This document appears to be an Internal Government Cost Estimate (IGCE) for the Osceola Ranger District Administrative Site Design project. The IGCE provides a detailed breakdown of the estimated costs and hours for the major services, travel, and reimbursables associated with this design effort.

The key details of the IGCE include:

  • Estimated construction cost of $11,000,000
  • Design/construction documents fee capped at 6% of construction cost ($660,000)
  • Commissioning agent services capped at 2% of construction cost ($82,000)
  • Construction administration services estimated at $220,000
  • Detailed task-based estimates for services such as site investigation, design, permitting, procurement, and construction administration
  • Estimated travel costs based on number of trips, airfare, rental cars, mileage, lodging, and per diem
  • Reimbursable costs for reproduction of drawings, specifications, and reports

The IGCE is intended to support the related federal contracting opportunity, which is for Commissioning Services for the Osceola Ranger District Administrative Site. That solicitation has a due date of 11/22/24 for quote submissions.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions Internal Government Estimate

Instructions

Cover Page
Fill in base information about project.
Estimated Costs will fill in from Major Services and Travel and Reimbursables Tab
Provide estimate of number of calendar days to execute each major task. Include Government Review time as listed in the SOW
Major Services
Major services include all direct labor as well as likely subcontracted services such as geotechnical borings or inspecting sewer systems by camera.
Add columns for major tasks within each category, but use groups to collapse the task by task. Task separation is not needed for Design phase. Generally, this will be for Predesign and planning services
Allocate Commissioning agent time across all phases used where provided by the A/E
Permit services also include other regulatory reporting and submission based on the design. This is the additional cost on top of design to prepare, submit, revise document required by regulators. Third party green building certification is included in this task
Review services include the review of designs by others, Value analysis, or other independent reivew services provided by the A/E. It does not include changes to the design based on reviews
Travel and Reimbursables
Break out each trip separately. If a number of similar trips are needed, like for Construction Administration, then copy/paste
Contractors will structure their travel in the way that makes the most sense for them. This is simply trying to figure out an appropriate estimate for price evaluation
Use Government YCA fares for airplane tickets--these are often similar to the cost of fully refundable tickets used by business travellers
Mileage--use current year IRS reimbursement rates. Mileage may also be used as a proxy for rental cars
Reimbursables are specified in the SOW. Generally, these are very limited as most deliverables will be electronic only. It can be useful to have a few copies of the final sets commercially printed for Government use

&G

Cover Page

Internal Government Estimate
Project UnitOsceola Ranger District
Project NameOsceola Ranger District Admin. Site Design
Project NumberProject #: 0805-FY23-8CL
Project CityLake City
Project StateFlorida
Prepared by:Sean G. Baldwin
Date Prepared:6/1/24
Estimated Cost of Construction$11,000,000
Max 6% of ECCDesign / Construction Documents$660,000
Max 0.75% of ECCCommissioning Agent Cx2$82,000
Max 2% of ECCConstruction Administration$220,000.00
Estimate Summary
Item #Item NameFeeBaseTotal Calendar DaysWorking Calendar DaysGovt Review Calendar DaysBuffer Calendar DaysTotal Calendar Days5
Base 003Review Services$0$04740747
Base 004Construction Administration Services$0$0366751489
Base 005Travel$0$000
Base 006Reproducibles$0$000
Total$0$0413
Total $BaseTotal Days
Estimate Notes

&G

&"Arial,Regular"&10Page &P of &N &D &T

Major Services

Osceola Ranger District Office Design - Commissioning Agent Contract - IGCE
FY 2024 FUNDS - April 2024FY 2025 FUNDS - CONSTRUCTION FUNDS

TASK I TASK II TASK III TASK IV TASK V TASK VI TASK VII TOTALS

Service CategoryUnitUnit RateSite InvestigationCharretteGeotechPredesign QTYPredesign CostDesign QTYDesign CostDesign Review HourValue Analysis HourReview QTYReview CostConstruction Documents QTYConstruction Documents CostPermit QTYPermit CostsProcurement Planning QTYProcurement Planning CostsCA QTYCA CostTotal QTYTotal CostRemarkSite InvestigationCharrette
Administrative 1Hour6900$0$00$0$0$0$00$01040
Commissioning Agent Cx2Hour0$0$0$0$0$0$0$00$000
Total Major Services$0$0$0$0$0$0$0$0
$0.00$0$0
$660,000 Design Cost (6%)
$XXX,XXX Commissioning Agent Cost (X.XX%)
$340,000 Construction Inspection (3%)
$11,000,000 Construction Cost
$1,000,000 Contingency
$XX,XXX,XXX Total Cost

&"Arial,Regular"&10Southern Region Architect Engineer Contracts Internal Government Estimate &"Arial,Regular"&10Prepared By: Sean G. Baldwin Date Prepared: 07/14/2023

&D &T

Travel and Reimbursables

Travel
TripTrip DaysAirfare #Airfare unit costAirfare TotalRental Car DaysRental Car Day CostRental Car CostMileage QTYMileage RateMileage TotalFuelLodging # of RoomsLodging NightsLodging RateLodging TotalM&IE Rate (GSA rate)M&IE # of PeopleM&IE Days/personM&IE TotalOther TravelTrip TotalRemark
Trip 10$1,200$0$000.560$01$110$0$5010.0$0$0$0
Trip 20$1,200$0$000.560$01$110$0$5010.0$0$0$0
Trip 30$1,200$0$000.560$01$110$0$5010.0$0$0$0
Trip 40$1,200$0$000.560$01$110$0$5010.0$0$0$0
Trip 50$1,200$0$000.560$01$110$0$5010.0$0$0$0
Trip 60$1,200$0$000.560$01$110$0$5010.0$0$0$0
Trip 70$1,200$0$000.560$01$110$0$5010.0$0$0$0
Trip 80$1,200$0$000.560$01$110$0$5010.0$0$0$0
Trip 90$1,200$0$000.560$01$110$0$5010.0$0$0$0
Trip 100$1,200$0$000.560$01$110$0$5010.0$0$0$0
Trip 110$1,200$0$000.560$01$110$0$5010.0$0$0$0
Trip 120$1,200$0$000.560$01$110$0$5010.0$0$0$0
Trip 130$1,200$0$000.560$01$110$0$5010.0$0$0$0
Trip 140$1,200$0$000.560$01$110$0$5010.0$0$0$0
Trip 150$1,200$0$000.560$01$110$0$5010.0$0$0$0
Trip 160$1,200$0$000.560$01$110$0$5010.0$0$0$0
Trip 170$1,200$0$000.560$01$110$0$5010.0$0$0$0
Trip 180$1,200$0$000.560$01$110$0$5010.0$0$0$0
Trip 190$1,200$0$000.560$01$110$0$5010.0$0$0$0
Trip 200$1,200$0$000.560$01$110$0$5010.0$0$0$0
Trip 210$1,200$0$000.560$01$110$0$5010.0$0$0$0
Trip 220$1,200$0$000.560$01$110$0$5010.0$0$0$0
Trip 230$1,200$0$000.560$01$110$0$5010.0$0$0$0
Trip 240$1,200$0$000.560$01$110$0$5010.0$0$0$0
Trip 250$1,200$0$000.560$01$110$0$5010.0$0$0$0
Trip 260$1,200$0$000.560$01$110$0$5010.0$0$0$0
Trip 270$1,200$0$000.560$01$110$0$5010.0$0$0$0
Trip 280$1,200$0$000.560$01$110$0$5010.0$0$0$0
Total Travel0$0$0$0$0$0$0$0$0$0
Reimbursables
Item/ServiceUnitUnit priceQTYItem/ Service CostRemark
Drawings, 1/2 sizesheet$0.500$0
Drawings, full sizesheet$1.500$0
Specifications/reportspage$0.100$0
Specifications/reports colorpage$0.750$0
Presentation Boardsea$500.00$0
Shippingea$0
$0
Total$00

&"Arial,Regular"&10Southern Region Architect Engineer Contracts Internal Government Estimate &"Arial,Regular"&10Project Name Project Location &"Arial,Regular"&10Prepared By: David Culp Date Prepared: 1 October 2021