attachment-1-bid-3013-25.pdf

PDF 575 KB Posted

Attached to
CONTRACT: Portsmouth Circuit Court Boiler Removal and Installation Services
Solicitation number
Bid 3013-25
Issued by
Rockingham County, New Hampshire

About this file

This file contains project execution specifications and requirements documentation prepared by the New Hampshire Department of Administrative Services for the Portsmouth Circuit Court Boiler Removal and Installation Services project. The project involves the removal of existing boilers and installation of two new high-efficiency gas-fired condensing boilers at the Portsmouth Circuit Court located at 111 Parrott Avenue. Work must commence within 15 days of the Notice to Proceed and be completed by September 30, 2025. Two mandatory pre-bid site walkthroughs are scheduled for March 7 and March 12, 2025 at 1:00 PM. The bid opening is set for March 28, 2025 at 9:00 AM Eastern Time. Work is restricted to normal business hours of 7:00 AM to 4:00 PM, Monday through Friday, excluding specified state holidays, though outside-hour work may be requested in writing with Contract Administrator approval. The State will continue to occupy and operate the premises during construction, requiring the contractor to coordinate activities to minimize disruption of normal court operations.

The contract is awarded on a lump sum basis with monthly progress payments made 30 days after invoice receipt based on percentage of work completed. All labor, materials, start-up, and required training must be included in the bid price. Acceptable boiler manufacturers are limited to Lochinvar Corporation, Aerco Corporation, and Cleaver-Brooks. The contractor must obtain a Payment and Performance Bond equal to 100% of the contract amount and ensure all on-site employees obtain background checks. A minimum one-year warranty covering 100% of repair or replacement costs, including parts, shipping, labor, and travel expenses, is required for all equipment. The contractor must complete and submit rebate paperwork for condensing boilers, pumps, and variable frequency drives, with rebate funds credited to the State. The project requires implementation of a construction waste management plan achieving a minimum 75% diversion of waste from landfills through recycling and adaptive reuse. Comprehensive documentation requirements include field record drawings, operations and maintenance manuals, spare parts inventory, product warranties, and proof of staff training prior to Substantial Completion.

View the file

Other files

File Type Posted
Addendum_2_bid_3013_25.pdf PDF
Addendum_1_bid_3013_25.pdf PDF
attachment_3_bid_3013_25.pdf PDF
attachment_2_bid_3013_25.pdf PDF
attachment_4_bid_3013_25.pdf PDF
attachment_1_bid_3013_25.pdf PDF
bid_3013_25.pdf PDF
bid-3013-25-award.pdf PDF
bid-3013-25.pdf PDF
attachment-3-bid-3013-25.pdf PDF
addendum-2-bid-3013-25.pdf PDF
attachment-2-bid-3013-25.pdf PDF
attachment-4-bid-3013-25.pdf PDF
addendum-1-bid-3013-25.pdf PDF
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

81224, Contract D – Portsmouth Circuit Court Boilers

Summary

01100 - 1

SECTION 01100

SUMMARY

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Contract description.

B. Contractor's use of site and premises.

C. Work sequence.

D. State occupancy.

E. Rebates.

F. Specification Conventions.

1.2 CONTRACT DESCRIPTION

A. Work of the Project includes removal of existing boilers and installation of new boilers and associated controls as required.

B. SITE EXAMINATION

1. Examine Project site before submitting a Bid.

2. A visit to the Project site has been arranged for Bidders per the bid document.

See Site Visitation section of the bid for additional information and points of contact.

C. Perform Work of Contract under stipulated lump sum grand total contract with State in accordance with Conditions of Contract.

D. The Contractor shall, except as otherwise specifically stated in the Contract Documents, provide and pay for all materials, labor, tools, equipment, water, heat, fuel, light, power, transportation, superintendence, temporary construction of every nature, and all other services and facilities of every nature whatsoever necessary to execute, complete, and deliver the work within the specified time.

1.3 CONTRACTOR'S USE OF SITE AND PREMISES

A. Access to Site: Limited to normal working hours.

01100 - 2

B. Emergency Building Exits During Construction: Shall be maintained and all building entrances and exits shall remain functional.

C. Construction Operations: Limited to areas noted on Drawings.

D. Time Restrictions for Performing Work: Normal working hours of 7:00 am to 4:00 pm, Monday through Friday with the following restrictions:

1. No access during the following observed holidays:

a. New Year’s Day.

b. Martin Luther King Jr. Civil Rights Day.

c. Washington’s Birthday.

d. Memorial Day.

e. Independence Day.

f. Labor Day.

g. Veterans’ Day.

h. Thanksgiving Day.

i. Day after Thanksgiving.

j. Christmas Day.

2. Access for work outside of normal working hours shall be requested in writing to the Contract Administrator, at least one week in advance. The Contract

Administrator may accept or reject the request.

E. Utility Outages and Shutdown: Shall be coordinated with the building users to minimize disruption of services and may require work to take place outside of normal working hours.

1.4 WORK SEQUENCE

A. Work shall commence within 15 days after issuance of Notice to Proceed. Failure to comply shall constitute Default of Contract.

1.5 STATE OCCUPANCY

A. The State will occupy the premises for the conduct of normal operations.

B. Cooperate with State to minimize conflict, and to facilitate State's operations.

C. Schedule the Work to accommodate State occupancy.

1.6 REBATES

D. The contractor shall be responsible to complete rebate paperwork for all condensing boilers, pumps, and VFD’s. The rebate money will be sent to the contractor and the

State will take a credit in the contract. This credit can be used to increase the contract or added to the allowance at the discretion of the Contract Administrator.

1.7 SPECIFICATION CONVENTIONS

E. These specifications are written in imperative mood and streamlined form. This imperative language is directed to the Contractor, unless specifically noted otherwise.

01100 - 3

The words “shall be” are included by inference where a colon (:) is used within sentences or phrases.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

Not Used.

END OF SECTION

Quality Requirements

01400 - 1

SECTION 01400

QUALITY REQUIREMENTS

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Quality control and control of installation.

B. Tolerances

C. References.

D. Safety

E. Mock-up requirements.

F. Supervision

G. Testing and inspection services.

H. Manufacturers' field services.

I. Examination.

J. Preparation.

1.2 QUALITY CONTROL AND CONTROL OF INSTALLATION

A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce Work of specified quality. Prior to acceptance of approved materials on site, establish & maintain controlled environmental conditions required for proper, sequential installations. Products affected by inadequate environmental control

(in storage or installed) shall be removed, disposed of and replaced in-kind with no adjustment to the contract price or work schedule.

B. Comply with manufacturers' instructions, including each step in sequence.

C. When manufacturers' instructions conflict with Contract Documents, request clarification from the Contract Administrator before proceeding.

D. The Contractor shall notify the Contract Administrator of any discrepancies, ambiguities or obvious omissions found in the Contract Documents before proceeding with the work affected thereby. Such notification shall be made in writing requesting clarification and/or interpretation with reasonable promptness consistent with and reasonably inferable from the Contract Documents. If the Contractor fails to make such request, no excuse will thereafter be entertained for failure to carry out work in a satisfactory manner, and no monies will be paid for correcting of items.

01400 - 2

E. The Contractor shall give the Contract Administrator timely notice of any additional drawings, specifications or instructions required to define the work in greater detail or to permit the proper progress of the work.

F. Comply with specified standards as minimum quality for the Work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.

G. Where, on any of the Drawings, a portion of the work is drawn out and the remainder is indicated in outline, the parts drawn out shall also apply to all other portions of the work.

H. Perform Work by persons qualified to produce required and specified quality.

I. Verify field measurements are as indicated on Shop Drawings or as instructed by manufacturer.

J. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, or disfigurement.

1.3 TOLERANCES

A. Monitor fabrication and installation tolerance control of products to produce acceptable

Work. Do not permit tolerances to accumulate.

B. Comply with manufacturers' tolerances. When manufacturers' tolerances conflict with

Contract Documents, request clarification from the Contract Administrator before proceeding.

C. Adjust products to appropriate dimensions; position before securing products in place.

1.4 REFERENCES

A. Conform to reference standard by date prior to the date of receiving bids, except where specific date is established by code. The standard referred to, except as modified in the specifications, shall have full force and effect as though printed in the Specifications.

B. Obtain copies of standards where required by product specification sections.

C. When specified reference standards conflict with Contract Documents, request clarification from the Contract Administrator before proceeding.

D. Neither contractual relationships, duties, nor responsibilities of parties in Contract nor those of Architect or Engineer shall be altered from Contract Documents by mention or inference otherwise in reference documents.

E. The Contractor shall comply with all applicable Federal, State, Local laws, ordinances, regulations, and requirements to work hereunder, including building code requirements.

If the Contractor ascertains at any time that any requirement of this Contract is at variance with applicable laws, ordinances, regulations or building code requirements, he/she shall notify the Contract Administrator in writing.

01400 - 3

1.5 SAFETY

A. The Contractor shall, at all times, safely guard the State’s property and persons from injury or loss in connection with this Contract. The Contractor shall, at all times, safely guard and protect their own work and that of adjacent property from damage. All passageways, guard fences, lights, and other facilities required for protection by Federal, State or Municipal laws and regulations must be provided and maintained.

B. Place upon the work or any part thereof, only such loads as are consistent with the safety of that portion of the work.

1.6 SUPERVISION

A. All work shall be done under the observation and inspection of the Contract

Administrator.

B. The Contract Administrator may observe, examine and test materials and workmanship at any and all times during manufacture and/or construction, and at any and all places where such manufacture and/or construction is carried on.

C. The Contract Administrator shall suspend work that may be subject to damage by climatic conditions.

D. Prior to final acceptance, the Contract Administrator at any time before final acceptance of the entire work to make an examination of work already completed that was not specifically called for to receive an inspection prior to covering over, and shall require removing or tearing out same, the Contractor shall, upon request, promptly furnish all necessary facilities, labor, and materials. If such work is found to be defective in any material respect, due to the fault of the Contractor or his Subcontractors, he shall defray all expenses of such examination and of satisfactory reconstruction. If however, such work is found to meet the requirements of the Contract, the actual cost of labor and material necessarily involved in the examination and replacement, shall be completed per a Time and Material Alteration Order.

1.7 MANUFACTURERS' FIELD SERVICES

A. When specified in individual specification sections, require material or product suppliers or manufacturers to provide qualified staff personnel to observe site conditions, conditions of surfaces and installation, quality of workmanship, start-up of equipment, test, adjust and balance of equipment as applicable, and to initiate instructions when necessary.

B. Submit qualifications of observer to the Contract Administrator 30 days in advance of required observations.

C. Report observations and site decisions or instructions given to applicators or installers that are supplemental or contrary to manufacturers' written instructions.

D. Refer to Section 01330 - SUBMITTAL PROCEDURES, MANUFACTURERS' FIELD

REPORTS article.

01400 - 4

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

3.1 EXAMINATION

A. Verify existing site conditions, controlled environment, protective measures and substrate surfaces are acceptable for subsequent Work. Beginning new Work means acceptance of existing conditions.

B. Verify existing substrate is capable of structural support or attachment of new Work being applied or attached.

C. Examine and verify specific conditions described in individual specification sections.

Notify the Contract Administrator and the Clerk of the Works of conditions, which prevent start of work.

D. Verify utility services are available, of correct characteristics, and in correct locations.

3.2 PREPARATION

A. Maintain specific environmental controls required in individual sections.

B. Clean substrate surfaces prior to applying next material or substance.

C. Seal cracks or openings of substrate prior to applying next material or substance.

D. Apply manufacturer required or recommended substrate primer, sealer, or conditioner prior to applying new material or substance in contact or bond.

Temporary Facilities and Controls

01500 - 1

SECTION 01500

TEMPORARY FACILITIES AND CONTROLS

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Temporary Utilities:

1. Temporary electricity.

2. Temporary lighting for construction purposes.

3. Temporary heating.

4. Temporary ventilation.

5. Temporary water service.

6. Temporary sanitary facilities.

B. Construction Facilities:

1. Field offices and sheds.

2. Vehicular access.

3. Parking.

4. Progress cleaning and waste removal.

5. Traffic regulation.

C. Temporary Controls:

1. Security.

2. Dust.

3. Noise Control.

4. Removal of Utilities, Facilities, and Controls.

D. All work completed herein must conform to applicable state, federal requirements, and guidelines at the Contractor’s expense as is necessary to complete the Work.

1.2 TEMPORARY ELECTRICITY

A. State will pay cost of energy used. Exercise measures to conserve energy. Utilize State’s existing power service.

1.3 TEMPORARY LIGHTING FOR CONSTRUCTION PURPOSES

A. Permanent building lighting may be utilized during construction.

1.4 TEMPORARY HEATING

A. Provide and pay for heating devices and heat as needed to maintain specified conditions for construction operations.

B. Contractor will pay cost of temporary heat and temporary heat devices when the permanent heating devices are not functional. Work shall not be done in the seasonal heating season.

01500 - 2

1.5 TEMPORARY VENTILATION

A. Ventilate enclosed areas to achieve curing of materials, to dissipate humidity, and to prevent accumulation of dust, fumes, vapors, or gases.

B. Utilize existing ventilation equipment. Extend and supplement equipment with temporary fan units as required to maintain clean air for construction operations.

1.6 TEMPORARY WATER SERVICE

A. State will pay cost of temporary water. Exercise measures to conserve energy. Utilize

State's existing water system, extend and supplement with temporary devices as needed to maintain specified conditions for construction operations.

1.7 TEMPORARY SANITARY FACILITIES

A. Provide and maintain required facilities and enclosures. Existing facility use is not permitted. Provide facilities at time of project mobilization.

1.8 ON SITE STORAGE

A. Storage Areas: Existing space within the Courthouse may be utilized for storage. If additional storage is necessary, the Contractor shall provide exterior storage units as required.

B. Maintenance And Cleaning:

1. Maintain approach walks free of mud, water, and snow.

C. Removal: At completion of Work remove storage boxes and debris. Restore areas.

1.9 VEHICULAR ACCESS

A. Location as approved by the Contract Administrator in consultation with the Owner.

B. Maintain and do not block existing driveways.

C. Provide and maintain access to fire hydrants and control valves free of obstructions.

1.10 PARKING

A. Arrange for surface parking areas to accommodate construction personnel from the City on adjacent streets as necessary.

B. Use of designated areas of existing parking facilities used by construction personnel is not permitted unless previously approved by the Contract Administrator.

C. Do not allow heavy vehicles or construction equipment in parking areas.

01500 - 3

1.11 PROGRESS CLEANING AND WASTE REMOVAL

A. Maintain areas free of waste materials, debris, and rubbish. Maintain site in clean and orderly condition.

B. Remove debris and rubbish from pipe chases, plenums, attics, crawl spaces, and other closed or remote spaces, prior to enclosing spaces.

C. Broom and vacuum clean interior areas prior to start of surface finishing and continue cleaning to eliminate dust.

D. Collect and remove waste materials, debris, and rubbish from site and dispose off-site.

1.12 SECURITY

A. Security Program:

1. Protect Work existing premises from theft, vandalism, and unauthorized entry.

2. Initiate program in coordination with State's existing security system at project mobilization.

1.13 DUST CONTROL

A. Execute Work by methods to minimize raising dust from construction operations.

B. Provide positive means to prevent air-borne dust from dispersing into atmosphere.

1.14 NOISE CONTROL

A. Provide methods, means, and facilities to minimize noise produced by construction operations.

1.15 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS

A. Remove temporary utilities, equipment, facilities, materials, prior to Substantial

Completion inspection.

B. Clean and repair damage caused by installation or use of temporary work.

C. Restore existing facilities used during construction to original condition. Restore permanent facilities used during construction to specified condition.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

01500 - 4

Construction Waste Management and Disposal

01505 - 1

SECTION 01505

CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

PART 1 GENERAL

1.1 SUMMARY

A. Section Includes:

1. Construction waste management plan.

2. Construction waste recycling.

3. Construction waste adaptive reuse.

1.2 PLAN REQUIREMENTS

A. Construction Waste Management Plan shall be developed with the following intent:

1. Divert construction, demolition, and land clearing debris from landfill disposal.

2. Redirect recyclable material back to manufacturing process.

B. Develop and implement a Construction Waste Management plan to be reviewed by the

Contract Administrator for compliance with the following

1. Divert 75 % of Project generated waste from landfills.

1.3 SUBMITTALS

A. Section 01330 - Submittal Procedures: Requirements for submittals.

B. Construction Plan: Submit construction waste management plan describing methods and procedures for implementation and monitoring compliance including the following:

1. Project specific analysis of the projected jobsite waste to be generated. Include materials and estimated quantities (weight/volume) of projected waste.

2. Construction waste materials anticipated for recycling and adaptive reuse.

3. On site sorting and site storage methods.

4. Name and location of landfill(s) to be used.

5. Certification from the landfill of ability to receive the types of waste to be generated and of sufficient capacity to accept the waste.

6. Transportation company hauling construction waste to waste processing facilities.

7. Recycling and adaptive reuse processing facilities and waste type each facility will accept.

C. Submit documentation with each application for payment substantiating that the construction waste management plan goals are being achieved. Include the following information:

1. Material category

2. Trash: Quantity by weight deposited in landfills.

01505 - 2

3. Salvaged, recovered and recycled material: Quantity by weight with destination for each type of material salvaged or recovered for resale, recycling, or adaptive reuse.

1.4 CLOSEOUT SUBMITTALS

A. Section 01700 - Execution Requirements: Requirements for submittals.

B. Waste Management final report: Prior to Completion, submit a written Waste

Management Final report summarizing the types and quantities of materials recycled and disposed of under the Waste Management Plan. Include the name and location of disposal facilities. Include the following:

1. Material category

2. Total quantity of waste, by weight

3. Quantity of waste salvaged, both estimated and actual, by weight

4. Quantity of waste recycled, both estimated and actual, by weight

5. Total quantity of waste recovered (salvaged plus recycled) as a percentage of total waste. ( Compare to minimum requirement of 75% by weight of waste.)

1.5 CONSTRUCTION WASTE MANAGEMENT PLAN

A. Construction Waste Landfill Diversion: Minimum 75 percent by weight of construction waste materials for duration of Project through resale, recycling, or adaptive reuse.

B. Implement construction waste management plan at start of construction.

C. Review construction waste management plan at pre-construction meeting and progress meetings.

D. Distribute the Construction Waste Management Plan to subcontractors and others affected by Plan Requirements.

E. Oversee plan implementation, instruct construction personnel for plan compliance, and document plan results.

F. Manager: The Contractor shall designate on-site personnel responsible for instructing workers and overseeing and documenting results of the Waste Management Plan for the

Project.

1.6 CONSTRUCTION WASTE RECYCLING

A. Use source separation method or co-mingling method suitable to sorting and processing method of selected recycling center.

B. Source Separation Method: Recyclable materials separated from trash and sorted into separate bins or containers, identified by waste type, prior to transportation to recycling center.

01505 - 3

C. Co-Mingling Method: Recyclable materials separated from trash and placed in unsorted bins or container for sorting at recycling center.

D. Materials recommended for recycling include:

1. Packing materials including paper, cardboard, foam plastic, and sheeting.

2. Recyclable plastics.

3. Organic plant debris.

4. Earth materials.

5. Native stone and granular fill.

6. Concrete and Asphalt paving.

7. Wood with and without embedded nails and staples.

8. Glass, clear and colored types.

9. Metals.

10. Gypsum products.

11. Acoustical ceiling tile.

12. Carpeting.

13. Equipment oil.

PART 2 PRODUCTS - Not Used

PART 3 EXECUTION

3.1 CONSTRUCTION WASTE COLLECTION

A. Collect construction waste materials in containers identified for specific waste materials and arrange for transportation to recycling centers or adaptive salvage and reuse processing facilities.

B. Maintain recycling and adaptive reuse storage and collection area in orderly arrangement with materials separated to eliminate co-mingling of materials required to be delivered separately to waste processing facility.

C. Store construction waste materials to prevent environmental pollution, fire hazards, hazards to persons and property, and contamination of stored materials.

D. Cover construction waste materials subject to disintegration, evaporation, settling, or runoff to prevent polluting air, water, and soil when not in use.

E. . Recycling and waste bin areas are to be kept neat and clean and clearly marked in order to avoid contamination of materials. Location shall be acceptable to the Contract

Administrator.

3.2 CONSTRUCTION WASTE DISPOSAL

A. Deliver construction waste to waste processing facilities. Obtain receipt for deliveries.

01505 - 4

B. Dispose of construction waste, not capable of being recycled or adaptively reused, by delivery to landfill, incinerator, or other legal disposal facility. Obtain receipt for deliveries.

Execution Requirements

01700 - 1

SECTION 01700

EXECUTION REQUIREMENTS

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Closeout procedures.

B. Final cleaning.

C. Starting of systems.

D. Demonstration and instructions.

E. Testing, adjusting and balancing.

F. Protecting installed construction.

G. Project record documents.

H. Operation and maintenance data.

I. Manual for materials and finishes.

J. Manual for equipment and systems.

K. Spare parts and maintenance products.

L. Product warranties and product bonds.

M. Maintenance service.

N. Guarantee of work.

1.2 CLOSEOUT PROCEDURES

A. Submit a signed Substantial Completion Application attesting that the Contract

Documents have been reviewed, Work has been inspected, and that all Work is complete in accordance with Contract Documents and ready for Contract Administrator review.

The Substantial Completion Application for use by the Contractor is attached to the end of this specification section. The Contract Administrator may modify this Agreement to accommodate any changes in Work.

1. Provide submittals to the Contract Administrator as required by the Contract

Documents and as required by authorities having jurisdiction.

01700 - 2

B. Only after completion of all Punch List items and submission of all items the Contractor shall submit a Final Application for Payment identifying total adjusted Contract Sum, previous payments, and sum remaining due.

1.3 FINAL CLEANING

A. Execute final cleaning prior to final project assessment.

B. Clean equipment and fixtures to sanitary condition with cleaning materials appropriate to surface and material being cleaned.

C. Replace filters of operating equipment.

D. Remove waste and surplus materials, rubbish, and construction facilities from site.

1.4 STARTING OF SYSTEMS

A. Coordinate schedule for start-up of various equipment and systems.

B. Notify the Contract Administrator seven days prior to start-up of each item.

C. Verify each piece of equipment or system has been checked for proper lubrication, drive rotation, belt tension, control sequence, and for conditions which may cause damage.

D. Verify tests, meter readings, and specified electrical characteristics agree with those required by equipment or system manufacturer.

E. Verify wiring and support components for equipment are complete and tested.

F. Execute start-up under supervision of applicable manufacturer's representative in accordance with manufacturers' instructions.

G. When specified in individual specification Sections, require manufacturer to provide authorized representative to be present at site to inspect, check, and approve equipment or system installation prior to start-up, and to supervise placing equipment or system in operation.

1.5 DEMONSTRATION AND INSTRUCTIONS

A. Demonstrate operation and maintenance of products to State's personnel two weeks prior to date of Substantial Completion.

B. For equipment or systems requiring seasonal operation, perform demonstration for other season within six months.

C. Utilize operation and maintenance manuals as basis for instruction. Review contents of manual with State's personnel in detail to explain all aspects of operation and maintenance.

01700 - 3

D. Demonstrate start-up, operation, control, adjustment, trouble-shooting, servicing, maintenance, and shutdown of each item of equipment at agreed time, at equipment designated location.

E. Prepare and insert additional data in operations and maintenance manuals when need for additional data becomes apparent during instruction.

F. Required instruction time for each item of equipment and system is specified in individual sections.

1.6 TESTING, ADJUSTING AND BALANCING

A. Perform services specified in Section 23 00 00.

B. Reports will be submitted by independent firm to the Contract Administrator indicating observations and results of tests and indicating compliance or non-compliance with requirements of Contract Documents.

1.7 PROTECTING INSTALLED CONSTRUCTION

A. Protect installed Work and provide special protection where specified in individual specification sections.

B. Provide temporary and removable protection for installed products. Control activity in immediate work area to prevent damage.

C. Provide protective coverings at walls, projections, jambs, sills, and soffits of openings.

D. Protect finished floors, stairs, and other surfaces from traffic, dirt, wear, damage, or movement of heavy objects, by protecting with durable sheet materials.

E. Prohibit traffic or storage upon waterproofed or roofed surfaces. When traffic or activity is necessary, obtain recommendations for protection from waterproofing or roofing material manufacturer.

F. Prohibit traffic from landscaped areas.

1.8 PROJECT RECORD DOCUMENTS

A. Maintain on site one set of the following record documents; record actual revisions to the

Work:

1. Drawings.

2. Specifications.

3. Addenda.

4. Change Orders and other modifications to the Contract.

5. Reviewed Shop Drawings, Product Data, and Samples.

6. Manufacturer's instruction for assembly, installation, and adjusting.

B. Ensure entries are complete and accurate, enabling future reference by State.

01700 - 4

C. Store record documents separate from documents used for construction.

D. Record information concurrent with construction progress, not less than weekly.

E. Specifications: Legibly mark and record at each product section description of actual products installed, including the following:

1. Manufacturer's name and product model and number.

2. Product substitutions or alternates utilized.

3. Changes made by Addenda and modifications.

F. Record Drawings and Shop Drawings: Legibly mark each item to record actual construction including:

1. Measured depths of foundations in relation to finish [first] [main] floor datum.

2. Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements.

3. Measured locations of internal utilities and appurtenances concealed in construction, referenced to visible and accessible features of the Work.

4. Field changes of dimension and detail.

5. Details not on original Contract drawings.

G. Submit documents to the Contract Administrator at time of Substantial Completion.

1.9 OPERATION AND MAINTENANCE DATA

A. Submit data bound in 8-1/2 x 11 inch (A4) text pages, three D side ring binders with durable plastic covers.

B. Prepare binder cover with printed title "OPERATION AND MAINTENANCE

INSTRUCTIONS", title of project, and subject matter of binder when multiple binders are required.

C. Internally subdivide binder contents with permanent page dividers, logically organized as described below; with tab titling clearly printed under reinforced laminated plastic tabs.

D. Drawings: Provide with reinforced punched binder tab. Bind in with text; fold larger drawings to size of text pages.

E. Contents: Prepare Table of Contents for each volume, with each product or system description identified, typed on white paper, in three parts as follows:

1. Part 1: Directory, listing names, addresses, and telephone numbers of Architect, Engineer(s), Contractor, Subcontractors, and major equipment suppliers.

2. Part 2: Operation and maintenance instructions, arranged by specification section

For each category, identify names, addresses, and telephone numbers of

Subcontractors and suppliers. Identify the following:

a. Significant design criteria.

b. List of equipment.

c. Parts list for each component.

d. Operating instructions.

e. Maintenance instructions for equipment and systems.

3. Part 3: Project documents and certificates, including the following:

01700 - 5

a. Shop drawings and product data.

b. Balance reports.

c. Certificates.

d. Originals of warranties and bonds.

1.10 MANUAL FOR MATERIALS AND FINISHES

A. Submit two copies of preliminary draft or proposed formats and outlines of contents before start of Work. The Contract Administrator will review draft and return one copy with comments.

B. For equipment, or component parts of equipment put into service during construction and operated by State, submit documents within ten days after acceptance.

C. Submit two copies of completed volumes 15 days prior to Substantial Completion. Draft copy be reviewed and returned after Substantial Completion, with Architect/Engineer comments. Revise content of document sets as required prior to final submission.

D. Submit two sets of revised final volumes in final form prior to final inspection.

E. Building Products, Applied Materials, and Finishes: Include product data, with catalog number, size, composition, and color and texture designations. Include information for re-ordering custom manufactured products.

F. Instructions for Care and Maintenance: Include manufacturer's recommendations for cleaning agents and methods, precautions against detrimental agents and methods, and recommended schedule for cleaning and maintenance.

G. Moisture Protection and Weather Exposed Products: Include product data listing applicable reference standards, chemical composition, and details of installation. Include recommendations for inspections, maintenance, and repair.

H. Additional Requirements: As specified in individual product specification sections.

I. Include listing in Table of Contents for design data, with tabbed fly sheet and space for insertion of data.

1.11 MANUAL FOR EQUIPMENT AND SYSTEMS

A. Submit one copy of preliminary draft or proposed formats and outlines of contents before start of Work. Contract Administrator will review draft and return one copy with comments.

B. For equipment, or component parts of equipment put into service during construction and operated by State, submit documents within ten days after acceptance.

C. Submit one copy of completed volumes 15 days prior to Substantial Completion. Draft copy be reviewed and returned after Substantial Completion, with Architect/Engineer comments. Revise content of document sets as required prior to final submission.

01700 - 6

D. Submit two sets of revised final volumes in final form prior to final inspection.

E. Each Item of Equipment and Each System: Include description of unit or system, and component parts. Identify function, normal operating characteristics, and limiting conditions. Include performance curves, with engineering data and tests, and complete nomenclature and model number of replaceable parts.

F. Include color coded wiring diagrams as installed.

G. Operating Procedures: Include start-up, break-in, and routine normal operating instructions and sequences. Include regulation, control, stopping, shut-down, and emergency instructions. Include summer, winter, and special operating instructions.

H. Maintenance Requirements: Include routine procedures and guide for preventative maintenance and trouble-shooting; disassembly, repair, and reassembly instructions; and alignment, adjusting, balancing, and checking instructions.

I. Include servicing and lubrication schedule, and list of lubricants required.

J. Include manufacturer's printed operation and maintenance instructions.

K. Include sequence of operation by controls manufacturer.

L. Include original manufacturer's parts list, illustrations, assembly drawings, and diagrams required for maintenance.

M. Include control diagrams by controls manufacturer as installed.

N. Include Contractor's coordination drawings, with color coded piping diagrams as installed.

O. Include charts of valve tag numbers, with location and function of each valve, keyed to flow and control diagrams.

P. Include list of original manufacturer's spare parts, current prices, and recommended quantities to be maintained in storage.

Q. Include test and balancing reports as specified in Section 01400.

R. Additional Requirements: As specified in individual product specification sections.

S. Include listing in Table of Contents for design data, with tabbed dividers and space for insertion of data.

1.12 SPARE PARTS AND MAINTENANCE PRODUCTS

A. Furnish spare parts, maintenance, and extra products in quantities specified in individual specification sections.

01700 - 7

B. Deliver to Project site and place in location as directed by State; obtain receipt prior to final payment.

1.13 PRODUCT WARRANTIES AND PRODUCT BONDS

A. Obtain warranties and bonds executed in duplicate by responsible subcontractors, suppliers, and manufacturers, within ten days after Substantial Completion. All warranties start dates shall be the Substantial Completion Date, if project is phased all warranties to start at the date of Substantial Completion of each phase.

B. Execute and assemble transferable warranty documents and bonds from subcontractors, suppliers, and manufacturers.

C. Verify documents are in proper form, contain full information, and are notarized.

D. Co-execute submittals when required.

E. Include Table of Contents and assemble in three D side ring binder with durable plastic cover.

F. Submit prior to final Application for Payment.

G. Time Of Submittals:

1. For equipment or component parts of equipment put into service during construction with State's permission, submit documents within ten days after acceptance.

2. Make other submittals within ten days after Date of Substantial Completion, prior to final Application for Payment.

3. For items of Work for which acceptance is delayed beyond Date of Substantial

Completion, submit within ten days after acceptance, listing date of acceptance as beginning of warranty or bond period.

1.14 MAINTENANCE SERVICE

A. Furnish service and maintenance of components indicated in specification sections during warranty period.

B. Examine system components at frequency consistent with reliable operation. Clean, adjust, and lubricate as required.

C. Include systematic examination, adjustment, and lubrication of components. Repair or replace parts whenever required. Use parts produced by manufacturer of original component.

D. Do not assign or transfer maintenance service to agent or Subcontractor without prior written consent of State.

01700 - 8

1.15 GUARANTEE OF WORK

A. Except as otherwise specified, all work shall be guaranteed by the Contractor against defects resulting form the use of inferior materials, equipment or workmanship for one

(1) year from the Date of Substantial Completion of the work.

B. If, within any guarantee period, repairs or changes are required in connection with guaranteed work, which in the opinion of the Contract Administrator, is rendered necessary as a result of the use of materials, equipment or workmanship which are inferior, defective, or not in accordance with the terms of the Contract shall, promptly upon receipt of notice from the Commissioner, and at his own expense:

1. Place in satisfactory condition in every particular, all such guaranteed work, correct all defects therein.

2. Make good all damage to the building or site, or equipment or contents thereof, which in the opinion of the Contract Administrator, is the result of the use of materials, equipment or workmanship which are inferior, defective, or not in accordance with the terms of the Contract.

3. Make good any work or material, or the equipment and contents of said building or site disturbed in fulfilling any such guarantee.

C. In any case, wherein fulfilling the requirements of the Contract or of any guarantee, embraced in or required thereby, the Contractor disturbs any work guaranteed under another contract, he shall restore such disturbed work to a condition satisfactory to the

Contract Administrator and guarantee such restored work to the same extent as it was guaranteed under such other contracts.

D. If the Contractor, after notice, fails to proceed promptly to comply with the terms of the guarantee, the Commissioner may have the defects corrected and the Contractor and his/her Surety shall be liable for all expense incurred.

E. All special guarantees applicable to definite parts of the work that may be stipulated in the Specifications or other papers forming a part of the Contract shall be subject to the term of this paragraph during the first year of the life of such special guarantee.

F. Failure to adhere to guarantee terms may result in suspension or barring from the prequalification list, or, alternatively, the requirement of a Letter of Credit or other guaranty equal to a percentage of the Contract amount.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

Charles M.

Arlinghaus

Commissioner

(603) 271-3201

State of New Hampshire

DEPARTMENT OF ADMINISTRATIVE SERVICES

25 Capitol Street – Room 120 Concord, New Hampshire 03301

Joseph B. Bouchard Assistant

Commissioner

(603) 271-3204

Catherine A. Keane Deputy Commissioner

(603) 271-2059

Substantial Completion Application

SUBSTANTIAL COMPLETION APPLICATION

Date:

Project Title: Portsmouth Circuit Court Boilers Project Number: 81224 Contract: D

Instructions: The items checked below are required to be completed, operational and documented in order for the project to be declared Substantially Complete. If Substantial Completion is anticipated on a portion of the work, the sequence and portions of the project shall be identified and the selected items below will be required for each substantial completion area. The Contractor shall submit this document, with attachments, to the Contract Administrator for review to determine if the terms of Substantial Completion have been met. If the terms have been met, the Contract Administrator will issue a Certificate of Substantial Completion. If the terms have not been met, the Contract Administrator will notify the Contractor of missing, incomplete, or incorrect items.

PART 1 STATE AND LOCAL REQUIREMENTS:

In addition to the requirements of the Construction Documents, Substantial Completion requires the following identified items be fully completed, executed, approved with certifications attached to this document. The Contractor is required to arrange and pay for all inspections and fees.

1.1 State of NH Office of the State Fire Marshal:

A. Certificate of Occupancy.

B. Modular Building Certificate

1.2 State of NH Office of the State Fire Marshal and Local Fire Official:

A. Sprinkler system. Reference NFPA 13 – Contractor’s Material and Test Certificate for Aboveground Piping Form.

B. Fire detection and notification system. Reference NFPA 72 – Inspection and Testing Form

C. Range hood and fire suppression system.

D. Emergency lighting and exit signs.

E. Oil fired equipment.

F. Other (list): Gas Fired Equipment

1.3 State of NH Department of Labor Division of Boilers and Elevators:

A. Elevator Inspection Certificate.

B. Boiler Inspection Certificate.

Substantial Completion Application

C. Pressure Vessel Certificate.

1.4 Local Building Inspection Department:

A. Building Permit.

1.5 State of NH Plumber’s Licensing Board and Local Building Inspection Department:

A. Plumbing Inspections.

1.6 State of NH Electrician Board and Local Building Inspection Department:

A. Electrical Inspections.

1.7 State of NH Department of Environmental Services and Local Building Inspection Department:

A. Approved Underground/Above Ground Tank Approved Registration Form.

B. Approved Underground/Above Ground Storage Tank Closure Notification Form.

C. Septic System Operation Approval.

D. Water System Operation Approval.

E. Statement of Certification that compliance with the Clean Indoor Air in State Buildings, ENV A-2200 has been met.

F. Other (list):

1.8 Other (list):

A. Other (list):

PART 2 CONTRACTOR’S REQUIREMENTS

In addition to the requirements of the Construction Documents, Substantial Completion requires the following identified items be fully completed, executed, approved with certifications attached to this document. The Contractor is required to arrange and pay for all inspections and fees.

2.1 Contractor has completed and verified the following:

A. Building egress and exit paths are clear of construction materials and equipment.

B. All building systems are functional and correctly operating.

C. Other (list):

2.2 Contractor has furnished the required Documents, Training and Manuals:

A. Field Record Drawings with markings.

B. Building systems operations and maintenance manuals.

C. Spare parts and extra materials stocks as per specifications.

D. Final Punch List as required by the General Conditions (Failure to include incomplete Work does not relieve the Contractor of the responsibility to complete or correct the Work)

E. Hazardous Waste Shipment Record (WSR).

F. Hazardous Material Abatement/Remediation Report.

Substantial Completion Application

G. NFPA Fire Alarm Record of Completion Form.

H. Clean Air Report.

I. Agency facility personnel have been trained as per specifications.

J. Other (list):

2.3 Construction Inspection Services:

A. Copies of all inspection reports are provided and corrections are documented as satisfactory.

B. Other (list):

2.4 Miscellaneous:

A. Identify Warranties that begin on a date other than the Substantial Completion date: (list below)

B. Other (list):

CERTIFICATION:

I hereby certify that Substantial Completion has been accomplished as defined in the General Conditions and in conformance with the requirements of the Contract. This certification declares that:

A. The work that remains to be completed after substantial completion is minor in scope and nature and is not disruptive to the function of the facility occupants and is limited to minor items required to finalize the project and is not an item specifically identified above.

B. All other requirements of the Contract related to Substantial Completion have been accomplished, to include review and acceptance of all operational and maintenance manuals, record drawings, maintenance training, warrantee certificates and start up activities.

SPECIAL CONDITIONS OR STIPULATIONS CONCERNING THE COMPLETION OF PUNCH LIST ITEMS OR

EXPLANATIONS OF SUBSTANTIAL COMPLETION:

Contractor Certification does not confer approval to occupy the facility.

Contractor By: Date

01100 Summary.pdf
RFB 2945-25 -- Circuit Courts Boiler Removal and Installation Services - Attachment 1 - Project Execution Requirements.pdf
RFB XXXX-25 -- Circuit Courts Boiler Removal and Installation Services - Attachment 1 - Project Execution Requirements.pdf
RFB XXXX-25 -- Circuit Courts Boiler Removal and Installation Services - Attachment 1 - Project Execution Requirements.pdf
RFB XXXX-25 -- Courts Boiler Removal and Installation - Attachment 1 - Project Execution Requirements.pdf
01400 Quality Requirements.pdf
01500 Temporary Facilities & Controls.pdf
01505 Construction Waste Requirements.pdf
01700 Execution Requirements.pdf
Substantional Completion Form.pdf
_Combined Front End
01700 Execution Requirements -2
SUBSTANTIAL COMPLETION APPLICATION
PART 1 STATE AND LOCAL REQUIREMENTS:
1.1 State of NH Office of the State Fire Marshal:
1.2 State of NH Office of the State Fire Marshal and Local Fire Official:
1.3 State of NH Department of Labor Division of Boilers and Elevators:
1.4 Local Building Inspection Department:
1.5 State of NH Plumber’s Licensing Board and Local Building Inspection Department:
1.6 State of NH Electrician Board and Local Building Inspection Department:
1.7 State of NH Department of Environmental Services and Local Building Inspection Department:
1.8 Other (list):
PART 2 CONTRACTOR’S REQUIREMENTS
2.1 Contractor has completed and verified the following:
2.2 Contractor has furnished the required Documents, Training and Manuals:
2.3 Construction Inspection Services:
2.4 Miscellaneous: