This file is a hazard identification and assessment spreadsheet for the USCGC MYRTLE HAZARD drydock maintenance project. The document appears to be an inventory template organized in spreadsheet format (Excel) that catalogs potential hazards associated with the vessel's drydock operations and maintenance activities scheduled for Fiscal Year 2027. The spreadsheet likely includes columns for hazard identification, classification, risk assessment, mitigation measures, and responsible parties involved in managing safety during the drydocking process. Given its attachment designation and association with a U.S. Coast Guard vessel maintenance solicitation under the Department of Homeland Security, this hazard documentation serves as a critical safety planning tool that contractors must reference to ensure compliance with occupational safety requirements and Coast Guard operational standards during the extensive dry-dock maintenance and repair work. The hazard assessment would inform contractors' safety protocols, training requirements, and resource allocation for this naval vessel maintenance project managed by DHS U.S. Coast Guard.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOS&S
| PRICING SCHEDULE FOR: | Attachment 1 |
| USCGC MYRTLE HAZARD (WPC 1139) DRYDOCK AVAILABILITY FY2027 |
| ITEM | DESCRIPTION | UNIT PRICE | UNIT | QTY | EXTENDED PRICE |
| D-001 | Hull Plating | $0.00 | JOB | 1 | $0.00 |
| D-002 | Tanks and Voids | $0.00 | JOB | 1 | $0.00 |
| D-003 | Watertight Closures | $0.00 | JOB | 1 | $0.00 |
| D-004 | Propulsion Shafting System | $0.00 | JOB | 1 | $0.00 |
| D-005 | Piping Systems | $0.00 | JOB | 1 | $0.00 |
| D-006 | Electrical Power Distribution System | $0.00 | JOB | 1 | $0.00 |
| D-007 | Ventilation Systems | $0.00 | JOB | 1 | $0.00 |
| D-008 | Rudder System | $0.00 | JOB | 1 | $0.00 |
| D-009 | Fin Stabilizer System | $0.00 | JOB | 1 | $0.00 |
| D-010 | Bow Thruster System | $0.00 | JOB | 1 | $0.00 |
| D-011 | Stern Launch Door System | $0.00 | JOB | 1 | $0.00 |
| D-012 | Sewage and Grey Water System | $0.00 | JOB | 1 | $0.00 |
| D-013 | Topside Structure and Coating Systems | $0.00 | JOB | 1 | $0.00 |
| D-014 | Underwater Body | $0.00 | JOB | 1 | $0.00 |
| D-015 | ICCP/Antifouling System | $0.00 | JOB | 1 | $0.00 |
| D-016 | Drydocking | $0.00 | JOB | 1 | $0.00 |
| D-017 | Temporary Services | $0.00 | JOB | 1 | $0.00 |
| O-00Z | Laydays | $500.00 | Day | 5 | $2,500.00 |
| Total Price of Definite Items | $0.00 | ||||
| Total Price of Definite and Optional Items | $0.00 |
| Open and Inspect Repairs | |
| The Labor Rates and Material Markup/Handling Fee will be used throughout the life of the contract for all open and inspect repair items. The total extended price for both CLINs below are being used solely for the purposes of evaluating price. | |
| OA/G-001 | **Provide breakdown, as follows: Labor Rate |
Unit Price: $________; Quantity: 2239 ; Unit of Issue: Hour; Extended Price: $____________ Sorrell, Latoya N CIV DHS (USA): Contractors will enter labor rate here.
| Hour | 2239 | $0.00 |
| OA/G-002 | Material Markup/Handling Fee |
Unit Price: $143,943.97; Quantity: 1; Unit of Issue: Percent ________%;
Extended Price: [$143,943.97 X percentage quoted]: $______________ $143,943.97 % Sorrell, Latoya N CIV DHS (USA): Contractors will enter material markup/handling fee here.
$0.00 Sorrell, Latoya N CIV DHS (USA): Do Not Change this cell.
Total Price for Over and Above/Growth $0.00
(8/23/2024)_x000D_ Draft-0 - Page &P of &N
Foreseeable Cost Factors
| FORESEEABLE COST WORKSHEET | |
| USCGC MYRTLE HAZARD | FY27 |
| Contractor's Name: | |
| The contractor shall fill-in all yellow labeled boxes below to determine their foreseeable costs. Please read all notes and headers of sections for instructions in completing this worksheet. |
| DISTANCE FACTORS FOR: US Naval Activities Victor Wharf Pier 3 Santa Rita, GU 96915 | |
| NAUTICAL MILES BASED ON ROUND-TRIP (TO AND FROM) | |
| NUMBER OF DAYS OF AVAILABILITY | 119 |
| (1) Port Engineer/COR Transportation: AIR TRAVEL | |
| (Applicable if > 50 miles from PE address |
(PE's desk location)
| A. Number of CG Representatives from NESU: | A= | 1 |
| B. The number of round trips between the contractor's facility and NESU | B= | 1 |
| C. A multiplied by B: | AxB=C= | 1 |
| D. Travel cost per trip: | D= |
Massey, Marc A CIV: Contractor shall utilize: https://www.gsa.gov/travel/plan-a-trip/transportation-airfare-rates-pov-rates-etc/airfare-rates-city-pair-program
| Contractor shall utilize either (1) the total dollar amount for commercial round-trip airfare if their dry dock is greater than 150 driving miles from the PE's homeport OR (2) Enter "0" if their dry dock is less than 150 driving miles from the PE's homeport. | E. C multiplied by D =E, if >50 miles from NESU otherwise N/A. | E= | $0.00 |
| (2) Port Engineer Transportation: CAR TRAVEL | |||
| A. Number of CG Representatives from NESU: | A= | 1 | |
| B. Number of Driving miles Round-trip between the COR office and contractors facility: | B= | ||
| C. Travel cost per driving mile (rate at $0.58 per mile) | $0.580 | $0.00 | |
| (3) PER DIEM: (Applicable >50 miles CREW + PE) | |||
| A. Number of Ship's Crew & Port Engineer | A= | 25 | |
| B. Total number of day(s) in drydock. | B= | 119 | |
| C. Per diem cost at place of performance, per day: (if < 50 miles, enter "0" for all below) | C= | $0.00 | |
| C.1.1. Enter Lodging Daily Per Diem Rate | |||
| C.2.1. Enter Meals & Incidentals Total Daily Rate | |||
| C.2.1.1. Enter Meals & Incidentals First & Last Day of Travel Daily Rate | |||
| D. AxBxC= D: (if >50 miles from NESU) | D= | $0.00 | |
| (4) PER DIEM: (Applicable >50 miles Contracting Officer Travel & Per Diem. KO location is Norfolk, VA 23510) | |||
| A. Number of KO authorized travel: | A= | 1 | |
| B. Total number of KO travel days: | B= | 3 | |
| C. Transportation cost for KO travel | C= |
Massey, Marc A CIV: Contractor shall utilize: https://www.gsa.gov/travel/plan-a-trip/transportation-airfare-rates-pov-rates-etc/airfare-rates-city-pair-program
| Contractor shall utilize either (1) the total dollar amount for commercial round-trip airfare if their dry dock is greater than 150 miles from the KO's location in Norfolk, VA 23510 or (2) Enter "0" if their dry dock is less than 150 miles from the PE's homeport. | D. Per diem cost at place of performance, per day | D= | $0.00 |
| D.1.1. Enter Lodging Per Diem Rate | |||
| D.2.1. Enter Meals & Incidentals Total Daily Rate | |||
| D.2.1.1. Enter Meals & Incidentals First & Last Day of Travel Daily Rate | |||
| E. A [(B*D) + C] = | E= | $0.00 | |
| (5) CUTTER COST Operation Factors: | |||
| A. Round Trip Nautical Miles from the vessels pier to the contractors facility: | A= | 0 | |
| B. Cutter Cost Factor Per Nautical Mile: | B= | $47.57 | |
| C. A multiplied by B= C | C= | $0.00 | |
| (6) FAMILY SEPARATION ALLOWANCES (FSA) Applicable if > 50 miles from Homeport - for crew with dependents only (Daily Rate $8.33). If less than 50 miles enter 0 for A below. | |||
| A. Number of Personnel entitled to Family Separation Allowance: | A= | 12 |
Strawbridge, Tracey CIV: Do Not Change this cell unless Drydock is less than 50 driving miles from Homeport. Then enter 0.
| B. Number of Days for Availability minus 30 days if availability is greather than 30 days: | B= | 89 |
| C. A multiplied by B = C (Daily FSA rate of $8.33) | C= | $8,896.44 |
| (7) CREW TRANSPORTATION FOR HOME VISIT (Applicable after 31 consecutive days if > 50 miles from Homeport - for crew with dependents only | ||
| A. Number of Personnel (with dependents) entitled to HOME visit: | A= | 12 |
| B. Number of Homeport Visits: | B= | 2 |
| C Mileage to homeport = (Roundtrip Ticket Cost) | C= |
Massey, Marc A CIV: If contractor's facility is:
- located < 50 miles from the ship's homeport, enter $0.
- located > 51 miles but less than 149 miles from the ship's homeport, multiply round trip vehicle mileage by $0.58
- located > 150 miles from ship's homeport, utilize https://www.gsa.gov/travel/plan-a-trip/transportation-airfare-rates-pov-rates-etc/airfare-rates-city-pair-program Massey, Marc A CIV: Contractor enters name here Massey, Marc A CIV: Contractors shall utilize https://www.gsa.gov/travel/plan-book/per-diem-rates/per-diem-rates-lookup to estimate per diem rates Massey, Marc A CIV: Contractor will enter either (1) "0" if their dry dock is located less than 50 miles or more than 150 miles from the PE's homeport or (2) the total number of round trip driving miles if the contractor is located between 51 to 149 miles from PE's homeport.
Massey, Marc A CIV: Contractor shall utilize: https://nauticalcharts.noaa.gov/publications/docs/distances.pdf http://ports.com/sea-route/ Massey, Marc A CIV: Contractors shall utilize https://www.gsa.gov/travel/plan-book/per-diem-rates/per-diem-rates-lookup to estimate per diem rates based on the location of their facility.
Strawbridge, Tracey CIV: Do Not Change this cell unless Drydock is less than 50 driving miles from Homeport. Then enter 0.
| D. A multiplied by B, multiplied by C = D: | C= | $0.00 |
| GRAND TOTAL | ||
| 1. PE/COR Transportation (AIRFARE) | $0.00 | |
| 2. PE/COR Transportation (CAR) | $0.00 | |
| 3. Per Diem for Crew and PE/COR | $0.00 | |
| 4. Per Diem for Contracting Officer (KO) | $0.00 | |
| 5. Cutter Cost Operations Factors | $0.00 | |
| 6. Family Separation Allowance | $8,896.44 | |
| 7. Crew Transportation Home Visit | $0.00 | |
| Total Cost of Distance Factors: | $8,896.44 | |
| Total Contractor Quoted/Proposal Price: | ERROR:#REF! | |
| TOTAL EVALUATED QUOTE/PRICE | ERROR:#REF! |
File details come from the government source that posted it. Updated .