Test PlanDeveloperD
Finalize Test Plan ReviewNHDOTN
Draft O&M planDeveloperDD
Draft O&M plan ReviewNHDOTNN
Final O&M PlanDeveloperD
Final O&M plan reviewNHDOTN
Construction TasksDeveloper
MobilizationDeveloper
Excavation/Underground Conduit InstallDeveloper
Underground InspectionsDeveloper
Concrete Foundations InstallDeveloper
Backfill/Restore SiteDeveloper
Finished LandscapingDeveloper
Install Electrical ServiceDeveloper
Install service conductorsDeveloper
Set EV Charging EquipmentDeveloper
Final InspectionsDeveloper
Punchlist CreationNHDOT
Punchlist CompletionDeveloper
Partial AcceptanceNHDOT
EV CommissioningDeveloper
Draft As Built PlansDeveloper
Draft As Built Plans ReviewNHDOT
Finalize As Built PlansDeveloper
Finalized As Built Plans ReviewNHDOT
Notice of Acceptance (Final Acceptance)NHDOT
Milestone Payment 3NHDOT
Continued Operations and MaintenanceDeveloper
Milestone Payment 4 (2% Q4 every year when uptime requirements are met)NHDOT
Legend:
Milestone Payment◊
NHDOT - NHDOT ResponsibilityN
Developer/Vendor - Developer/Vendor ResponsibilityD
Schedule Template Notes:
CD50: 50% Construction Drawings
CD90: 90% Construction Drawings
CD100: 100% Construction Drawings
All Design tasks included are as outlined in the RFP. Construction tasks are typical to EV installations. Proposers are encouraged to adjust task and durations per their proposal
All Task durations are provided as an example. Proposers are encouraged to adjust task duration per their proposal
End of the worksheet