This file is a governance and project planning presentation for the MOVERS (an enterprise resource planning implementation) initiative. The document outlines the organizational structure, escalation procedures, and implementation timeline for deploying multiple software releases across fiscal years 2026 through 2028. Release 1, scheduled for March 1, 2027, includes Recruit and Core HR functionalities. Release 2, the ERP module going live July 1, 2027, encompasses General Ledger, Fixed Assets, Accounts Payable and Receivable, Inventory, Costing, Purchasing, Budget Controls, Expenses, Manufacturing, Order Management, Cash Management, Reporting, Project and Portfolio Management, Chart of Accounts, Leasing, and a custom solution to synchronize balances between MOVERS and SAMII systems. Release 3, the HCM module launching January 1, 2028, covers Payroll, Time and Labor, Compensation, Benefits, Absence Management, Talent Management, and Employee Self-Service capabilities. Release 4, also going live January 1, 2028, adds Narrative Reporting and 1099 functionality.
The governance structure establishes three decision-making bodies: an Oversight Committee responsible for executive oversight and strategic direction; a Change Control Board approving material changes to program baseline elements; and a Program Team managing day-to-day activities. Governance escalation thresholds allocate approximately 75 percent of decisions to operational level, 20 percent to tactical level, and 5 percent to strategic level. Following each release's post-implementation support period, the program will transition to Maintenance and Operations status, providing ongoing support through ticket triage via JIRA and ServiceNow, quarterly and monthly updates, and Oracle service request management.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| STATE 0000000496SL,2_BidTabulation.pdf | ||
| MOVERS IVV RFP - Amendment 02.docx | DOCX document | |
| Attachment 2 SOW Secondary IV&V.pdf | ||
| MOVERS IVV RFP.docx | DOCX document | |
| MOVERS IVV RFP - Amendment 01.docx | DOCX document | |
| Attachment 3 SOW Project Management.pdf | ||
| Attachment 2 SOW Secondary IV&V - Amendment 01.pdf | ||
| Attachment 4 - SOW Requirements.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Governance Structure Overview
Governance Chart Oversight Committee Deliver executive oversight, establish strategic direction, and champion the project Resolve high-impact issues Approve key project milestones and changes Ensure resource commitment Change Control Board Approve material changes to the program baseline (scope, schedule, budget, delivery) Provide recommendations to Oversight Committee for strategic decisions Program Team Oversees day-to-day project activities including managing scope, schedule, budget Manage stakeholders and project resources Escalate issues as needed
Governance Escalation Thresholds
Strategic ~5% of decisions Tactical ~20% of decisions Operational ~75% of decisions
RePlan Schedule
| CY2026 | CY2027 | CY2028 | ||
| FY26 | FY27 | FY28 |
Release 2 (ERP): GL, Fixed Assets, AP, AR, Inventory, Costing, Purchasing, Budget Ctrl, Expenses, Manufacturing, Order Management, Cash Mgmt. Reporting, PPM COA, Leasing, PPM, Custom solution to keep balances in sync between MOVERS and SAMII (FCCS or Acct Hub), MoBGT Restructure (Pending Proof of Concept Approval)
Release 3 (HCM): Payroll, Time & Labor, Comp, Benefits, Absence Mgmt, Talent, Employee Self-Service, Remaining Core HR, Knowledge Center
Release 1: Recruit, Core HR, EDMCS
Release 4: Narrative Reporting (ACFR), 1099
Go Live March 1, 2027
Go Live July 1, 2027
Go Live January 1, 2028
Go Live January 1, 2028
Maintenance & Operations (M&O) Ongoing support for Planning & Budgeting, Solicitation, Learn (MOVERS Production) including JIRA/ServiceNow Ticket Triage, Quarterly/Monthly Updates & Oracle SR Triage. Will begin for each release following the post go-live support period.