70Z08026QPBPL0055 Amendment 2 with Question answer.pdf

PDF 311 KB Posted

Attached to
DRYDOCK: USCGC MYRTLE HAZARD DD FY27
Solicitation number
70Z08026QPBPL0055
Issued by

About this file

This is an Amendment of Solicitation/Modification of Contract (Standard Form 30) issued by the U.S. Navy (70Z080 CPD 1 - Norfolk, VA) on September 21, 2026. The amendment number is 70Z08026QPBPL00550002, referencing solicitation 70Z08026QPBPL0055 dated September 18, 2026. The amendment addresses questions submitted by bidders and does not extend the hour and date specified for receipt of offers. All other terms and conditions of the referenced solicitation remain unchanged and in full force and effect.

The amendment includes a questions and answers section covering Work Item 2 of a ship repair/drydock project. Key responses include: estimated residual fluids for disposal should be minimized with fuel at 50% or less upon arrival; QP1 certified painters and AMPP CIP Level 3 Technical Representatives may be provided by subcontractors as long as required certifications are attached and verified; relevant past performance is limited to similar drydock ship repair work performed within three years of the solicitation posting date, with no consideration of projects older than three years; vessel lifting plans, docking plans with block support locations, and rigging/sling arrangements are referenced in Work Item 16 of the specification. The contracting officer is Jaime R. Smith, and the amendment was digitally signed on September 21, 2026.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

Jaime R. Smith, Contracting Officer

70Z08026QPBPL00550002

Summary of Changes

Work Item 2

Q: 1. For bidding purposes, what are the total estimated residual fluids for disposal?

A: 1. The cutter will make best effort to arrive as low as possible with fuel 50% or less.

Coatings Certification Requirement

Q: 2. If contractor intends to subcontract coating work, may the QP1 certified painters and/or

AMPP CIP Level 3 Technical Representative be provided by the subcontractor?

A: 2. As long as they hold the required certification and those certifications are attached for review in the solicitation.

Past performance

Q: 3. Will ship repair, maintenance, or marine coating contract of similar scope be considered relevant past performance if they are not specifically drydock projects?

A: 3. As stated in the solicitation, The quoter shall identify up to three (3) recent and relevant contracts or efforts as past performance references. Recent and relevant past performance is defined as similar work being performed within three (3) years of the posting of the solicitation.

Similar work meaning drydock ship repair.

Q:4. If fewer than three relevant contracts are available within the last three years, will the

Government consider older projects?

A:4. We will only consider work within the past 3 years of the posting of the solicitation.

Q:5. Is there an approved vessel lifting plan or lifting arrangement?

A:5. WORK ITEM 16 of the SPECIFICATION

Q:6 Is there a docking plan showing the vessel’s docking block support locations and/or cradle details?

A:6. WORK ITEM 16 of the SPECIFICATION

Q:7. Is there a rigging or sling arrangement previously approved or used for lifting the vessel?

A:7. WORK ITEM 16 of the SPECIFICATION

70Z08026QPBPL00550002 signed.pdf
MYRTLE HAZARD DD FY-27 QA.pdf
Text52:
Text54: 1
TOTAL_NO_OF_PAGES: 2
CUST_PROJ_CODE:
DOCUMENT_NUMBER: 70Z08026QPBPL00550002
EFFECTIVE_DATE: 2026-09-21T08:56:58.000-04:00
REF_PR_NUM_T: 52000PR260027277
SOL_DOCUMENT_NUMBER: 70Z08026QPBPL0055
SOL_OPEN_BID_DATE: 2026-09-18T08:43:46.000-04:00
NO_OF_COPIES: 1
Check Box91: Yes
Check Box92: Off
MANUAL_EXTEND_FLAG: N
Check Box95: Yes
Check Box96: Off
Check Box97: Off
Check Box98: Off
Check Box99: Off
Check Box100: Off
Check Box101: Off
Text1: AMENDMENT CONTROL NUMBER :
HDR_DOCUMENT_NUMBER: 70Z08026QPBPL0055
Text134: SUMMARY OF CHANGES :
AMENDMENT_DESCRIPTION: AMEND-This amendment is to answer questions. See attached for questions and answers. All other terms and conditions remain the same.
Text2: Same As Issuing Office
AMD_ISSUING_OFFICE_LADDR: 70Z080 CPD 1 - Norfolk, VA

Commander, USCG-SFLC-CPD 1, 300 East Main Street, Suite 550 Norfolk, VA, 23510, US

AMD_ISSUING_OFFICE_LOCCODE: 70Z080
2026-09-21T13:42:52-0400
SMITH.JAIME.RACHELLE.1046221610

File details come from the government source that posted it. Updated .