Attachment 1 - 676-233 Construct Material Shed 12282023 SOW.pdf

PDF 180 KB Posted

Attached to
Y1DZ-- Minor Construction - Tomah VAMC 676-233 Construct Material Shed Federal contract opportunity
Solicitation number
36C77624B0014_1
Issued by
Department of Veterans Affairs Technology Acquisition Center Austin

About this file

This document is a Statement of Work (SOW) for a construction project to build a 4,800 square foot material storage building at the Tomah VA Medical Center in Tomah, Wisconsin. The project, numbered 676-233 and titled "Construct Material Shed," requires the contractor to provide all labor, materials, equipment, supervision, and other items necessary to complete the work within 245 calendar days of the Notice to Proceed. The SOW outlines a 6-phase project plan, including pre-construction activities such as submitting plans and schedules, a 120-day construction period, and a 45-day closeout phase. Key deliverables include an Accident Prevention Plan, Construction Schedule, Quality Control Plan, and as-built drawings. This project is being solicited under Solicitation Number 36C77624B0014_1 by the Department of Veterans Affairs Technology Acquisition Center in Austin.

View the file

Other files for this federal contract opportunity

Other files attached to Y1DZ-- Minor Construction - Tomah VAMC 676-233 Construct Material Shed, newest first.
File Type Posted
36C77624B0014 0003.pdf PDF
Bid Open Sign-in Sheet - Tomah Minor - 07-16-2024.pdf PDF
36C77624B0014 0003.pdf PDF
Abstract of Bids OF 1419 - CONSTRUCTION pg 1_2.pdf PDF
36C77624B0014 0002.pdf PDF
36C77624B0014_1_Amended 07012024.pdf PDF
36C77624B0014 0001.pdf PDF
Attachment - Site Visit Agenda - Tomah.pdf PDF
Sign in Sheet - Tomah site visit.pdf PDF
36C77624B0014_1.pdf PDF
Attachment 6 - B2307270 - Geotechnical Evaluation.pdf PDF
Attachment 13 - Soil Loss Calc Spreadsheet.pdf PDF
Attachment 4 - 24 MAY 24 - Material Shed - FINAL BID DOCUMENTS - Specs Vol 2.pdf PDF
Attachment 5 - 23003453 02 VA Topo Survey Material Shed Site.pdf PDF
Attachment 9 - Contractor Safety and Environmental Record Evaluation Form.docx DOCX document
Attachment 11 - Surface Water Data Viewer Map.pdf PDF
Attachment 8 - Limitations on Subcontracting - Construction.docx DOCX document
Attachment 2 - 24 MAY 24 - Material Shed - FINAL BID Docs - DRAWINGS.pdf PDF
Attachment 3 - 24 MAY 24 - Material Shed - FINAL BID DOCUMENTS - Specs Vol 1.pdf PDF
Attachment 7 - Wage Determination - Monroe County.pdf PDF
Attachment 10 - ERR Review verificationform1700-079_No-Low Impact.pdf PDF
Attachment 12 - Erosion Control Plan.pdf PDF
Attachment 14 - Tomah VA_Stormwater Narrative.pdf PDF
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tomah VA Medical Center

Construct Material Shed

Project 676-233

Scope of Work December 28, 2023

US Department of Veterans Affairs

Tomah VA Medical Center

500 East Veterans St.

Tomah, WI 54660

STATEMENT OF WORK

Prepared by:

Facility Management Division

I. General Description:

Provide Construction Services for Project: Construct Material Shed

PROJECT NO: 676-233

PROJECT NAME: Construct Material Shed

II Project Scope:

1. General Description:

Provide Construction Services for Project #676-233, Construction of 4,800 square foot Materials storage building.

1. Contractor shall provide for and furnish all labor, materials, equipment, qualified supervision, and other items designated in this contract in accordance with the specifications and drawings to complete Project # 676-233 Construct Material Shed at Tomah VA Medical Center, 500 E. Veterans St, Tomah, WI.

2. All work shall be completed within 245 calendar days after receiving Notice to Proceed.

3. The C&A Requirements do not apply, a security Accreditation Package is not required.

This project shall be completed within Two Hundred Forty Five Days (245) days once NTP is issued.

• Phase 1: Pre-construction (kick-off) Meeting is anticipated to be scheduled on the effective date identified in the Notice to Proceed (NTP).

• Phase 2: Pre-Construction Accident Prevention Plan and Construction Schedule, to be completed no later than NTP + 30 days. Within this period the contractor shall submit the Accident Prevention Plan, submit the Construction Schedule, Submittal Registry, Product Submittals, Submittal Exchange Subscription, and schedule a review meeting with the COR and VA Safety.

• Phase 3: Pre-Construction Period duration is NTP + 60 calendar days (not to exceed). Within this period the contractor shall provide a submittal exchange subscription for the VA and submit the following (as applicable per the specification requirements):

1. Construction Phasing Plan.

2. Accident Prevention Plan.

3. Activity Hazard Analyses.

4. Construction Schedule.

5. Schedule of Values.

6. Existing Conditions Survey.

7. Infection Control Plan.

8. Quality Control Plan.

9. Environmental Protection Plan.

PROJECT NO: 676-233

PROJECT NAME: Construct Material Shed

10. Document Submissions.

11. Demolition Debris Management Plan.

12. Certificates, Licenses, and Training Documents.

13. Obtain PIV badges.

14. Material Procurement and Delivery

• Phase 4: Pre-Construction VA Review Period. Phase 4 is anticipated to be 30 calendar days and shall be completed no later than NTP + 90 calendar days. Within this period the VA will complete all review and approvals of contractor Pre- Construction submittals.

• Phase 5: Construction Period – Phase duration is anticipated to be 120 days; to be completed no later than NTP + 210. All applicable documentation listed in Phase 2 and any necessary submittals required to mobilize must be approved by the COR prior to commencing work. No demolition or construction shall be started without COR review and approval of those items listed in the Pre-Construction Period unless authorized in writing by the COR or the CO. Should naturally occurring weather delays occur, the contractor shall restart construction immediately once conditions permit.

• Phase 6: Construction Closeout Period duration is NTP + 245 calendar days. The contractor shall provide all required materials to include the following within 45 days of completion of Phase 5.

1. Inspection and Approval by the COR and/or the CO.

2. Final Approval and Beneficial Occupancy when applicable.

3. Warranties documents and O&M Manuals.

4. As-built drawings and record submittals.

5. Staff training when applicable.

6. Final Waste Reports.

7. Existing Conditions Re-survey.

8. Release of Claims.

-- End SOW --