This document contains an amendment to a federal solicitation for reconstruction of the GAOA Marshall Dam. The amendment provides additional details on the project scope, extends the period of performance from February 8, 2024 to September 8, 2025, and includes answers to questions from interested offerors. Reconstruction work includes improvements to the access road, stripping and stockpiling topsoil in designated areas, disposal of debris, and quality control testing by an independent laboratory. Offerors must acknowledge receipt of the amendment by the response deadline of December 11, 2023. The solicitation is seeking offers for reconstruction of the GAOA Marshall Dam being conducted by the Bureau of Land Management.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140L3624R0003_Amd_0004.pdf | ||
| Amendment_04_0004.pdf | ||
| Amendment_03_0003.pdf | ||
| Sol_140L3624R0003_Amd_0003.pdf | ||
| Sol_140L3624R0003_Amd_0002.pdf | ||
| Amendment_01_0001.pdf | ||
| Sol_140L3624R0003_Amd_0001.pdf | ||
| Attachment_1_-_Marshall_Dam_Specs.pdf | ||
| Attachment_7_-_SF_24_Bid_Bond.pdf | ||
| Attachment_3_-_Wage_Determination.pdf | ||
| Sol_140L3624R0003.pdf | ||
| 140L3624R0003.pdf | ||
| Attachment_8_-_SF25_Performance_Bond.pdf | ||
| Attachment_6_-_Financial_Responsibility_Required_Documentation.pdf | ||
| Attachment_5_-_Past_Performance_Questionnaire.pdf | ||
| Attachment_9_-_SF25A_Payment_Bond.pdf | ||
| Attachment_4_-_Reference_List.pdf | ||
| Attachment_2_-_Marshall_Dam_Drawing.pdf |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140L3624R0003 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
LMA
BILLINGS MT 59101
5001 SOUTHGATE DR.
BLM MT STATE OFC(MT935)
LMA
BILLINGS MT 59101
5001 SOUTHGATE DR.
BLM MT-STATE OFC(MT935)
12/12/20230002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
11/09/2023
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
See Page 2 of 5 for changes incorporated by this amendment.
Period of Performance: 02/08/2024 to 09/08/2025
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Jorge Alvarez
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
12/12/2023
PROJECT DESCRIPTION: GAOA Marshall Dam Solicitation No. 140L3624R0003
Description of Changes - This amendment incorporates the following information:
1. For informational purposes only, the Government is providing the Site Visit Attendance Records from the organized site visit that the Government held on November 28, 2023, at 11:00 am Mountain Time.
2. The Government is providing the Questions received from interested offerors and the associated Answers provided by the Government.
3. The period of performance is extended and adjusted to 8 February 2024 – 8 September 2025. The amount of calendar days is extended to 578.
Acknowledgement - See Block 11 above regarding how to acknowledge this amendment. The Government must receive the acknowledgement at the place designated for receipt of offers (See Block 8 of the Standard Form 1442).
Third Party – If you have given a copy of the solicitation to someone else, please forward this amendment accordingly.
SITE INSPECTION TOUR / PREBID CONFERENCE RECORD
The Government strongly urges offerors to inspect the site to gain a better understanding of the work requirements and to satisfy themselves regarding all general and local conditions that may affect the cost of performance. In no event shall failure to inspect the site constitute grounds for a claim after award.
Solicitation Number: 140L3624R0003 Project Title: GAOA Marshall Dam Date and Time: 11/28/2023 at 11:00 AM Meeting Place(s): Marshall Dam Conducted by: Josh Helm, Civil Engineer
Attended by:
Name Company
Ryna Schaner Bishop Inc.
Virgil Aderholt H-2 Mark Bachman Bachman Construction Marvin Robb Prospect Construction Jared Dirkson Youderian Construction Doug Moore Rain For Rent
Questions and Answers Offerors shall submit questions by 11 December 2023, at 1:00 pm, Mountain Time. Questions submitted after this date and time may not be answered. Offerors for this RFQ, including subcontractors and teammates, shall consolidate questions related to this solicitation in a Request for Information (RFI) formatted Word document. Any RFI is to be emailed as an editable attachment to Jorge Alvarez (jalvarez@blm.gov) with the subject line: RFI – 140L3624R0003 GAOA Marshall Dam. Only written RFI’s will be considered and responded to. BLM responses to the RFI will be posted as an amendment to the solicitation on https://sam.gov.
Solicitation Number: 140L3624R0003 Project Title: GAOA Marshall Dam
• Will the Contractor be able to prepare and make slight improvements, modifications, etc. the access road to the dam?
o See Specifications 01010-2, Section 1.06 – “Improvements for road access including fill, culverts, and fencing to remain after project completion as approved by
GOVERNMENT.”
o The Government will consider and approve reasonable efforts that will be needed to haul large equipment and materials into the site, including minor cut/fill, minor reroutes, culverts, etc.
• Could cattle guards be temporarily installed in place of existing gates?
o Temporary cattle guards are an acceptable means of preparing the access road.
• Will the Contractor be required to reclaim the access road?
o See Specifications 01010, Section 1.06. Improvements to remain after project completion as approved by the Government.
• On sheet 4, will the new Auxiliary Spillway area at crest stationing 2+05 to 3+07 be required to be stripped?
o Strip all areas that will be graded. Strip all areas of equipment and material storage. Strip consistently with plans and specifications.
o Sheet 19 indicates “1’ Strip” in the Profile View. The Contractor shall strip and store topsoil as indicated in plans and specifications for the New Auxiliary Spillway Construction.
• What locations are designated for borrow material?
o Working on answer.
• Has the borrow material locations been quantified?
o Working on answer.
• Will Proctors be required for new borrow material?
o The Contractor shall provide a Moisture-Density (Proctor) Test for each soil type per
Specifications 02300, Section 3.06. The soil type may vary even in similar location(s), the Moisture-Density Test shall be representative of the material being used.
• What is the flow rate for June-November into the reservoir?
o Working on answer.
• What is the static level of reservoir?
o Working on answer.
• Is there a designated discharge point?
https://sam.gov/ o The Contractor shall plan a dewatering discharge point as part of the site use requirements in Specification 01010, Section 1.02 & 1.04. The Government shall approve of the site use plan. Dewatering must meet local, federal, etc. laws for dewatering activities.
• Is there a designated stockpile and mixing location for lime treated soil?
o See Specifications 01010, Section 1.02 for requirements.
o The Contractor shall be responsible for site use planning of equipment and materials. The
Contractor’s site use layout shall be approved by the Government.
• How will excess debris be handled (trees, CMP, etc.)?
o See Specifications 02050, Section 3.02 for concrete and CMP disposal requirements.
o See Specifications 02110, Section 3.01 – “Dispose of trees onsite as directed by the
Government at no additional cost to the Government.”
• Who will set new control monuments?
o The Government will provide any new control monuments after completion of construction and outside of this contract.
• Who does the initial survey work?
o Working on answer.
• Will the Contractor have access to the CAD/survey files?
o The Government will provide electronic CAD/survey data.
• Could the Contractor review the original Geotechnical investigation/report? The dam appears to be leaking.
o Original Geotechnical Investigation/Report is not on file for the BLM.
• The period of performance appears to be too short to complete all submittals and material orders.
o Period of performance shall be adjusted to be 530 days. From 8 February 2024 to 8 September 2025.
• Could construction start prior to 7/15?
o Construction activity and surface disturbance would be prohibited from March 15 to July
15 to protect sage grouse strutting activities and migratory birds.
• Will 3rd Party Testing be required with the Quality Control process and plan?
o The Contractor shall employ an Independent Laboratory to provide onsite quality control services. All testing (e.g. In-Place Density, Cast-In-Place Concrete, etc.) specified in the plans and specifications shall be performed by an Independent Testing Laboratory/Agency.