This is a Performance Work Statement (PWS) for elevator preventive maintenance and repair services at two facilities operated by the Bureau of Reclamation's Eastern Colorado Area Office in Loveland, Colorado.
The contract covers two elevators: a passenger elevator at the Eastern Colorado Area Office (ECAO) with approximately 30 feet of travel distance and 3 stops, and a service elevator at Carter Lake Shaft House (CLSH) with approximately 190 feet of travel distance and manual stops. The contractor must provide quarterly preventive maintenance (every 90 days), service calls, emergency response, annual and five-year load testing as required, minor adjustments and repairs, and complete documentation and reporting. All labor, supervision, transportation, tools, equipment, materials, and incidentals are the contractor's responsibility; the Government provides site access only. The contractor must comply with ANSI A17.1 and A17.2, Colorado State Elevator Code, OSHA regulations, and Reclamation Safety and Health Standards, with the most stringent requirement governing.
Performance standards require a 98 percent minimum operational availability during normal working hours (Monday-Thursday, 8:00 AM to 4:00 PM, excluding Federal holidays), response to standard service calls within 24 hours, and emergency response within 3 hours. Routine repairs must be completed within 72 hours when parts are available; repairs requiring ordered parts should be completed within 10 calendar days. All technicians must possess state-required elevator mechanic licenses, have a minimum of three years of elevator maintenance experience, and comply with OSHA and Reclamation procedures. The contract period runs from October 1, 2026, through September 30, 2027, with four optional one-year renewal periods through September 30, 2031.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT (PWS)
Elevator Preventive Maintenance and Repair Services
Eastern Colorado Area Office (ECAO) and Carter Lake Shaft House (CLSH) Bureau of Reclamation – Eastern Colorado Area Office
Loveland, Colorado
1.0 BACKGROUND
The Bureau of Reclamation, Eastern Colorado Area Office (ECAO), requires elevator preventive maintenance and repair services for two elevators located in Loveland, Colorado.
The elevators are used by Reclamation personnel and authorized visitors for transportation of personnel and equipment.
Elevator locations:
Eastern Colorado Area Office (ECAO)
• Passenger elevator
• Travel distance: approximately 30 feet
• Number of stops: 3
Carter Lake Shaft House (CLSH)
• Service elevator used for maintenance personnel
• Travel distance: approximately 190 feet
• Manual stops
The Government requires a preventive maintenance program to ensure the elevators remain safe, reliable, and compliant with applicable codes and standards.
2.0 SCOPE OF WORK
The Contractor shall provide preventive maintenance, inspection, testing, and repair services necessary to maintain the elevators in safe and operational condition.
Services shall include:
• Quarterly preventive maintenance
• Service calls
• Emergency response
• Annual load testing (if required)
• Five-year load testing (if required)
• Minor adjustments and repairs
• Documentation and reporting
The Contractor shall provide all labor, supervision, transportation, tools, equipment, materials, and incidentals required to perform the work.
The Government will provide site access only.
3.0 APPLICABLE REGULATIONS AND STANDARDS
The Contractor shall comply with all applicable federal, state, and local regulations including but not limited to:
• ANSI A17.1 – Safety Code for Elevators and Escalators
• ANSI A17.2 – Guide for Inspection of Elevators
• Applicable Colorado State Elevator Code
• OSHA regulations
• Reclamation Safety and Health Standards (RSHS)
When multiple standards apply, the most stringent requirement shall govern.
4.0 TASK REQUIREMENTS
4.1 Preventive Maintenance Services
The Contractor shall perform preventive maintenance inspections quarterly (approximately every 90 days).
Maintenance shall include inspection, cleaning, lubrication, adjustment, and functional testing of elevator components to ensure safe and reliable operation.
Preventive Maintenance Checklist
At a minimum, preventive maintenance inspections shall include:
• Controller systems
• Elevator machines
• Hoist motors
• Braking systems
• Door operators and door safety edges
• Interlocks
• Guide rails and rollers
• Control panels and wiring
• Push buttons and indicator lights
• Car lighting and ventilation
• Intercom and communication systems
• Safety circuits and limit switches
• Leveling devices
• Hoist mechanisms
• Emergency alarm systems
Minor adjustments necessary for proper operation shall be completed during preventive maintenance visits.
4.2 Service Calls
Standard Service Calls
The Contractor shall respond to non-emergency service calls within 24 hours after notification by the Government.
Emergency Service Calls
Emergency service includes situations such as:
• Personnel trapped in an elevator
• Elevator failure presenting a safety hazard
The Contractor shall arrive on site within three (3) hours of notification.
Emergency services performed outside normal working hours shall be compensated according to the labor rates specified in the contract.
4.3 Repair Services
The Contractor shall perform repairs necessary to maintain safe elevator operation.
Repair Completion Time
Routine repairs shall normally be completed within 72 hours after diagnosis when required parts are available.
If parts must be ordered, the Contractor shall:
• Notify the Government within 24 hours
• Provide estimated delivery date
• Provide expected repair completion schedule
Repairs requiring ordered parts should normally be completed within ten (10) calendar days unless otherwise approved by the Contracting Officer.
Major repairs or replacement of major components require prior written approval from the Contracting Officer.
4.4 Annual Load Testing
The Contractor shall perform annual load testing when required by applicable state or local regulations.
Testing shall be conducted in accordance with:
• ANSI A17.1
• State elevator inspection requirements
Documentation and certification results shall be submitted to the Government within two (2) weeks of completion.
4.5 Five-Year Load Testing
The Contractor shall perform required five-year load testing and safety inspections in accordance with applicable regulations.
Testing documentation shall be provided to the Government within two (2) weeks of completion.
5.0 OPERATIONAL AVAILABILITY
The Contractor shall maintain elevator operational availability of 98 percent or greater during normal operating hours.
Downtime shall begin when the elevator becomes non-operational and end when normal operation is restored.
Downtime does not include:
• Scheduled preventive maintenance
• Government-directed shutdowns
• Major repairs approved by the Contracting Officer
Failure to maintain required operational availability may result in corrective action or payment deductions.
6.0 DOCUMENTATION AND REPORTING
The Contractor shall maintain a maintenance log for each elevator.
Logs shall include:
• Date of service
• Maintenance actions performed
• Components inspected
• Parts replaced
• System deficiencies identified
• Corrective actions taken
• Technician name and signature
Maintenance logs shall be available for Government review and may be maintained either in the machine room or electronically.
7.0 HOURS OF OPERATION
Normal working hours are:
Monday through Thursday
8:00 AM – 4:00 PM
Excluding Federal holidays.
Preventive maintenance visits shall be coordinated with the Government at least one day in advance.
8.0 CONTRACTOR PERSONNEL REQUIREMENTS
All elevator maintenance and repair services shall be performed by qualified elevator technicians.
Technicians must:
• Possess any state-required elevator mechanic licenses
• Have a minimum of three (3) years of elevator maintenance experience
• Be trained on the elevator equipment being serviced
• Comply with OSHA safety requirements
• Follow Reclamation Lockout/Tagout procedures
Contractor personnel shall also maintain valid state driver’s licenses.
9.0 CONTRACTOR QUALITY CONTROL
The Contractor shall implement a Quality Control Plan (QCP) to ensure contract requirements are met.
The QCP shall include:
• Inspection procedures
• Documentation procedures
• Corrective action procedures
• Methods used to ensure service quality
10.0 GOVERNMENT QUALITY ASSURANCE
The Government will monitor contractor performance through:
• Inspection of completed work
• Review of service logs
• Response time verification
• Documentation review
The Contracting Officer will designate a Quality Assurance Evaluator (QAE) to oversee contract performance.
11.0 PERFORMANCE REQUIREMENTS SUMMARY (PRS)
Task Performance Standard Monitoring Method Acceptable Quality Level
Preventive Maintenance Completed every 90 days Maintenance logs / inspection 95%
Standard Service Calls Response within 24 hours Service records 95% Emergency Response On-site within 3 hours Service records 100%
Repair Completion Routine repairs completed within required timeframe Work order review 95%
Elevator Operational Availability
Minimum 98% operational uptime Maintenance logs 98%
Maintenance Documentation Logs completed and submitted Documentation review 95%
Failure to meet performance standards may result in corrective action or payment deductions in accordance with FAR 52.212-4.
12.0 PERIOD OF PERFORMANCE
Base Year October 1, 2026 – September 30, 2027
Option Years Option Year 1: October 1, 2027 – September 30, 2028 Option Year 2: October 1, 2028 – September 30, 2029 Option Year 3: October 1, 2029 – September 30, 2030 Option Year 4: October 1, 2030 – September 30, 2031
Options may be exercised at the Government’s discretion in accordance with FAR 52.217-9.
13.0 GOVERNMENT POINTS OF CONTACT
Contracting Officer (CO) Feyna Li Acquisition Management Division feyna_li@ios.doi.gov
Quality Assurance Evaluator (QAE) William “Jeff” Cross Bureau of Reclamation Flatiron Facility Loveland, Colorado Phone: 970-461-5600
| PERFORMANCE WORK STATEMENT (PWS) |
| 1.0 BACKGROUND |
| 2.0 SCOPE OF WORK |
| 3.0 APPLICABLE REGULATIONS AND STANDARDS |
| 4.0 TASK REQUIREMENTS |
| 4.1 Preventive Maintenance Services |
| Preventive Maintenance Checklist |
| 4.2 Service Calls |
| Standard Service Calls |
| Emergency Service Calls |
| 4.3 Repair Services |
| Repair Completion Time |
| 4.4 Annual Load Testing |
| 4.5 Five-Year Load Testing |
| 5.0 OPERATIONAL AVAILABILITY |
| 6.0 DOCUMENTATION AND REPORTING |
| 7.0 HOURS OF OPERATION |
| 8.0 CONTRACTOR PERSONNEL REQUIREMENTS |
| 9.0 CONTRACTOR QUALITY CONTROL |
| 10.0 GOVERNMENT QUALITY ASSURANCE |
| 11.0 PERFORMANCE REQUIREMENTS SUMMARY (PRS) |
| 12.0 PERIOD OF PERFORMANCE |
| 13.0 GOVERNMENT POINTS OF CONTACT |