The work elements include: 1) Project Management with monthly progress reports, 2) Work Plan development, 3) Field Work execution, and 4) Draft and Final Annual Project Reports. All elements require 100% Navy acceptance as the quality standard and are reviewed and accepted by the Contracting Officer's Representative (COR). Payment for all elements is structured as a lump sum payable monthly based on percentage of completion through deliverable submission, with CPARS evaluation. Field Work specifically requires scheduled surveillance of fieldwork activities, with methods and results needing to be consistent with the PWS and contractor's Work Plans, along with submission of field work summary reports to the COR.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 1- Quality Assurance Surveillance Plan (QASP)

Work Element /

Task

Performance Standard

Acceptable Quality Level

Assessment Method

Performance Payment

Project Management − monthly progress reports

Navy acceptance of deliverable

100% Navy acceptance

Navy Review;

Acceptance by

COR

Lump sum payable monthly as a percentage of completion through submission of deliverables to the Navy; CPARS Evaluation

Work Plan Navy acceptance of deliverable

100% Navy acceptance

Navy Review;

Acceptance by

COR

Lump sum payable monthly as a percentage of completion through submission of deliverables to the Navy; CPARS Evaluation

Field Work Navy acceptance of deliverable

100% Navy acceptance

Scheduled surveillance of fieldwork. Field methods and results consistent with the PWS and contractor’s Work Plans. Field Work summary reports submitted to COR.

Navy Review;

Acceptance by COR.

Lump sum payable monthly as a percentage of completion through submission of deliverables to the Navy; CPARS Evaluation

Draft and Final Annual Project Reports

Navy acceptance of deliverable

100% Navy acceptance

Navy Review;

Acceptance by

COR

Lump sum payable monthly as a percentage of completion through submission of deliverables to the Navy; CPARS Evaluation