Attachment 05 - Bid Schedule.xlsx

XLSX spreadsheet 25 KB Posted

Attached to
Repair Fire Hydrants
Solicitation number
FA480326B0005
Issued by

About this file

The file is an Excel-based Bid Schedule for a fire hydrant and water infrastructure repair project. The solicitation is a 100% Small Business set-aside for NAICS 236220, with a construction magnitude between $250,000 and $500,000, issued by the Department of the Air Force Air Combat Command. The project, identified as VLSB 24-0104, involves potential work across four Contract Line Items (CLINs) that include tasks such as demolishing and installing fire hydrants, isolation valves, thrust blocks, painting, flow testing, and installing new water pipes.

Key procurement details include a period of performance not exceeding 111 days after the Notice to Proceed, with bids due by 30 January 2026 at 9:00 A.M. and bid opening at 1:00 P.M. EST. The solicitation notes that funds are not currently available, and the government's obligation is contingent on appropriated funds. Questions and clarification requests must be submitted by COB 7 January 2026, with responses provided by 16 January 2026. Bid submissions should be emailed to SSgt Braulio Ramirez Galvan and SrA Tariq Ellis. The bid schedule template is currently populated with zero quantities and costs, indicating it is a framework for potential bidders to complete.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

`CUI
Project:Repair valvesVLSB 24-0104Project Engineer:
Location:Department:
Contractor:
Address:
PR No.:
CUI
CLIN 01
ReferenceLine No.ItemUnit of MeasureQuantityMaterial CostsLabor CostsDirect CostLine TotalNotes
Unit Cost (Means)TotalLabor Hours per Unit (Means)Labor Cost per Unit (Means)Labor-HoursAvg. Rate ($/hr)TotalNotes
1Demo Fire HydrantsEA0$0.00$0.000$0.00$0.00
2Demo Isolation ValveEA0$0.000$0.00
3Install New Fire HydrantEA0$0.00$0.000$0.00$0.00
4Install Isolation ValveEA0$0.00$0.000$0.00
5Install New Thrust BlockEA0$0.00$0.000$0.00
6PaintSF0$0.00$0.000$0.00
7Flow TestEA0$0.00$0.000$0.00
8New Water PipeLF0$0.00$0.000$0.00
SUPERVISION
9Project Managerdays0$0.000$0.00
10Project Superintendantdays0$0.000$0.00
Totals:$0.00$0.00$0.00$0.00
CLIN 01
Total Material Cost:$0.00
Total Labor Cost:$0.00
Direct Cost:$0.00
Total Line Item Cost:$0.00
Overhead:0%$0.00
Subtotal:$0.00
Profit:0%$0.00
Subtotal:
Bond:0.0%
Total Contract Price:
CLIN 02
ReferenceLine No.ItemUnit of MeasureQuantityMaterial CostsLabor CostsDirect CostLine TotalNotes
Unit Cost (Means)TotalLabor Hours per Unit (Means)Labor Cost per Unit (Means)Labor-HoursAvg. Rate ($/hr)TotalNotes
1Abate concrete asbestosSQ0$0.00$0.000$0.00$0.00
2Demo Fire HydrantsEA0$0.00$0.000$0.00$0.00
Demo Isolation ValveEA0$0.00$0.000$0.00
3Install New Fire HydrantEA0$0.00$0.000$0.00$0.00
4Install Isolation ValveEA0$0.00$0.000$0.00
5Install New Thrust BlockEA0$0.00$0.000$0.00
6PaintSF0$0.00$0.000$0.00
7Flow TestEA0$0.00$0.000$0.00
8New Water PipeLF0$0.00$0.000$0.00
SUPERVISION
9Project Managerdays0$0.000$0.00
10Project Superintendantdays0$0.000$0.00
Totals:$0.00$0.00$0.00$0.00
CLIN 02
Total Material Cost:$0.00
Total Labor Cost:$0.00
Direct Cost:$0.00
Total Line Item Cost:$0.00
Overhead:0%$0.00
Subtotal:$0.00
Profit:0%$0.00
Subtotal:
Bond:0.0%
Total Contract Price:
CLIN 03
ReferenceLine No.ItemUnit of MeasureQuantityMaterial CostsLabor CostsDirect CostLine TotalNotes
Unit Cost (Means)TotalLabor Hours per Unit (Means)Labor Cost per Unit (Means)Labor-HoursAvg. Rate ($/hr)TotalNotes
1Demo Fire HydrantsEA0$0.00$0.000$0.00$0.00
2Install New Fire HydrantEA0$0.00$0.000$0.00$0.00
3Install Isolation ValveEA0$0.00$0.000$0.00
4Install New Thrust BlockEA0$0.00$0.000$0.00
5PaintSF0$0.00$0.000$0.00
6Flow TestEA0$0.00$0.000$0.00
7New Water PipeLF0$0.00$0.000$0.00
SUPERVISION
8Project Managerdays0$0.000$0.00
9Project Superintendantdays0$0.000$0.00
Totals:$0.00$0.00$0.00$0.00
CLIN 03
Total Material Cost:$0.00
Total Labor Cost:$0.00
Direct Cost:$0.00
Total Line Item Cost:$0.00
Overhead:0%$0.00
Subtotal:$0.00
Profit:0%$0.00
Subtotal:
Bond:0.0%
Total Contract Price:
CLIN 04
ReferenceLine No.ItemUnit of MeasureQuantityMaterial CostsLabor CostsDirect CostLine TotalNotes
Unit Cost (Means)TotalLabor Hours per Unit (Means)Labor Cost per Unit (Means)Labor-HoursAvg. Rate ($/hr)TotalNotes
Abate concrete asbestosSQ0$0.00$0.000$0.00$0.00
1Demo Fire HydrantsEA0$0.00$0.000$0.00$0.00
2Install New Fire HydrantEA0$0.00$0.000$0.00$0.00
3Install Isolation ValveEA0$0.00$0.000$0.00
4Install New Thrust BlockEA0$0.00$0.000$0.00
5PaintSF0$0.00$0.000$0.00
6Flow TestEA0$0.00$0.000$0.00
7New Water PipeLF0$0.00$0.000$0.00
SUPERVISION
8Project Managerdays0$0.000$0.00
9Project Superintendantdays0$0.000$0.00
Totals:$0.00$0.00$0.00$0.00
CLIN 04
Total Material Cost:$0.00
Total Labor Cost:$0.00
Direct Cost:$0.00
Total Line Item Cost:$0.00
Overhead:0%$0.00
Subtotal:$0.00
Profit:0%$0.00
Subtotal:
Bond:0.0%
Total Contract Price:
Total Contract Price:ERROR:#VALUE!

File details come from the government source that posted it. Updated .