Attachment 1 - B118_PWS_REPLACE VCT_WITH_LVP_31JUL24.pdf
PDF 252 KB Posted
- Attached to
- LRAFB B118 Flooring Replacement Federal contract opportunity
- Solicitation number
- W50S6P24QA012
- Issued by
- Department of the Army National Guard
About this file
This document is a Performance Work Statement (PWS) for a federal contract opportunity to remove and replace vinyl composition tile (VCT), ceramic tile, and floor base in selected areas of Building 118 at Little Rock Air Force Base with new luxury vinyl planks (LVP), transition strips, and resilient floor base.
The key details are: the contractor must remove and dispose of approximately 3,300 SF of VCT and 200 SF of ceramic tile, install 3,200 SF of new Mohawk Group LVP flooring and 1,600 LF of new Roppe resilient floor base, and install transition strips where the new LVP meets existing flooring. The contractor must provide written verification of materials and procedures, ensure compliance with safety regulations, and provide 5% replacement stock. All work must be completed during normal business hours on normal workdays. The related federal contract opportunity, Solicitation Number W50S6P24QA012, requires submission of quotes by 3:00 PM CST on August 30, 2024, with the contract awarded to the responsible offeror whose quote conforms to the solicitation and is the most advantageous to the Government, price and other factors considered.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 1 - B118_PWS_REPLACE VCT_WITH_LVP_20AUG24_.pdf | ||
| Questions and Answers_21AUG24.pdf | ||
| W50S6P24QA012_Amend 1.pdf | ||
| W50S6P24QA012.pdf | ||
| Attachment 3 - SCA 2015-5117 rev 25.pdf | ||
| Mohawk _Roppe_Brand_Name_Justification_8JUN24_3_Redacted.pdf | ||
| Attachment 2 - Provisions and Clauses.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement
Replace VCT with LVP in Bldg 118
***Current as of 31 July 2024***
The general requirement for the project is to remove and dispose of all vinyl composition tile
(VCT), ceramic tile, and floor base in the selected areas of Building 118 and replace with new luxury vinyl planks (LVP), new transition strips, and new resilient floor base.
1. In the selected areas of Building 118 (See Attachment 1) remove and dispose of approximately 3,300 SF of VCT and 200 SF of Ceramic Tile, all associated transition strips, and approximately 1,600 LF of resilient floor base. Take special care to not damage the existing wall finishes. Some areas have wallpaper or other finishes that are not repairable if damaged.
a. Remove all excess glue as necessary from wall and floor.
b. Provide any necessary floor leveling in accordance with the manufacture’s recommendations.
c. Install new LVP in approximately 3,200 SF of the designated areas of Building 118.
Flooring shall be glued using appropriate adhesive glue and shall not use sticky strips.
i. Manufacture: Mohawk Group
ii. Size: 18”x36”
iii. Type: Hot and Heavy Collection (Previously Mass Appeal Collection)
iv. Style: Metal
v. Color: 859 On the Line
d. Install approximately 1,600 LF new floor base meeting the following criteria:
i. Manufacturer: Roppe
ii. Height: 4” For normal wall areas. 6” for stair treads and where Ceramic
Tile wall base is removed.
iii. Type: Standard Base with Toe
iv. Color: #123 Charcoal
v. Floor base shall consist of “roll” or “coil” material, NOT 4’ strips. The number of joints in the installation shall be minimized.
e. Install transition strips at locations where new LVP meets existing flooring to remain and where new LVP meets bare concrete flooring in adjacent rooms/hallways.
i. Transition strips shall be Roppe Color #123 of appropriate type for transition to the existing surface and attached to the floor in accordance with the manufacturer recommendations.
Additional Information
1. Location/extent of work: selected locations within Building 118 as shown in the attached drawing. Please note: approximate dimensions and total floor areas are provided only to aid in describing the general scope of the project; contractor shall field verity all dimensions / quantities and bids shall be based on field verified quantities.
2. Work Schedule: All work must take place between the hours of 0700 and 1700 on and during normal workdays. No work to be scheduled on weekends or Federal Holidays.
3. Material Verification Requirement: Written verification that the products and procedures outlined in this Statement of Work must be provided to the Contracting Officer a minimum of 10 working days prior to beginning work on this project – an email verification will be acceptable. At a minimum, the written material verification and work plan shall include confirmation of the following:
a. Work schedule
b. Luxury Vinyl Planks that will be used on project
c. Tile Glue that will be used on project
d. Resilient Floor Base that will be used on project
e. Resilient Floor Base Glue that will be used on project
f. Floor Leveler that will be used on project
g. Transition strips that will be used on project
h. Transition strip installation method that will be used on project
4. Provide 5% replacement stock: Provide a minimum of 5% matching spare LVP to allow for future replacement of damaged tiles.
5. Techniques and procedures: Conduct all prep work and LVP / resilient floor base installation in accordance with the manufacture’s recommendations and standard installation practices.
6. To ensure adherence to the requirements are in this performance work statement (PWS), the contractor shall have a superintendent/ foreman on-site during all phases of installation. The superintendent/ foreman must have the authority to make decisions on behalf of the contractor regarding the contract requirements.
7. Safety regulations: It is the Contractor’s responsibility to ensure that all work is conducted in compliance with applicable base, local, state, and Federal safety regulations.
8. Access and General Protection/Security Policy and Procedures
a. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting
Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency
Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes. VC
b. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center
Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB)
(AFI 10-245, AFI 31-101 and AFMAN 31-113), applicable installation, facility and area commander installation/facility access and local security policies and procedures
(provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
1 Attachment:
Tile Replacement Scope
ATTACHMENT 1: TILE REPLACEMENT SCOPE
B 118 First Floor
Legend:
Remove VCT & Place New LVP & Floor Base Remove VCT – Install New Floor Base Only Remove & Replace Floor Base Only Remove Ceramic Tile & Place New LVP & Floor Base
6” Cove Base on Face of Stair Risers
New 4” Cove Base on Concrete Landings
New 4” Cove Base on Concrete Landings
6” Cove Base Where Tile Base is Removed
B 118 Second Floor
Legend:
Remove VCT & Place New LVP & Floor Base Remove VCT – Install New Floor Base Only Remove & Replace Floor Base Only
No Work Above 2nd Floor Landing
New 4” Cove Base on Concrete Landings
New 4” Cove Base on Concrete Landings