This file is a governance and project planning presentation for the MOVERS (an enterprise resource planning implementation) initiative. The document outlines the organizational structure, escalation procedures, and implementation timeline for deploying multiple software releases across fiscal years 2026 through 2028. Release 1, scheduled for March 1, 2027, includes Recruit and Core HR functionalities. Release 2, the ERP module going live July 1, 2027, encompasses General Ledger, Fixed Assets, Accounts Payable and Receivable, Inventory, Costing, Purchasing, Budget Controls, Expenses, Manufacturing, Order Management, Cash Management, Reporting, Project and Portfolio Management, Chart of Accounts, Leasing, and a custom solution to synchronize balances between MOVERS and SAMII systems. Release 3, the HCM module launching January 1, 2028, covers Payroll, Time and Labor, Compensation, Benefits, Absence Management, Talent Management, and Employee Self-Service capabilities. Release 4, also going live January 1, 2028, adds Narrative Reporting and 1099 functionality.

The governance structure establishes three decision-making bodies: an Oversight Committee responsible for executive oversight and strategic direction; a Change Control Board approving material changes to program baseline elements; and a Program Team managing day-to-day activities. Governance escalation thresholds allocate approximately 75 percent of decisions to operational level, 20 percent to tactical level, and 5 percent to strategic level. Following each release's post-implementation support period, the program will transition to Maintenance and Operations status, providing ongoing support through ticket triage via JIRA and ServiceNow, quarterly and monthly updates, and Oracle service request management.

View the file

Other files

File Type Posted
STATE 0000000496SL,2_BidTabulation.pdf PDF
MOVERS IVV RFP - Amendment 02.docx DOCX document
Attachment 2 SOW Secondary IV&V.pdf PDF
MOVERS IVV RFP.docx DOCX document
MOVERS IVV RFP - Amendment 01.docx DOCX document
Attachment 3 SOW Project Management.pdf PDF
Attachment 2 SOW Secondary IV&V - Amendment 01.pdf PDF
Attachment 4 - SOW Requirements.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Governance Structure Overview

Governance Chart Oversight Committee Deliver executive oversight, establish strategic direction, and champion the project Resolve high-impact issues Approve key project milestones and changes Ensure resource commitment Change Control Board Approve material changes to the program baseline (scope, schedule, budget, delivery) Provide recommendations to Oversight Committee for strategic decisions Program Team Oversees day-to-day project activities including managing scope, schedule, budget Manage stakeholders and project resources Escalate issues as needed

Governance Escalation Thresholds

Strategic ~5% of decisions Tactical ~20% of decisions Operational ~75% of decisions

RePlan Schedule

CY2026CY2027CY2028
FY26FY27FY28

Release 2 (ERP): GL, Fixed Assets, AP, AR, Inventory, Costing, Purchasing, Budget Ctrl, Expenses, Manufacturing, Order Management, Cash Mgmt. Reporting, PPM COA, Leasing, PPM, Custom solution to keep balances in sync between MOVERS and SAMII (FCCS or Acct Hub), MoBGT Restructure (Pending Proof of Concept Approval)

Release 3 (HCM): Payroll, Time & Labor, Comp, Benefits, Absence Mgmt, Talent, Employee Self-Service, Remaining Core HR, Knowledge Center

Release 1: Recruit, Core HR, EDMCS

Release 4: Narrative Reporting (ACFR), 1099

Go Live March 1, 2027

Go Live July 1, 2027

Go Live January 1, 2028

Go Live January 1, 2028

Maintenance & Operations (M&O) Ongoing support for Planning & Budgeting, Solicitation, Learn (MOVERS Production) including JIRA/ServiceNow Ticket Triage, Quarterly/Monthly Updates & Oracle SR Triage. Will begin for each release following the post go-live support period.

image5.png image1.png image4.jpeg