This document contains an amendment to a federal solicitation for reconstruction of the GAOA Marshall Dam. Key details include:

The amendment provides responses to questions from interested offerors regarding requirements for the project. It adjusts the period of performance to 530 days from February 8, 2024 to September 8, 2025. Improvements may be made to the access road to transport equipment and materials, and a staging area at the road intersection can be utilized. The contractor has the option to use either gabion baskets or riprap for the outlet stilling basin construction. Geotextile stabilization fabric is required for all riprap areas. ASR testing of concrete aggregates is not required.

The solicitation is issued by the Bureau of Land Management for reconstruction of the GAOA Marshall Dam located in Montana. Questions covered borrow material locations, flow rates, survey and control requirements, and material testing. The amendment provides clarification on these and other technical requirements for the project.

View the file

Other files for this federal contract opportunity

Other files attached to GAOA MARSHALL DAM RECONSTRUCTION, newest first.
File Type Posted
Sol_140L3624R0003_Amd_0004.pdf PDF
Sol_140L3624R0003_Amd_0003.pdf PDF
Amendment_03_0003.pdf PDF
Amendment_02_0002.pdf PDF
Sol_140L3624R0003_Amd_0002.pdf PDF
Amendment_01_0001.pdf PDF
Sol_140L3624R0003_Amd_0001.pdf PDF
Attachment_2_-_Marshall_Dam_Drawing.pdf PDF
Attachment_9_-_SF25A_Payment_Bond.pdf PDF
Attachment_4_-_Reference_List.pdf PDF
Attachment_1_-_Marshall_Dam_Specs.pdf PDF
Attachment_7_-_SF_24_Bid_Bond.pdf PDF
Attachment_3_-_Wage_Determination.pdf PDF
Sol_140L3624R0003.pdf PDF
140L3624R0003.pdf PDF
Attachment_8_-_SF25_Performance_Bond.pdf PDF
Attachment_6_-_Financial_Responsibility_Required_Documentation.pdf PDF
Attachment_5_-_Past_Performance_Questionnaire.pdf PDF
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140L3624R0003 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

LMA

BILLINGS MT 59101

5001 SOUTHGATE DR.

BLM MT STATE OFC(MT935)

LMA

BILLINGS MT 59101

5001 SOUTHGATE DR.

BLM MT-STATE OFC(MT935)

12/18/20230004

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

11/09/2023

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

See Page 2 of 5 for changes incorporated by this amendment.

Period of Performance: 02/08/2024 to 09/08/2025

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Jorge Alvarez

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

12/18/2023

PROJECT DESCRIPTION: GAOA Marshall Dam Solicitation No. 140L3624R0003

Description of Changes - This amendment incorporates the following information:

1. The Government is providing the Questions received from interested offerors and the associated Answers provided by the Government.

Acknowledgement - See Block 11 above regarding how to acknowledge this amendment. The Government must receive the acknowledgement at the place designated for receipt of offers (See Block 8 of the Standard Form 1442).

Third Party – If you have given a copy of the solicitation to someone else, please forward this amendment accordingly.

Questions and Answers Offerors shall submit questions by 11 December 2023, at 1:00 pm, Mountain Time. Questions submitted after this date and time may not be answered. Offerors for this RFQ, including subcontractors and teammates, shall consolidate questions related to this solicitation in a Request for Information (RFI) formatted Word document. Any RFI is to be emailed as an editable attachment to Jorge Alvarez (jalvarez@blm.gov) with the subject line: RFI – 140L3624R0003 GAOA Marshall Dam. Only written RFI’s will be considered and responded to. BLM responses to the RFI will be posted as an amendment to the solicitation on https://sam.gov.

Solicitation Number: 140L3624R0003 Project Title: GAOA Marshall Dam

• Will the Contractor be able to prepare and make slight improvements, modifications, etc. the access road to the dam?

o See Specifications 01010-2, Section 1.06 – “Improvements for road access including fill, culverts, and fencing to remain after project completion as approved by

GOVERNMENT.”

o The Government will consider and approve reasonable efforts that will be needed to haul large equipment and materials into the site, including minor cut/fill, minor reroutes, culverts, etc.

• Could cattle guards be temporarily installed in place of existing gates?

o Temporary cattle guards are an acceptable means of preparing the access road.

• Will the Contractor be required to reclaim the access road?

o See Specifications 01010, Section 1.06. Improvements to remain after project completion as approved by the Government.

• On sheet 4, will the new Auxiliary Spillway area at crest stationing 2+05 to 3+07 be required to be stripped?

o Strip all areas that will be graded. Strip all areas of equipment and material storage. Strip consistently with plans and specifications.

o Sheet 19 indicates “1’ Strip” in the Profile View. The Contractor shall strip and store topsoil as indicated in plans and specifications for the New Auxiliary Spillway Construction.

• What locations are designated for borrow material?

o Soil near test pits TP-3 and TP-6, located downstream of the dam, will be suitable for compacted embankment.

• Has the borrow material locations been quantified?

o The amount of soil available for borrow around test pits TP-3 and TP-6 has not been quantified.

• Will Proctors be required for new borrow material?

o The Contractor shall provide a Moisture-Density (Proctor) Test for each soil type per

Specifications 02300, Section 3.06. The soil type may vary even in similar location(s), the Moisture-Density Test shall be representative of the material being used.

• What is the flow rate for June-November into the reservoir?

o The reservoir is located in an ephemeral watershed where there is no regular flow, but runoff occurs due to snowmelt or rain.

https://sam.gov/

• What is the static level of reservoir?

o The reservoir's normal high water elevation is up to 2,447.9 ft. The reservoir water surface was surveyed at 2,446.5 in October 2018.

• Is there a designated discharge point?

o The Contractor shall plan a dewatering discharge point as part of the site use requirements in Specification 01010, Section 1.02 & 1.04. The Government shall approve of the site use plan. Dewatering must meet local, federal, etc. laws for dewatering activities.

• Is there a designated stockpile and mixing location for lime treated soil?

o See Specifications 01010, Section 1.02 for requirements.

o The Contractor shall be responsible for site use planning of equipment and materials. The

Contractor’s site use layout shall be approved by the Government.

• How will excess debris be handled (trees, CMP, etc.)?

o See Specifications 02050, Section 3.02 for concrete and CMP disposal requirements.

o See Specifications 02110, Section 3.01 – “Dispose of trees onsite as directed by the

Government at no additional cost to the Government.”

• Who will set new control monuments?

o The Government will provide any new control monuments after completion of construction and outside of this contract.

• Who does the initial survey work?

o As stated in Specification Section 01050, the Contractor is responsible for all construction surveying, including verifying confirming the existing control, and construction staking.

• Will the Contractor have access to the CAD/survey files?

o The Government will provide electronic CAD/survey data.

• Could the Contractor review the original Geotechnical investigation/report? The dam appears to be leaking.

o Original Geotechnical Investigation/Report is not on file for the BLM.

• The period of performance appears to be too short to complete all submittals and material orders.

o Period of performance shall be adjusted to be 530 days. From 8 February 2024 to 8 September 2025.

• Could construction start prior to 7/15?

o Construction activity and surface disturbance would be prohibited from March 15 to July

15 to protect sage grouse strutting activities and migratory birds.

• Will 3rd Party Testing be required with the Quality Control process and plan?

o The Contractor shall employ an Independent Laboratory to provide onsite quality control services. All testing (e.g. In-Place Density, Cast-In-Place Concrete, etc.) specified in the plans and specifications shall be performed by an Independent Testing Laboratory/Agency.

• It appears that we have a choice of either using a grouted riprap (sheets SB1 – SB2) OR use a Gabion Basket System (sheets SB3 – SB4). Please confirm this is the intention of the plans on these sheets.

o Yes.

Specifications 01150 Section 1.07 states:

L. Item 12 – Outlet Basin: CONTRACTOR has the two options for constructing the basin either (1) gabions or (2) riprap. (1) Item includes furnishing and installing gabion baskets for the gabion outlet stilling basin and gabion headwall structure in accordance with the Contract Documents. This item includes gabion baskets, fasteners, gabion rock fill, gabion rock fill for the apron, drain gravel, and geotextile fabric. Excavation and backfill necessary for construction of the Gabion Outlet Basin is considered incidental to this item. Measurement and payment will be made at the Contract lump sum price.

Which confirms the Contractor having either option for the Stilling Basin.

• The BLM access road from the intersection of Whitney creek rd to the job site needs to be improved to allow material, redi mix, and aggregate deliveries. Can the road be improved? Can a staging area at the intersection of Whitney Creek Rd and the BLM access trail be utilized for intermediate staging? It will be utilized for materials not easily delivered to the location.

o Improvements may be accepted. See previous questions detailing acceptance of improvements to the access road and leaving the improvements after construction is completed (no reclamation or restoration to previous conditions).

o The intersection of Whitney Creek Rd and the Access Road on BLM property may be used for temporary storage of materials not easily delivered to the location. The area used for storage shall be approved by the Government prior to placement and the area shall be leveled and left in a condition that the area may return to similar previous conditions.

• Pay item 15: Stabilization Fabric – is the intention of this pay item to cover ALL Geotech fabric required for the project (such as under all rip rap)?

o Yes. All Geotextile Stabilization Fabric shall be paid for and covered by Pay Item 15.

Therefore, the effort and costs associated with Geotextile Stabilization Fabric in Pay Items 9 and 12 (or any other Geotextile Stabilization Fabric locations) shall be included in Pay Item 15.

• Can the ASR requirements be waived for this project?

o Although ASTM C1260 is listed in Section 03300 Reference Standards, a relevant requirement is not listed in Section 03300, Part 2, so there is no ASR testing requirement for the concrete aggregates on this project.

• Would the attached testing be approved to pass project requirements?

o The ASTM C1012 preliminary nine-month test results indicate that the Montana City

Type IL cement and Coal Creek fly ash will likely meet the project requirements for less than 0.10% expansion at 18 months. Final approval of a proposed concrete mix design, including the cement, would occur during the submittal review process after the construction contract is awarded.

2023-12-18T15:40:13-0700
JORGE ALVAREZ