Security Gate System & Quarterly Preventative Maintenance Federal contract opportunity
Solicitation number
H9224025QE005
Issued by
United States Special Operations Command

About this file

This Performance Work Statement (PWS) details a security gate upgrade and preventative maintenance project for Naval Special Warfare Command at Ranges East-Camp Atterbury in Edinburgh, Indiana. The requirement involves furnishing and installing a new security gate operating system for one entrance point with specific technical requirements, including a 3/4 HP, 230V motor, maximum 45 ft gate size, and a 5-year manufacturer warranty. Additional required components include a slide, keypad, proximity reader, indoor control station, communication remote, and loop detector.

The contract includes quarterly preventative maintenance for two gates and four overhead doors, to be performed in the first month of each quarter (July, October, January, April). The period of performance spans a base year plus four option years, totaling approximately 5 years. Contractor personnel must be U.S. citizens and obtain necessary military installation access. The project requires implementing a Quality Control Plan, and the government reserves the right to perform inspections. The security gate operating system must be installed no later than 30 days after contract award, with performance standards mandating compliance with industry and safety guidelines.

View the file

Other files for this federal contract opportunity

Other files attached to Security Gate System & Quarterly Preventative Maintenance, newest first.
File Type Posted
H9224025QE005_0002.pdf PDF
Gate Pictures.pdf PDF
RFI_20250505.xlsx XLSX spreadsheet
Attachment 2 - WD 2015-4787.pdf PDF
RFQ_H9224025QE005.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Version 0 – 1/8/24

Performance Work Statement Naval Special Warfare Command

Ranges East-Camp Atterbury Security Gate Upgrade and Preventative Maintenance

1. BACKGROUND

1.1 The Security Gate at the Ranges East Camp Atterbury Site is working intermittently due to old components and no preventative maintenance (PM) being performed.

2. OBJECTIVES

2.1 The objective of this requirement is to remove and replace a security gate operating system for 1 entrance point and acquire quarterly preventative maintenance service for two gates and four overhead doors. Ranges East Camp Atterbury is requesting to have the gate operating system replaced with new and updated components as well as quarterly preventative maintenance added as option years.

3. SCOPE

3.1 The Contractor shall provide the personnel, management, materials, equipment and facilities (not otherwise provided by the Government) necessary to install and maintain a security gate operating system and associated gates along with four overhead doors.

4. REQUIREMENTS

4.1 The contractor shall furnish and install a new security gate operating system. The security gate operating system will be required to meet the following minimums:

4.1.1 3/4 HP, 230V 1 Phase

4.1.2 Max gate size: 45 ft, 1200 lbs.

4.1.3 Max duty cycle: Continuous

4.1.4 5 Year Manufacturer Warranty

4.2 Additional components required for furnish and installation:

4.2.1 Slide

4.2.2 Keypad and Proximity Reader

4.2.3 3-Button Indoor Surface Mount Station

4.2.4 1-Button Comm Remote

4.2.5 Plug-In Loop Detector

4.3 Preventative Maintenance is required to be conducted on a quarterly basis on the security gate operating system to include the associated gates as well as four overhead doors. PM is to include but not limited to:

4.3.1 Operate gates/overhead doors, both powered and manually, to inspect operation and insure proper function of all equipment.

4.3.2 Inspect all moving parts on gate(s) and operators, adjust/tighten as required.

4.3.3 Clean and lubricate gate rollers and chain or drive assembly as required per manufacturer guidelines.

4.3.4 Inspect proper function of all safety devices.

4.3.5 Replace batteries in any safety device annually. (safety edge, receivers etc.) This does not include batteries for solar systems or back-up battery systems on A/C operators.

4.3.6 Provide reports on a quarterly basis in conjunction with PM schedule. PM will need to take place on the first month of each quarter. July, October, January, April or otherwise mutually agreed upon by all parties without any impact on overall price. Coordinate with Range to schedule date of performance.

5. DELIVERABLES

Description Number PWS

Ref.

Delivery Date

Quarterly Preventative Maintenance Report

0001 4.3.6 July, October, January, April (Scheduled w/ Range)

Version 0 – 1/8/24

6. SECURITY

6.1 Contact range complex personnel for access to Range Compound at 812-526-1329.

6.2 All contractor personnel requiring on base access are required to be citizens of the United States.

6.3 Contractor must be able to obtain personnel and vehicle access to military installations. Contractor is responsible for coordinating all necessary access through the local Military Pass and Decal Office.

7. SAFETY

7.1 Nothing in the PWS, nor any Government action or failure to act in performance of the contract shall relieve the contractor of its responsibility for the safety of the contractor's personnel and property, the Government's personnel and property. Furthermore, nothing in this PSW shall relieve the contractor of its responsibility for complying with applicable Federal, State, and Local laws, ordinances, codes and regulations (including those requiring applicable licenses and permits) in connection with the performance of this contract.

8. QUALITY CONTROL

8.1 The contractor shall implement and maintain a Quality Control Plan (QCP) to ensure work performed conforms to the scope of work and meets the requirements under this PWS. The QCP shall, at a minimum provide a method for performing inspections; identifying, correcting and preventing problems/defective service; addressing customer complaints, and improving the quality of services over the life of the contract.

9. QUALITY ASSURANCE

9.1 The Government reserves the right to perform inspections and surveillance to evaluate the Contractor’s compliance to the contract terms and performance of the requirements in the PWS. The Government will make every effort to ensure that the surveillance methods used are conducted in an objective, fair, and consistent manner

10. PLACE OF PERFORMANCE

10.1 Fairbanks Street, Building 226

Edinburgh, IN 46124

11. PERIOD OF PERFORMANCE

11.1 Base Year: Day 1 – 365

Option Year 1: Day 366 -731 Option Year 2: Day 732 -1,096 Option Year 3: Day 1,096 – 1,461 Option Year 4: Day 1,461 – 1,826

11.2 Security Gate Operating System (Furnish / Installation)

NLT 30 Days after contract award date

Performance Objective

PWS

Paragraph

Performance Threshold Method of Surveillance

Performance Incentive

PRS # 1

Contractor shall perform Routine Maintenance in accordance with the timelines and standards established in this PWS.

PWS 4.3 Contractor will be in violation of performance standard if unable to demonstrate the services performed meet industry and safety standards.

COR

Observation and Validated Customer Complaint received by

COR.

Contractor responsible for rework. Any expenditures associated with rework are the responsibility of the contractor. Government will not provide additional funding for rework activities.

4. REQUIREMENTS
4.1 The contractor shall furnish and install a new security gate operating system. The security gate operating system will be required to meet the following minimums:
4.1.1 3/4 HP, 230V 1 Phase
4.1.2 Max gate size: 45 ft, 1200 lbs.
4.1.3 Max duty cycle: Continuous
4.1.4 5 Year Manufacturer Warranty
4.2 Additional components required for furnish and installation:
4.2.1 Slide
4.2.2 Keypad and Proximity Reader
4.2.3 3-Button Indoor Surface Mount Station
4.2.4 1-Button Comm Remote
4.2.5 Plug-In Loop Detector
4.3 Preventative Maintenance is required to be conducted on a quarterly basis on the security gate operating system to include the associated gates as well as four overhead doors. PM is to include but not limited to:
4.3.1 Operate gates/overhead doors, both powered and manually, to inspect operation and insure proper function of all equipment.
4.3.2 Inspect all moving parts on gate(s) and operators, adjust/tighten as required.
4.3.3 Clean and lubricate gate rollers and chain or drive assembly as required per manufacturer guidelines.
4.3.4 Inspect proper function of all safety devices.
4.3.5 Replace batteries in any safety device annually. (safety edge, receivers etc.) This does not include batteries for solar systems or back-up battery systems on A/C operators.
4.3.6 Provide reports on a quarterly basis in conjunction with PM schedule. PM will need to take place on the first month of each quarter. July, October, January, April or otherwise mutually agreed upon by all parties without any impact on overall pr...