Attachment 1- AQRC262050 - Replace Alert Generator - SOW.pdf
PDF 620 KB Posted
- Attached to
- Alert Generator
- Solicitation number
- W50S8F26QA017
- Issued by
-
Department of the Army National Guard
About this file
Statement of Work Summary
This is a Statement of Work (SOW) for the Air National Guard's 177th Civil Engineer Squadron at Egg Harbor, New Jersey, for Project Number AQRC262050, dated May 12, 2026. The project involves the removal and replacement of an existing 750kW emergency diesel generator system at the Alert Complex (Buildings 456, 457, 458, 459, and 461) to ensure continuous power support for mission-critical operations.
The vendor must furnish and install a new 750kW industrial diesel generator with the following specifications: three-phase 277/480 VAC, 60 Hz, integrated fuel tank with minimum 40 hours runtime (Generac model SD750 or approved equal), and aluminum weather-protected enclosure. Installation and testing must be performed by a licensed electrician. The vendor is responsible for removing the existing generator and belly tank (after the Government removes fuel), replacing the deck structure with composite decking, and coordinating the new generator with the existing ASCO 7000 series Automatic Transfer Switch, including ATS testing, turn-up, commissioning, and verification of proper communication and transfer functionality. The vendor must also provide operational training to Government personnel, manufacturer-recommended installation diagrams, and product data submissions, allowing 14 business days for Government review. All work must comply with manufacturer instructions, industry standards, and applicable safety/environmental regulations, with coordination required at least 7 business days prior to mobilization. Final acceptance requires complete installation, successful integrated testing, submission of all documentation, Government inspection and approval, and site restoration, with the vendor providing a minimum one-year warranty on workmanship and manufacturer warranties for all components. Work hours are Monday to Friday 0700 to 1530, with the vendor unable to access the base on Federal Holidays and base Scheduled Days Off.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CUI
STATEMENT OF WORK
AIR NATIONAL GUARD
177th CIVIL ENGINEER SQUADRON
EGG HARBOR, NEW JERSEY
PROJECT: Replace Alert Generator
PROJECT NUMBER: AQRC262050
DATE: May 12, 2026
The project to include the Replacement of the emergency power system at the Alert Complex (Bldgs 456, 457, 458, 459, and 461) to ensure continuous support to mission critical operations.
Removal of the existing 750kW generator and belly tank, installation of a new 750kW generator with integrated fuel tank, electrical connection to existing automatic transfer switch.
1377270769C CUI-CE Rojas
Table of Content:
1. Vendor Responsibilities
2. Project Description
3. Administrative - Submittals
4. Coordination and Access Requirements
5. Environmental and Safety Requirements
6. Cleanup
7. Final Acceptance and Warranty
1. VENDOR RESPONSIBILITIES
1.1. The Vendor shall furnish all labor, equipment, tools and material, transportation, and supervision necessary to deliver and install a complete and operational generator system to the Government. All work and deliverables shall be in accordance with this Statement of Work (SOW), all associated documents and attachments, industry standards, Governing Codes and Federal Regulations (RFO FAR, RFO DFARS AND AFARS).
1.2. The Vendor shall submit to the Base Civil Engineer (BCE) for approval all documentation, installation diagrams, product data, and warranties.
1.3. Ensure all work complies with manufacturer instructions, industry standards, and applicable safety/environmental regulations.
1.4. All activities shall be coordinated with the Government, Contracting Officer Representative (COR), at least 7 business days before beginning work, to maintain uninterrupted mission operations.
2. PROJECT DESCRIPTION
2.1. The purpose of this project is to remove and replace existing 750kW generator and its associated parts at the Alert Complex (Bldgs 456, 457, 458, 459, 461)
2.2. Decking Replacement:
2.2.1. Remove existing deck structure and decking around generator.
2.2.2. Furnish and install composite decking and any required framing components per manufacturer recommendations.
2.2.3. Provide Product data and installation details for approval.
2.3. Generator Removal:
2.3.1. Disconnect and remove the existing generator and associated parts.
2.3.2. Government will remove fuel from belly tank prior to vendor work.
2.3.3. Backup power must remain available at all times.
2.4. New Generator Installation:
2.4.1. Vendor shall furnish and install a new industrial diesel generator meeting the following minimum specifications:
2.4.1.1. 750kW
2.4.1.2. Three-Phase 277/480 VAC
2.4.1.3. 60 Hz
2.4.1.4. Integrated fuel tank with minimum 40 hours runtime
2.4.1.4.1. Generac model SD750, or approved equal
2.4.1.5. Aluminum weather protected enclosure
2.4.1.6. Installation and testing performed by a licensed electrician..
2.4.1.7. Provide a certified technician to conduct operational training for Government personnel, including generator operations, emergency procedures, and routine maintenance requirements.
2.4.1.8. Coordinate the new generator with the existing ASCO 7000 series Automatic Transfer Switch including:
2.4.1.8.1. ATS testing
2.4.1.8.2. Turn-up
2.4.1.8.3. Commissioning
2.4.1.8.4. Verification of proper communication and transfer functionality.
2.5. Generator Testing must include full ATS functional testing to ensure the system transfers power correctly under load and returns to normal power without fault.
2.6. Vendor shall provide manufacturer-recommended installation diagrams, including:
2.6.1. Generator installation diagrams
2.6.2. Fuel tank installation diagrams
2.6.3. Composite decking installation details
2.6.4. Electrical connection diagrams
2.6.5. Startup, testing, and commissioning procedures
2.6.6. All documentation must be approved prior to installation.
3. ADMINISTRATIVE - Submittals
3.1. Vendor shall submit the following via email:
3.1.1. Generator product data and cut sheets
3.1.2. Composite decking product data
3.1.3. Installation diagrams
3.1.4. SDS for any materials brought on site
3.1.5. Warranty documentation
3.1.6. Startup and commissioning reports
3.1.7. Training materials for Government personnel
3.2. Allow 14 business days for Government review.
4. COORDINATION AND ACCESS REQUIREMENTS
4.1. Coordinate access with the COR and Bldg 459 building manager at least 7 business days prior to mobilization.
4.2. Hours of operations are Monday to Friday 0700 to 1530. Work outside normal hours is possible but requires prior coordination.
4.3. Vendor will NOT have access to the base on Federal Holidays and base Scheduled Days Off. Contractor must coordinate none working days with the COR. Holidays:
4.3.1. New Year`s Day – 1 January
4.3.2. Martin Luther King`s Birthday - Third Monday of January
4.3.3. President`s Day – Third Monday of February
4.3.4. Memorial Day – Last Monday of May
4.3.5. Juneteenth – June 19th
4.3.6. Independence Day – July 4th
4.3.7. Labor Day – First Monday in September
4.3.8. Columbus Day – Second Monday in October
4.3.9. Veteran`s Day – November 11th
4.3.10. Thanksgiving Day – Fourth Thursday in November
4.3.11. Christmas Day – December 25th
4.3.12. NOTE: Base Scheduled Day Off (SDO). If the Federal Holiday occurs on a
Monday, the base will observe a SDO and be closed the following Tuesday in addition to the Federal Holiday.
4.4. Vendor personnel must obtain DBIDS credentials
4.5. Vendor will be escorted to and from the work site daily.
4.6. Vendor shall provide portable restroom facilities for their personnel.
4.7. No weapons or prohibited items permitted on base.
5. ENVIRONMENTAL AND SAFETY REQUIREMENTS
5.1. Hazardous Material – under NO CIRCUMSTANCES shall any waste materials, cleaning fluids, solvents, paints, etc. be poured into the base storm drains, sewer/septic systems or discharged onto the ground. Vendor shall adhere to all Federal, State and Local Regulations. All materials on the job will be accompanied by a MSDS (Material Safety Data Sheet). All containers of waste will be disposed of properly following IAW State and Federal Regulations to include proper manifesting. Provide the Base Engineer with quantities of recyclable materials discarded such metals, concrete, etc.
5.2. Hazardous Material is defined in the latest version of Federal Standard No. 313. (ref.:
FAR 23.301). SDS must accompany all materials
5.3. Vendor shall maintain a safe work environment and follow appliable safety regulations.
6. CLEAN UP
6.1. The Vendor shall remove all debris, packaging, and waste materials daily and leave the site in a clean and orderly condition, acceptable to the Government.
7. FINAL ACCEPTANCE AND WARRANTIES
7.1. Final Acceptance requires:
7.1.1. Complete installation
7.1.2. Successful generator and ATS integrated testing
7.1.3. Submission of all required documentation
7.1.4. Government inspection and approval
7.1.5. Site restored to original or better condition
7.2. Warranty. Vendor shall provide
7.2.1. Minimum one year warranty on workmanship and installation
7.2.2. Manufacturer warranties for generator, fuel tank, decking, and all components
7.2.3. All warranty documents delivered at closeout