This solicitation is for the Marshall Dam Reconstruction project to be performed on Bureau of Land Management property in Prairie County, Montana. Key work includes dewatering, excavating, and reconstructing the existing earth dam embankment. The reconstruction will include installing a new principal spillway riser, outlet conduit, and low-level inlet structure made of precast concrete. The project will also construct either a gabion or grouted riprap stilling basin at the outlet works. The solicitation includes technical specifications describing the materials and construction methods required for the embankment zones, outlet works, and other project elements.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_04_0004.pdf | ||
| Sol_140L3624R0003_Amd_0004.pdf | ||
| Sol_140L3624R0003_Amd_0003.pdf | ||
| Amendment_03_0003.pdf | ||
| Sol_140L3624R0003_Amd_0002.pdf | ||
| Amendment_02_0002.pdf | ||
| Amendment_01_0001.pdf | ||
| Sol_140L3624R0003_Amd_0001.pdf | ||
| Attachment_2_-_Marshall_Dam_Drawing.pdf | ||
| 140L3624R0003.pdf | ||
| Attachment_8_-_SF25_Performance_Bond.pdf | ||
| Attachment_6_-_Financial_Responsibility_Required_Documentation.pdf | ||
| Attachment_5_-_Past_Performance_Questionnaire.pdf | ||
| Attachment_9_-_SF25A_Payment_Bond.pdf | ||
| Attachment_4_-_Reference_List.pdf | ||
| Attachment_7_-_SF_24_Bid_Bond.pdf | ||
| Attachment_3_-_Wage_Determination.pdf | ||
| Sol_140L3624R0003.pdf |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MARSHALL DAM RECONSTRUCTION
BUREAU OF LAND MANAGEMENT
PRAIRIE COUNTY, MONTANA
TECHNICAL SPECIFICATIONS
PREPARED FOR
BUREAU OF LAND MANAGEMENT
MILES CITY FIELD OFFICE
MONTANA STATE OFFICE
PREPARED BY
222 NORTH 32ND STREET, SUITE 700
BILLINGS, MT 59101
MARCH 2023
03-21-2023
Print Date: March 2023 Table of Contents - i Q:\26\21710-03\55Specs\_TOC_Cover_Marshall.docx
MARSHALL DAM RECONSTRUCTION
TECHNICAL SPECIFICATIONS
TABLE OF CONTENTS
DIVISION 1 - GENERAL REQUIREMENTS
01010 Summary of Work 01050 Field Engineering 01060 Permits 01150 Measurement and Payment 01200 Project Meetings 01300 Submittals 01400 Quality Control/Quality Assurance 01570 Traffic Control 01600 Material and Equipment 01700 Contract Closeout
DIVISION 2 - SITEWORK
02050 Demolition 02110 Clearing 02241 Gabions 02275 Riprap 02300 Earth Dam 02370 Geosynthetics 02724 Outlet Works 02910 Restoration and Topsoiling
DIVISION 3 - CONCRETE
03300 Cast-In-Place Concrete
DIVISION 5 - METALS
05500 Metal Fabrications
APPENDICES
APPENDIX A – Geotechnical Testing Summary
BID FORM – Bound Separately DRAWINGS – Bound Separately
GENERAL
REQUIREMENTS
MARSHALL DAM SECTION 01010
BLM SUMMARY OF WORK
Print Date: March 2023 01010-1 Q:\26\21710-03\55Specs\01010_Summary.docx
GENERAL
WORK INCLUDED:
This project will repair Marshall Dam located in Prairie County, Montana approximately 3 miles south of Mildred, MT. Major items of work at this dam include:
1. Dewater reservoir and construction area.
2. Excavate the existing dam embankment and foundation including removal of a 30-inch diameter Corrugated Metal Pipe (CMP) broken-back outlet works pipe.
3. Reconstruct the dam embankment, including:
a. Placement of compacted fill from onsite borrow sources,
b. Placement of lime amended backfill,
c. Placement of imported rock and cobbles for riprap slope protection along the upstream face,
d. Placement and compaction of imported sand and gravel for internal filter and drain features.
4. Construct precast concrete spillway riser for a new principal spillway.
5. Construct concrete encased, precast reinforced concrete pipe outlet conduit.
6. Construct precast concrete low-level inlet structure.
7. Construct gabion or grouted riprap stilling basin.
8. Excavation, fill, and grading for new auxiliary spillway.
9. Place gravel road surfacing along the crest of the dam.
10. Reclaim all disturbed areas including staging areas and temporary roads. Reclamation consists of preparation of the soil for seeding but does not include seeding.
a. Seeding of the reclaimed areas will be completed by Others.
CONTRACTOR USE OF PREMISES:
Confine operations to the site of the proposed Work or within the right-of-way or construction easements provided and shown on the drawings. Construction camps and staging areas outside the construction area must be approved by the GOVERNMENT. Obtain advance approval from the GOVERNMENT of all staging areas, excavated soil stockpile and waste areas and camp areas.
It shall be understood that the responsibility for protection and safekeeping of equipment and materials on or near the site will be entirely that of the CONTRACTOR and that no claim shall be made against the GOVERNMENT by reason of any act of an employee or trespasser whether GOVERNMENT has paid CONTRACTOR for equipment or materials in storage or not. It shall be further understood that should any occasion arise necessitating access by the GOVERNMENT to the sites occupied by these stored materials and equipment, the CONTRACTOR owning or responsible for the stored materials or equipment shall immediately remove same. No materials or equipment
Print Date: March 2023 01010-2 Q:\26\21710-03\55Specs\01010_Summary.docx may be placed upon the property of the GOVERNMENT until the GOVERNMENT has agreed to the location contemplated by the CONTRACTOR to be used for storage. CONTRACTOR is solely responsible for obtaining and shall pay all costs in connection with any additional work area, storage sites, access to the site, or temporary right-of-way, which may be required for proper completion of the Work.
PROTECTION OF EXISTING UTILITIES:
Utility service connections are generally shown on the drawings, but the CONTRACTOR is solely responsible for locating all existing underground installations, including service connections, in advance of excavating or trenching, by contacting 811 (in-state) or 1-800-424-5555 (outside of Montana) or the owners thereof. The CONTRACTOR shall use his own information and shall not rely solely upon information shown on the drawings concerning existing underground installations.
Repair all damage to existing utilities or property at CONTRACTOR's expense.
PROTECTION OF EXISTING STRUCTURES:
Where excavation will be required adjacent to existing structures, the CONTRACTOR is solely responsible to maintain the structural integrity of the existing structures. Take whatever means necessary to ensure the existing structures are not damaged. Repair all damage to the existing structures at CONTRACTOR's expense. Repair any fences destroyed during construction to the satisfaction of the Government or property owner. Unless otherwise noted on the Construction Drawings, restore all existing ditches disturbed by construction to their original size, line, and grade.
Structures located downstream of the dam shall also be protected during reservoir dewatering activities. Restore or repair to original condition roads, culverts, bridges, cattle guards and fences or any other structures damaged by the CONTRACTOR’s activities and access to the sites at no additional cost to the project.
FIELD CHECK OF EXISTING STRUCTURES:
Dimensions and elevations of existing structures and locations of existing fences, pipelines, conduits, cables, and equipment shown on the drawings were taken for the most part from available records and survey data and are not guaranteed for accuracy.
Check all dimensions and elevations of existing structures, pipelines, conduits, cables, equipment, or other existing items, both above and below ground, affected by or affecting the Work under this contract, prior to the start of construction or ordering materials and equipment affected thereby.
SITE ACCESS:
Determine the adequacy of all roads, culverts, cattle guards, and bridges used in moving or gaining access for equipment and materials to the construction site. Provide alternative methods of access, such as a temporary crossing for any equipment that exceeds the structural limits of existing facilities.
Improvements for road access including fill, culverts, and fencing to remain after project completion as approved by GOVERNMENT.
Print Date: March 2023 01010-3 Q:\26\21710-03\55Specs\01010_Summary.docx
LIVESTOCK:
The CONTRACTOR shall provide temporary fencing for excluding livestock from construction areas, excavations, trenches, etc.
CONTRACTOR shall be solely responsible for any livestock injuries or losses as a result of CONTRACTOR’s activities.
FIELD OFFICES AND SHEDS:
The CONTRACTOR is responsible for providing their own temporary field offices and storage sheds required for completion of the work. Locate these temporary structures in areas approved by the GOVERNMENT. All expenses for telephone, utilities, security and waste disposal are the responsibility of the CONTRACTOR.
REFERENCES:
References to documents, such as ASTM, shall be for the current printing.
ABBREVIATIONS:
AASHTO - American Association of State Highway and Transportation Officials ACI - American Concrete Institute ASTM - American Society for Testing and Materials AWWA – American Water Works Association GOVERNMENT - Contracting Officer OSHA - Occupational Safety and Health Act PVC - Polyvinyl Chloride RCP – Reinforced concrete pipe CMP – Corrugated Metal Pipe
PRODUCTS – NONE
Not Used.
EXECUTION – NONE
Not Used.
END OF SECTION
MARSHALL DAM SECTION 01050
BLM SURVEYING
Print Date: March 2023 01050-1 Q:\26\21710-03\55Specs\01050_Surveying.docx
PART 1 - GENERAL
WORK INCLUDED:
The CONTRACTOR is responsible to provide construction staking for horizontal and vertical alignment of the control lines, grading, and all appurtenant features of the work, including offset lines if necessary. CONTRACTOR is responsible for performing measurements and maintaining controls to complete the construction to the lines and grades shown in the Contract Documents.
GOVERNMENT has established primary control with control points adjacent to the Work as shown in the Contract Documents.
SUBMITTALS:
Survey Plan:
1. Describe work layout and survey methods.
2. Include survey schedule.
Resume
1. Engineer or surveyor responsible for supervising and directing survey work.
Control Survey Verification:
1. Accuracy check of existing primary control.
Quantity Survey Notes and Computations
1. Required for progress payments. Include notes and computations as supporting information for relevant progress payment quantities.
PRIMARY CONTROL:
As shown on the Drawings, existing control points are available for establishing work lines and grades.
The CONTRACTOR shall confirm the horizontal and vertical accuracy of the existing control.
If discrepancies are identified, resolve discrepancies with the GOVERNMENT before beginning work.
Preserve and maintain primary control points unless otherwise authorized by the
GOVERNMENT.
QUALIFICATIONS:
Surveyors: Experienced construction surveyors with a minimum of two years of experience in
Print Date: March 2023 01050-2 Q:\26\21710-03\55Specs\01050_Surveying.docx charge of construction surveys.
PRODUCTS
SURVEY MATERIALS AND EQUIPMENT:
Provide required materials and equipment for surveying work including, but not limited to, instruments, stakes, spikes, steel pins, templates, platforms, and tools.
Except as required to be incorporated in work or left in place, survey materials and equipment are, and will remain, property of the CONTRACTOR.
EXECUTION
LAYOUT OF WORK SURVEYS:
Establish lines, grades, and work layout from the primary control points.
Provide stakes, markers, and other survey controls necessary to control, check, and guide construction.
QUANTITY SURVEYS:
Where required for a progress payment, perform surveys and computations to determine quantities of work performed or placed during each payment period.
Unless specifically waived, perform quantity surveys in presence of the GOVERNMENT.
Notify the GOVERNMENT at least 24 hours before performing a quantity survey.
SURVEY REQUIREMENTS:
Minimum Alignment Staking Intervals: 50 feet on tangent and 25 feet on curves.
Minimum Slope Staking Intervals: 50 feet on tangent and 25 feet on curves, and every 10 feet in elevation.
Structures: Stake out structures before and during construction.
Blue Top Intervals for Roads: 50 feet, on tangent and 25 feet on curves.
As-builts: As required for structures and other features of work.
ACCURACY:
Degree of Accuracy:
1. Alignment of Tangents and Curves: Set within 0.1 foot.
2. Structure Points: Set within 0.01 foot, except where installation or operation considerations require tighter tolerances.
3. Blue Tops: Set within 0.1 foot.
4. Cross-Section Points: Locate within 0.1 foot, horizontally and vertically.
5. Vertical Elevation Surveys: Close within 0.05 foot times the square root of the circuit
Print Date: March 2023 01050-3 Q:\26\21710-03\55Specs\01050_Surveying.docx length in miles.
FIELD RECORDS:
Record original field notes, computations, and other survey data in fieldbooks.
Record survey data in accordance with recognized professional survey standards.
1. Notes or data not in accordance with standard formats will be rejected.
2. Illegible notes or erasures on any page of a fieldbook will be sufficient cause for rejection of part or all of fieldbook.
3. Corrections by ruling or lining our errors will be permitted.
4. Rejection of part of all of a fieldbook may necessitate resurveying.
Data and notes may be collected on electronic data collection devices.
1. Electronic files: In approved format.
2. Include both electronic files and paper copies of notes in submittals.
END OF SECTION 01050
MARSHALL DAM SECTION 01060
BLM PERMITS
Print Date: March 2023 01060-1 Q:\26\21710-03\55Specs\01060_Permits.docx
PART 1 - GENERAL
WORK INCLUDED:
Prepare, maintain, and proceed in conformity with Storm Water Discharge Permit/Storm Water Pollution Prevention Plan as required by the Montana Department of Environmental Quality. Once the CONTRACTOR prepares and submits the final permit to the GOVERNMENT, the GOVERNMENT will obtain this permit and pay all fees associated with the Storm Water Discharge Permit. During the construction of the reservoir, the CONTRACTOR is responsible for all maintenance to the pollution prevention plan. When the CONTRACTOR has completed work on the project and has been issued the final payment, the GOVERNMENT will continue maintenance on the pollution prevention plan. When all criteria have been met, the GOVERNMENT will file the Notice of Termination for the permit.
Except as otherwise noted, identify, obtain, maintain, and proceed in conformity with any and all additional required permits necessary for completion of the Work.
Any costs associated with these Permits are included as part of the Contract Price as incidental costs.
SUBMITTALS:
The CONTRACTOR shall supply to the GOVERNMENT a draft Storm Water Discharge Permit within 10 days after issuance of the Notice to Proceed. The GOVERNMENT will have 10 days to review and provide comments back to the CONTRACTOR. The CONTRACTOR then has 10 additional days to submit the final Storm Water Discharge Permit to the GOVERNMENT. Work may proceed after the final Storm Water Discharge Permit has been returned to the CONTRACTOR with an acceptance letter from the GOVERNMENT. The CONTRACTOR shall perform all compliance testing required by all permits. Submit results of compliance testing directly to the appropriate review agency. Provide copies of all results to the GOVERNMENT. Submit copies of any additional required permits to the GOVERNMENT when they are acquired.
PART 2 - PRODUCTS – NONE
Not Used.
PART 3 - EXECUTION – NONE
END OF SECTION 01060
MARSHALL DAM SECTION 01150
BLM MEASUREMENT AND PAYMENT
Print Date: March 2023 01150-1 Q:\26\21710-03\55Specs\01150_Measurement_Payment.docx
PART 1 - GENERAL
SCOPE:
The method of measurement and basis of payment is described in this section.
GENERAL:
Bid price for each item of the Contract covers all Work shown on the Drawings and required by the specifications and other Contract Documents.
All costs are included in the unit and lump-sum prices bid including all materials, equipment, supplies and appurtenances; all construction plant, equipment, and tools; and all labor and supervision necessary to fully complete the Work.
No item that is required by the Contract Documents, for the proper and successful completion of the Work, will be paid for outside of or in addition to the prices submitted in the Bid.
All work not specifically set forth as a pay item in the Bid Form is considered an incidental obligation of the CONTRACTOR, and all costs in connection therewith shall be included in the unit prices bid.
ESTIMATED QUANTITIES:
All quantities in the Price Schedule of the Bid Form or other Contract Documents, which are to be paid per field measurement, are approximate only, and are to be used only as:
1. A basis for estimating the probable cost of the Work, and
2. For the purpose of comparing Bids submitted for the Work.
Actual work performed, and materials furnished under the unit-price items for those items to be field measured may differ from the estimated quantities.
Basis of payment for work and materials will be the actual amount of work done and materials furnished to the pay lines defined in this section.
Payment will be paid at the unit price bid for listed items successfully completed according to Contract requirement.
Lump-sum items and those based on neat-line plan dimensions are not field-measured. They will be paid at neat-line or the lump-sum price bid for the items listed.
AUTHORITY:
GOVERNMENT will perform all measurements and compute quantities for payment.
GOVERNMENT will verify measurements and quantities provided by CONTRACTOR.
CONTRACTOR provides access to work areas for survey measurements, as required.
Print Date: March 2023 01150-2 Q:\26\21710-03\55Specs\01150_Measurement_Payment.docx
MEASURED QUANTITIES:
Measurement by Volume: Measured by cubic dimension using mean length, width, and height or thickness.
1. Measurement for payment of excavations upon or against which concrete or cementitious backfill is not to be placed will be limited to the lines and grades shown on the Drawings or to the most practical lines, grades, and dimensions established by the GOVERNMENT, in writing. No measurement will be made of over excavations beyond design lines and grades.
2. Fill quantities will be computed using the average-end-area method or other computation method approved of by the GOVERNMENT.
Measurement by Area: Measured by square dimension using mean length and width. Items that are measured by area will be measured parallel to the ground surface.
Linear Measurement: Measured by linear dimension at the item centerline or mean chord. Items that are measured by the lineal foot will be measured parallel to the ground surface, unless otherwise specified.
Stipulated Sum/Price Items: Measured by weight, volume, area, or linear means, or combination, as appropriate, as completed items or units of the work.
Lump-Sum Items: Will not be measured for payment. Interim measurements may be made to monitor work progress.
SCHEDULE OF VALUES:
A schedule of values or “allocation of contract price” is required for all lump sum items.
The schedule of values is used only to help assess the intermediate value of work completed for the purpose of making progress payments. The schedule of values is not considered as a commitment to prices in the event of later negotiations.
MEASUREMENT AND PAYMENT ITEMS:
Item 1 – Mobilization & Preparatory Work:
1. This item includes, but is not limited to:
a. Preparatory work and operations performed by the CONTRACTOR for work and operations that are performed or costs incurred before beginning work on the various items on the project site.
b. Providing required bonds and insurance.
c. Preparing and maintaining the project schedule.
d. Delivering and removing the contractor’s equipment, supplies, and materials; and
Print Date: March 2023 01150-3 Q:\26\21710-03\55Specs\01150_Measurement_Payment.docx final site clean-up and demobilization.
e. Preparing and securing approvals of submittals.
f. Preparing record drawings.
g. This item also includes constructing and maintaining detour road(s) and traffic control devices as necessary to provide public access through the project site on the BLM Lands Road year-round and for the duration of the project.
h. Mobilization costs for subcontracted work are also considered included.
i. Providing all other related and necessary labor, equipment, and materials to complete the work that are not accounted for in the other bid items is included in this item.
2. Measurement and payment for mobilization and preparatory work will be made at the Contract lump sum price. Progress payments for mobilization and preparatory work will be as follows:
a. 50% of the contract lump sum price will be paid at the time of the first monthly progress payment; an additional 30% will be paid when one-half of the original contract amount (excluding Mobilization) is earned. The remaining 20% will be paid at project completion on the final progress payment.
Item 2 – Topsoil Stripping & Replacement: Consists of stripping, stockpiling and replacing topsoil from all staging, borrow, excavation, embankment, and waste areas. Seeding will be completed by the GOVERNMENT. Topsoil stripping and replacement will be measured and paid at the Contract lump sum price.
Item 3 – Outlet Demolition: Includes removal of existing CMP outlet pipes and riser. This item includes removal of pipes, concrete headwalls, concrete cutoff collars, miscellaneous concrete, wire, rock, debris; protection of existing materials not designated for removal; legal disposal at off-site facilities; removal of loose material and all cleaning necessary or incidental to demolition.
Measurement will be based on acceptable demolition, cleanup and removal. Payment will be made at the Contract lump sum price.
Item 4 – Common Excavation: Consists of excavation and stockpiling or wasting as necessary to construct work in accordance with the Contract Documents. Excavation areas include outlet works area. The quantity measured for payment will be to the defined neat-lines or as otherwise directed by the GOVERNMENT. Unauthorized over-excavation will not be included in measurement for this item. Waste of materials from excavation areas that are unsuitable for embankment placement is included in this item. Payment for this work will be made at the Contract unit price per cubic yard.
Item 5 – Muck Excavation: (Field Measured). Consists of excavation and wasting, as necessary, to remove muck (saturated soil) from the area of the existing principal spillway inlet, outlet, dam foundation and the area of the construction of the riprap outlet basin. Wasting will be in areas as directed by the GOVERNMENT. Payment for this work will be made at the Contract unit price per cubic yard.
Item 6 – Compacted Embankment: Consists of loading from stockpiles or excavating from borrow areas, hauling, placing and compacting embankment in accordance with the Contract
Print Date: March 2023 01150-4 Q:\26\21710-03\55Specs\01150_Measurement_Payment.docx
Documents. Embankment areas include outlet works areas. Excavation and backfill for examination test pits is considered incidental to the price of this item. The quantity measured for payment will be to the defined neat-lines or as otherwise directed by the GOVERNMENT.
Embankment placed to compensate for unauthorized over-excavation will not be included in measurement for this item. Payment will be made at the Contract unit price per cubic yard.
Item 7 – Filter Sand: Consists of furnishing and placing filter sand material in accordance with the Contract Documents. The quantity measured for payment will be computed using the neat line dimensions shown on the plans. Payment for this work will be made at the Contract unit price per cubic yard
Item 8 – Drain Gravel: Consists of furnishing and placing drain gravel material in accordance with the Contract Documents. The quantity measured for payment will be computed using the neat line dimensions shown on the Drawings. Payment for this work will be made at the Contract unit price per cubic yard.
Item 9 – Road Gravel: Consists of furnishing and placing road gravel material in accordance with the Contract Documents. Supplying and installing geotextile filter fabric between the road gravel and subgrade is considered incidental to this item. The quantity measured for payment will be computed using the neat line dimensions shown on the Drawings. Payment for this work will be made at the Contract unit price per ton.
Item 10 – New Riprap Slope Protection: Consists of supplying from offsite sources and placing riprap on the upstream face in accordance with the Contract Documents. Measurement will be computed using the neat line dimensions shown on the Drawings. Payment for this work will be made at the Contract unit price per ton.
Item 11 – New Cobble Slope Protection: Consists of supplying from offsite sources and placing cobbles on the upstream face in accordance with the Contract Documents. Measurement will be computed using the neat line dimensions shown on the Drawings. Payment for this work will be made at the Contract unit price per ton.
Item 12 – Outlet Basin: CONTRACTOR has the two options for constructing the basin either
(1) gabions or (2) riprap. (1) Item includes furnishing and installing gabion baskets for the gabion outlet stilling basin and gabion headwall structure in accordance with the Contract Documents.
This item includes gabion baskets, fasteners, gabion rock fill, gabion rock fill for the apron, drain gravel, and geotextile fabric. Excavation and backfill necessary for construction of the Gabion Outlet Basin is considered incidental to this item. Measurement and payment will be made at the Contract lump sum price.
(2) Item includes furnishing and placing rock riprap material from an offsite source and furnishing and placing grout in accordance with the Contract Documents to construct the grouted riprap basin.
PVC and steel pipes for drain weeps, HDPE pipe for dewatering sumps, and geotextile fabric associated with the outlet basin are considered incidental to this item. Excavation and backfill to construct the riprap basin are not included in this item and will
Item 13 – Spillway Tower and Inlet Structure: Consists of providing all materials for construction of the concrete spillway tower structure and Low-Level Inlet Structure. Item includes precast concrete manhole sections, stainless steel vent pipe, nonshrink grout for vent pipe encasement, lean concrete slab, concrete bedding around foundation, structural concrete floor, galvanized steel trash rack, precast concrete inlet, galvanized steel grating, steel tubes for stop
Print Date: March 2023 01150-5 Q:\26\21710-03\55Specs\01150_Measurement_Payment.docx logs, stainless steel stoplog guides, inlet to tower PVC pipe, KNAACK Jobsite Box on concrete slab, and all other items necessary to construct the Spillway Tower and Inlet Structure in accordance with the Contract Documents. Excavation and backfill will be measured and paid for separately under other items of work. Measurement and payment will be made at the Contract lump sum price.
Item 14 – Outlet Conduit: Consists of furnishing and installing precast reinforced concrete pipe outlet conduit in accordance with the Contract Documents. This item includes outlet trench excavation through Compacted Embankment, pipe support blocks, reinforced concrete pipe, flap gate, steel reinforcing bars, and providing and placing concrete bedding and lean concrete cap.
Compacted Embankment around the outlet is not included in this item and will be paid separately.
Measurement and payment will be made at the Contract lump sum price.
Item 15 – Stabilization Fabric: (Field Measured). Consists of furnishing and installing geotextile stabilization fabric in accordance with the Contract Documents in areas directed by the GOVERNMENT. Potential areas for fabric include outlet excavation foundation and downstream toe berm foundation. Payment for this work will be made at the Contract unit price per square yard as measured and accepted in-place, excluding overlaps and anchoring.
Item 16 – Water Control/Dewatering: Consists of dewatering the reservoir and other water control measures necessary to complete the Work in accordance with the Contract Documents.
Includes all design, equipment, facilities (including, but not limited to pumps, hoses, trenches, dikes, wells, sediment control), and operation required to maintain excavations and work areas free from water. This item also includes removal of dewatering facilities upon completion of construction. The CONTRACTOR is responsible to design and maintain all construction water control features to prevent damage to the Work. Measurement and payment will be made, subject to acceptable construction progress, based on the Contract lump sum price for this item, prorated in equal monthly amounts throughout the construction schedule.
Item 17 – Lime Amended Embankment: Consists of furnishing hydrated lime, hauling, mixing lime with soil, water conditioning, placing, and compacting the lime treated soil in accordance with the Contract Documents. The quantity measured for payment will be computed using the neat line dimensions shown on the Drawings. Payment for this work will be made at the Contract unit price per cubic yard.
Item 18 – General Construction Operations:
1. This item includes, but is not limited to:
a. Furnishing, establishing, maintaining, and removing all construction facilities.
b. Obtaining, complying with, and transferring permits.
c. Installing and maintaining environmental controls for the duration of the construction Contract.
d. Installing 20 cubic yards of Cobble Slope Protection in areas directed by the Government to provide permanent erosion control features.
e. Temporary construction utilities such as electricity and sanitary facilities.
f. General site maintenance and clean-up for the duration of the construction
Print Date: March 2023 01150-6 Q:\26\21710-03\55Specs\01150_Measurement_Payment.docx
Contract.
g. All CONTRACTOR’s costs for construction surveying and staking, including, but not limited to, verifying the primary survey control points, establishing temporary construction survey control, construction staking, quantity surveys, and as-constructed surveys.
h. All CONTRACTOR’s costs for quality control testing and inspection.
2. Payment will be at the Contract lump sum price.
a. Payment will be based on the percent of the total Project Costs completed to-date, excluding the price for the General Construction Operations item.
PRODUCTS – NONE
Not Used.
EXECUTION – NONE
END OF SECTION 01150
MARSHALL DAM SECTION 01200
BLM PROJECT MEETINGS
Print Date: March 2023 01200-1 Q:\26\21710-03\55Specs\01200_Project_Meetings.docx
PART 1 - GENERAL
PRE-CONSTRUCTION CONFERENCE:
A pre-construction conference will be held prior to the start of work. CONTRACTOR will be notified in advance of meeting time, date and place. The purpose will be to review required work, project drawings and specifications, construction schedules, payroll and payments, and administrative provisions of the Contract.
CONTRACTOR, SUBCONTRACTORS and the PERSONS responsible for coordination of the work are required to be present at the meeting.
CONTRACTOR is required to be prepared to summarize and explain procedures planned for the project and to present the pre-construction submittals required.
PART 2 - PRODUCTS – NONE
Not Used.
PART 3 - EXECUTION – NONE
END OF SECTION 01200
MARSHALL DAM SECTION 01300
BLM SUBMITTALS
Print Date: March 2023 01300-1 Q:\26\21710-03\55Specs\01300_Submittals.docx
PART 1 - GENERAL
DESCRIPTION:
This section includes the procedures for submittals. Items that need to be reviewed by the GOVERNMENT are included.
PRODUCTS – NONE
Not Used
EXECUTION
SUBMITTAL PROCEDURE:
Coordinate all submittals and review them for accuracy, completeness, and compliance with contract requirements; and indicate CONTRACTOR's approval thereon as evidence of such coordination and review. Items submitted without evidence of the CONTRACTOR's approval will be returned for resubmission.
Date and Number: Forward to GOVERNMENT at least 30 days prior to needing approval or delivery to the site, all items required by the individual sections of the specifications.
Cover Letter: Forward all submittals with a cover letter from the CONTRACTOR, identifying the project and the portion of the Project to which it applies. Submittals that are related to or affect each other shall be forwarded simultaneously as a package to facilitate a coordinated review.
Uncoordinated submittals will be rejected. The GOVERNMENT reserves the right to require submittals in addition to those called for in individual sections.
Electronic Submittals: An internet-based electronic submittal and review system will be available for this project. The use of this system will be organized by the GOVERNMENT at no cost to the CONTRACTOR and will be the means for receiving and reviewing submittals.
GOVERNMENT'S APPROVAL:
The GOVERNMENT will indicate approval or disapproval of each submittal and, if not approved, will indicate reasons therefor. Any work done prior to approval shall be at the CONTRACTOR's own risk. Any work done, or materials provided, prior to approval will not be eligible for payment until approval is obtained. Approvals do not relieve the CONTRACTOR from responsibility for complying with the requirements of this Contract. If submittals show variations from the Contract requirements, the CONTRACTOR shall describe such variations in writing, in the cover letter at the time of submission. The request for a variation shall include a proposal addressing the net effect on contract price and time.
Print Date: March 2023 01300-2 Q:\26\21710-03\55Specs\01300_Submittals.docx
REQUIRED SUBMITTALS:
Subcontractors: At the preconstruction conference, provide a list of all suppliers and subcontractors to be used on the project and a completed Form SF1413 (form provided at the end of this section) for each subcontractor.
Certificates: For those items called for in individual sections, furnish certificates from manufacturers, suppliers, or others certifying that materials or equipment being furnished under the Contract comply with the requirements of these specifications.
Shop Drawings: See the individual sections for specific requirements.
Work Schedule and Progress Payment Schedule: Submit a Work Schedule and an estimated Progress Payment Schedule.
Summary of Required Submittals: The following table is a summary of submittals, by section, required by these specifications. Consult individual sections for a more complete description of individual requirements.
Print Date: March 2023 01300-3 Q:\26\21710-03\55Specs\01300_Submittals.docx
List of Submittals*
Submittal Number Submittal
Specification Reference Date Due*
01050-1 Survey Plan 01050 **
01050-2 Surveyor Resume 01050 **
01050-3 Control Survey Verification 01050 **
01050-4 Quantity Survey Notes and Computations 01050 As produced
01060-1 Contractor-Obtained Permits 01060 Preconstruction Conf.
01150-1 Schedule of Values for Lump Sum Items 01150 **
01300-1 List of Subcontractors & Suppliers with completed Form SF1413 for each subcontractor
01300 Preconstruction Conf.
01300-2 Work Schedule 01300 Preconstruction Conf.
01300-3 Estimated Progress Payment Schedule 01300 **
01400-1 Quality Procedures Plan 01400 Preconstruction Conf.
01400-2 Quality Control Test Results 01400 As produced
01570-1 Traffic Control Plan 01570 **
01700-1 Contractor Record Drawings 01700 At project closeout
01700-2 Supplier O&M Instructions 01700 At project closeout
02241-1 Gabion Data 02241 **
02241-2 Gabion Rock Fill Test Results 02241 **
02275-1 Riprap Source Data and Test Results 02275 **
02300-1 Off-site Material Test Results 02300 **
02300-2 Filter Sand and Drain Gravel Quality Control Tests 02300 As produced
02300-3 Foundation Treatment and Protection Plan 02300 **
02300-4 Embankment Construction Plan 02300 **
02300-5 Lime Treatment Plan 02300 **
02370-1 Geosynthetics Product Data & Samples 02370 **
02724-1 Reinforced Concrete Pipe Materials Shop Drawings, and Product Data
02724
02724-2 Pipe Anchor Details to Prevent Flotation 02724 **
02724-3 Waterproofing Products 02724 **
02724-4 Manhole Shop Drawings, Product Data, and Placement Information
02724 **
02724-5 Flap Gate Shop Drawings and Product Data 02724 **
02724-6 Steel and PVC Pipe Shop Drawings and Data 02724 **
02724-7 Vent Pipe Encasement Form, Support, and Placement Plan 02724 **
03300-1 Concrete Mix Design 03300 **
03300-2 Concrete Materials Product Data 03300 **
03300-3 Reinforcement Shop Drawings 03300 **
03300-4 Reinforcement Certified Materials Test Report (CMTR) 03300 **
03300-5 Formwork Design and Assembly Drawings 03300 **
03300-6 Concrete Placement Drawings 03300 **
03300-7 Concrete Placement Schedule 03300 **
Print Date: March 2023 01300-4 Q:\26\21710-03\55Specs\01300_Submittals.docx
List of Submittals*
Submittal Number Submittal
Specification Reference Date Due*
03300-8 Concrete Placement Plan(s) 03300 **
03300-9 Cold Weather Placement Plan 03300 **
03300-10 Hot Weather Placement Plan 03300 **
03300-11 Certifications 03300 **
03300-12 Concrete Batch Tickets 03300 As produced
03300-13 Protection Period Temperature Records 03300 As produced
05500-1 Manufacturer Product Data Sheets 05500 **
05500-2 Steel Fabrication Shop Drawings 05500 ** *This list is not intended to be comprehensive; consult individual sections.
**Due date for all submittals is 30 days prior to needing approval or delivery to the site, unless stated otherwise.
Print Date: March 2023 01300-5 Q:\26\21710-03\55Specs\01300_Submittals.docx
END OF SECTION 01300
MARSHALL DAM SECTION 01400
BLM QUALITY CONTROL/QUALITY ASSURANCE
Print Date: March 2023 01400-1 Q:\26\21710-03\55Specs\01400_QC_QA.docx
PART 1 - GENERAL
SECTION INCLUDES
This section covers the requirements for Quality Control (QC) on all work performed to ensure it conforms to the drawings and specifications.
QUALITY SUBMITTALS
Quality Procedures Plan.
1. A plan that identifies the CONTRACTOR’s representative responsible for the quality of the completed construction and outlines the quality control program (including construction management controls, quality control testing, test frequency, and test agencies).
Quality Control Test Results
A. Submit records of all CONTRACTOR tests to the GOVERNMENT within 24 hours of the completion of testing. The Quality Control laboratory is to notify the CONTRACTOR and the GOVERNMENT promptly of irregularities or deficiencies observed in the Work during performance of the Quality Control Testing.
DEFINITIONS
Quality Assurance (QA): Inspection and tests performed by the GOVERNMENT to assure compliance with the terms of the contract. QA testing is not used to determine construction procedures or operations (i.e. rolling patterns, lift thickness, etc.). Quality assurance also includes oversight of the CONTRACTOR’s quality control, verifying the results of the CONTRACTOR’s testing and additional assurance sampling and testing. QA testing and oversight will be provided by the GOVERNMENT at a level/frequency determined necessary by the GOVERNMENT.
Quality Control (QC): Activities performed by the CONTRACTOR to ensure work conforms to contract requirements.
Quality Control Testing: Tests to be performed by the Contractor.
1. The GOVERNMENT may use the contractor’s QC test results for Quality Assurance.
2. The Contractor may include the GOVERNMENT’s QA test records in the QC test report documenting compliance with the construction documents.
3. The tests required by the individual specification sections do not relieve the CONTRACTOR of providing adequate quality control measures to ensure the completed construction complies with the contract documents.
PRODUCTS
Not Used
MARSHALL DAM SECTION 01400
BLM QUALITY CONTROL/QUALITY ASSURANCE
Print Date: March 2023 01400-2 Q:\26\21710-03\55Specs\01400_QC_QA.docx
EXECUTION
COOPERATION WITH QUALITY ASSURANCE:
Assure the GOVERNMENT has access to all work areas at all times work is in progress.
Provide any special facilities or equipment to access work areas at CONTRACTOR expense.
Notify the GOVERNMENT when the work is ready for quality assurance/quality control testing.
Establish and update the construction schedule to provide the GOVERNMENT with estimated sampling/testing dates and times. The GOVERNMENT may choose to obtain a split and comparison test of any samples collected for quality control testing. Provide adequate notice of testing plans to coordinate collection of samples
END OF SECTION 01400
MARSHALL DAM SECTION 01570
BLM TRAFFIC CONTROL
Print Date: March 2023 01570-1 Q:\26\21710-03\55Specs\01570_Traffic_Control.docx
PART 1 - GENERAL
DESCRIPTION:
This work is the furnishing of labor, materials and equipment for installing, maintaining and operating traffic control devices to ensure the safety of the general public and project personnel.
REQUIREMENTS:
Perform work under this section meeting Manual of Uniform Traffic Control Devices (MUTCD) and contract requirements. CONTRACTOR shall obtain approval of the Traffic Control Plan (TCP) from the GOVERNMENT.
SUBMITTALS:
Conform with Section 01300 – Submittals.
Traffic Control Plan – Submit at least 30 days prior to the beginning of construction. In the TCP, name one individual whose purpose shall be to coordinate traffic control and provide a 24-hour a day telephone number or numbers to contact this person. Cooperate with the GOVERNMENT and make adjustments to the traffic control plan as required or as necessary to fit specific field conditions.
SAFETY PROVISIONS:
Safety provisions are the responsibility of CONTRACTOR. CONTRACTOR must meet County, State, and Federal laws, regulations and ordinances to protect the public.
DETOURS:
Where required by the authority having jurisdiction that traffic be maintained over any construction work in a public street, road, or highway, and the traffic cannot be maintained on the alignment of the original roadbed or pavement, construct and maintain a detour around the construction work. Include with each detour all necessary barricades, guard rails, approaches, lights, signals, signs, and other devices and precautions necessary for protection of the Work and safety of the public all in accordance with the current edition of the MUTCD.
BARRICADES AND LIGHTS:
Provide all open trenches and other excavations with suitable barriers, signs, and lights to the extent adequate protection is provided to the public. Provide similar warning signs and lights to indicate obstructions such as material piles and equipment.
Illuminate all barricades and obstructions by means of warning lights from sunset to sunrise. Place materials stored upon or alongside public roads (if any) and conduct the work at all times so as to cause minimum obstruction and inconvenience to the traveling public. Install all barricades, signs, lights and other protective devices, and maintain in conformity with applicable statutory or regulatory requirements and as required by the authority having jurisdiction.
MARSHALL DAM SECTION 01570
BLM TRAFFIC CONTROL
Print Date: March 2023 01570-2 Q:\26\21710-03\55Specs\01570_Traffic_Control.docx
PART 2 - PRODUCTS
TRAFFIC CONTROL DEVICES:
Compliance with Manual on Uniform Traffic Control Devices: Ensure all traffic control devices and their application or usage conform to the current edition of "Manual of Uniform Traffic Control Devices" (MUTCD): http://mutcd.fhwa.dot.gov/pdfs/2009r1r2/pdf_index.htm.
Reflectorized Signs and Barricades:
1. Ensure all signs and barricades are reflectorized. Ensure all traffic control devices in use are equipped with lighting devices as required in the most current edition of the MUTCD.
2. In particular ensure the channelization spacing, taper rates, standard mounting heights and size of signs are adhered to on this project. Where lighting devices are used at night, ensure they are flashing or constantly on (steady burn) depending upon their use, as defined in the MUTCD.
Assure all traffic control devices are clean, legible, reflective for night-time use, and operable.
PART 3 - EXECUTION
WORK METHODS:
Place all traffic control devices as planned before permitting men or equipment on the traveled way.
Inspect the work area at least twice each day during construction and maintain records of traffic control devices used and their location.
Assure traffic control is appropriate to the work. Assure traffic control devices are appropriate and clean before suspending work for the day.
Remove and store all unnecessary traffic control devices away from traffic's view.
END OF SECTION 01570
http://mutcd.fhwa.dot.gov/pdfs/2009r1r2/pdf_index.htm
MARSHALL DAM SECTION 01600
BLM MATERIAL AND EQUIPMENT
Print Date: March 2023 01600-1 Q:\26\21710-03\55Specs\01600_Material&Equipment.docx
PART 1 - GENERAL
COMPLETION OF WORK:
It is understood that, except as otherwise specifically stated in the Contract Documents, the CONTRACTOR shall provide and pay for all materials, labor, tools, equipment, water, light, power, transportation, supervision, temporary construction of any nature, and all other services and facilities of any nature whatsoever necessary to execute, complete, and deliver the Work within the specified time.
CONTRACTOR RESPONSIBILITY:
Store materials so as to insure the preservation of their quality and fitness for the Work. Locate stored materials to be incorporated in the Work so as to facilitate prompt inspection by the GOVERNMENT.
The CONTRACTOR is responsible for the condition and security of all materials furnished by CONTRACTOR, and shall replace all such material found to be defective or which has been damaged after delivery. This includes the replacement of material which is found to be defective at any time prior to expiration of the guarantee period.
MANUFACTURER'S RECOMMENDATIONS:
Apply, install, connect, erect, use, clean, and condition manufactured articles, materials and equipment as directed by the manufacturer.
SAMPLES:
Provide materials, supplies and equipment in accordance with samples submitted by the CONTRACTOR and approved by the GOVERNMENT.
PART 2 - PRODUCTS – NONE
Not Used.
PART 3 - EXECUTION – NONE
END OF SECTION 01600
MARSHALL DAM SECTION 01700
BLM CONTRACT CLOSEOUT
Print Date: March 2023 01700-1 Q:\26\21710-03\55Specs\01700_Contract_Closeout.docx
PART 1 - GENERAL
DESCRIPTION:
The work covered under this section includes items required in final closeout of this Project. Included are items such as post-construction inspection, acceptance of the work, closeout records and Project record drawings.
SUBMITTALS:
Provide closeout submittals for approval prior to final payment. Items to be submitted are:
Project Record Documents - See Item 3.02 for requirements.
Operation and Maintenance Instructions - Furnish electronically, complete literature, operating instructions, installation instructions, maintenance instructions, parts lists, and technical data on all items required herein or by the GOVERNMENT.
PRODUCTS
MISCELLANEOUS PRODUCTS:
Provide all maintenance materials, spare parts, tools, keys and other items either required in the Contract Documents or furnished by the suppliers of the various products.
EXECUTION
CLEANING:
Use cleaning materials recommended by the manufacturer of the surface to be cleaned. Follow the instructions on the container.
Remove all tools, equipment, surplus materials, and rubbish. Repair all marred surfaces, and remove grease, dirt, stains and foreign materials from finished surfaces.
PROJECT RECORD DRAWINGS:
Using red colored ink, CONTRACTOR shall mark changes on a set of clean prints. Indicate all changes and revisions to the original design that affect the permanent structures and that exist in the completed work. Reference all underground facilities to permanent physical objects. Reference elevation of all existing lines on profile sheets or call out elevations in plan if no profile exists. Keep record drawings current during construction activities. Certification of accuracy and completeness is required on monthly payment requisitions.
MARSHALL DAM SECTION 01700
BLM CONTRACT CLOSEOUT
Print Date: March 2023 01700-2 Q:\26\21710-03\55Specs\01700_Contract_Closeout.docx
POST-CONSTRUCTION INSPECTION:
Prior to expiration of the one-year correction period, the GOVERNMENT will inspect the Project to determine whether corrective work is required. The CONTRACTOR will be advised 14 days prior to inspection and notified in writing of all deficiencies. CONTRACTOR shall attend the post-construction inspection.
END OF SECTION 01700
SITEWORK
MARSHALL DAM SECTION 02050
BLM DEMOLITION
Print Date: March 2023 02050-1 Q:\26\21710-03\55Specs\02050_Demolition.docx
PART 1 - GENERAL
WORK INCLUDED:
Remove and dispose of existing concrete and metal structures and pipes encountered in completing project excavations. Structures to be removed include but are not limited to the existing CMP spillway riser pipe and outlet conduit, steel trash rack, and miscellaneous concrete and steel structures.
PROTECTION AND RESTORATION OF PROPERTY:
The CONTRACTOR is responsible for all methods and operations of demolition. The CONTRACTOR is solely responsible for protection of all public and private property. Promptly repair any damage caused to adjacent facilities or property to the satisfaction of the GOVERNMENT at no additional cost to the GOVERNMENT.
PRODUCTS – NONE
Not Used.
EXECUTION
SUBGRADE:
Remove all pieces of concrete, soil and rock loosened by demolition unless otherwise directed by GOVERNMENT.
Completely fill and compact areas and voids resulting from demolition work. Prepare soil subgrade surfaces as required beneath concrete structures and earth fills in accordance with the Contract Documents.
DISPOSAL OF MATERIALS REMOVED:
Concrete demolition material, including grout from inside pipes, may be buried on site in designated waste area as approved by the GOVERNMENT. Steel and metal demolition material becomes property of the CONTRACTOR and shall be removed from the site. CONTRACTOR is responsible for lawful transport and disposal of materials.
END OF SECTION 02050
MARSHALL DAM SECTION 02110
BLM CLEARING
Print Date: March 2023 02110-1 Q:\26\21710-03\55Specs\02110_Clearing.docx
PART 1 - GENERAL
WORK INCLUDED:
The work within this section consists of removing all trees, root balls, shrubs, brush, tall grass and similar vegetation as necessary to complete the Work.
PRODUCTS
Not Used.
EXECUTION
REQUIREMENTS:
Remove all trees, shrubs, brush, tall grass, and similar vegetation located on the embankment or auxiliary spillway. Perform all clearing in a safe, prudent and lawful manner and only within the construction limits indicated on the Drawings. Dispose of all trees onsite as directed by the GOVERNMENT at no additional cost to the GOVERNMENT. Do not remove trees from the site without approval from the GOVERNMENT.
TOPSOIL REUSE
Do not use topsoil removed by stripping for backfill or constructing embankments.
END OF SECTION 02110
MARSHALL DAM SECTION 02241
BLM GABIONS
Print Date: March 2023 02241-1 Q:\26\21710-03\55Specs\02241_Gabions.docx
PART 1 - GENERAL
1.01 WORK INCLUDED:
Consist of furnishing, assembling, and filling PVC-coated woven wire mesh Gabions with rock to the dimensions, lines, and grades shown on the Drawings, or as determined by the
GOVERNMENT.
1.02 SUBMITTALS:
A. Submit manufacturers’ certification, test results, and records to show that all wire materials, fasteners, and coatings to be used for Gabions on this project conform to these specifications.
B. Submit source identification, samples, and certification for rock material to be used as fill for the Gabions. Include laboratory test results showing conformance with these specifications.
PART 2 - PRODUCTS
2.01 MATERIALS:
A.…
This is the start of the file's text. The full file is on GovTribe.