Attachment 05 - Bid Schedule.xlsx
XLSX spreadsheet 25 KB Posted
- Attached to
- Repair Fire Hydrants
- Solicitation number
- FA480326B0005
About this file
The file is an Excel-based Bid Schedule for a fire hydrant and water infrastructure repair project. The solicitation is a 100% Small Business set-aside for NAICS 236220, with a construction magnitude between $250,000 and $500,000, issued by the Department of the Air Force Air Combat Command. The project, identified as VLSB 24-0104, involves potential work across four Contract Line Items (CLINs) that include tasks such as demolishing and installing fire hydrants, isolation valves, thrust blocks, painting, flow testing, and installing new water pipes.
Key procurement details include a period of performance not exceeding 111 days after the Notice to Proceed, with bids due by 30 January 2026 at 9:00 A.M. and bid opening at 1:00 P.M. EST. The solicitation notes that funds are not currently available, and the government's obligation is contingent on appropriated funds. Questions and clarification requests must be submitted by COB 7 January 2026, with responses provided by 16 January 2026. Bid submissions should be emailed to SSgt Braulio Ramirez Galvan and SrA Tariq Ellis. The bid schedule template is currently populated with zero quantities and costs, indicating it is a framework for potential bidders to complete.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| ` | CUI | |||||||||||||
| Project: | Repair valves | VLSB 24-0104 | Project Engineer: | |||||||||||
| Location: | Department: | |||||||||||||
| Contractor: | ||||||||||||||
| Address: | ||||||||||||||
| PR No.: | ||||||||||||||
| CUI | ||||||||||||||
| CLIN 01 | ||||||||||||||
| Reference | Line No. | Item | Unit of Measure | Quantity | Material Costs | Labor Costs | Direct Cost | Line Total | Notes | |||||
| Unit Cost (Means) | Total | Labor Hours per Unit (Means) | Labor Cost per Unit (Means) | Labor-Hours | Avg. Rate ($/hr) | Total | Notes |
| 1 | Demo Fire Hydrants | EA | 0 | $0.00 | $0.00 | 0 | $0.00 | $0.00 | ||
| 2 | Demo Isolation Valve | EA | 0 | $0.00 | 0 | $0.00 | ||||
| 3 | Install New Fire Hydrant | EA | 0 | $0.00 | $0.00 | 0 | $0.00 | $0.00 | ||
| 4 | Install Isolation Valve | EA | 0 | $0.00 | $0.00 | 0 | $0.00 | |||
| 5 | Install New Thrust Block | EA | 0 | $0.00 | $0.00 | 0 | $0.00 | |||
| 6 | Paint | SF | 0 | $0.00 | $0.00 | 0 | $0.00 | |||
| 7 | Flow Test | EA | 0 | $0.00 | $0.00 | 0 | $0.00 | |||
| 8 | New Water Pipe | LF | 0 | $0.00 | $0.00 | 0 | $0.00 | |||
| SUPERVISION | ||||||||||
| 9 | Project Manager | days | 0 | $0.00 | 0 | $0.00 | ||||
| 10 | Project Superintendant | days | 0 | $0.00 | 0 | $0.00 | ||||
| Totals: | $0.00 | $0.00 | $0.00 | $0.00 |
| CLIN 01 | |
| Total Material Cost: | $0.00 |
| Total Labor Cost: | $0.00 |
| Direct Cost: | $0.00 |
| Total Line Item Cost: | $0.00 |
| Overhead: | 0% | $0.00 |
| Subtotal: | $0.00 |
| Profit: | 0% | $0.00 |
| Subtotal: |
| Bond: | 0.0% |
| Total Contract Price: |
| CLIN 02 | ||||||||||||||
| Reference | Line No. | Item | Unit of Measure | Quantity | Material Costs | Labor Costs | Direct Cost | Line Total | Notes | |||||
| Unit Cost (Means) | Total | Labor Hours per Unit (Means) | Labor Cost per Unit (Means) | Labor-Hours | Avg. Rate ($/hr) | Total | Notes |
| 1 | Abate concrete asbestos | SQ | 0 | $0.00 | $0.00 | 0 | $0.00 | $0.00 | ||
| 2 | Demo Fire Hydrants | EA | 0 | $0.00 | $0.00 | 0 | $0.00 | $0.00 | ||
| Demo Isolation Valve | EA | 0 | $0.00 | $0.00 | 0 | $0.00 | ||||
| 3 | Install New Fire Hydrant | EA | 0 | $0.00 | $0.00 | 0 | $0.00 | $0.00 | ||
| 4 | Install Isolation Valve | EA | 0 | $0.00 | $0.00 | 0 | $0.00 | |||
| 5 | Install New Thrust Block | EA | 0 | $0.00 | $0.00 | 0 | $0.00 | |||
| 6 | Paint | SF | 0 | $0.00 | $0.00 | 0 | $0.00 | |||
| 7 | Flow Test | EA | 0 | $0.00 | $0.00 | 0 | $0.00 | |||
| 8 | New Water Pipe | LF | 0 | $0.00 | $0.00 | 0 | $0.00 | |||
| SUPERVISION | ||||||||||
| 9 | Project Manager | days | 0 | $0.00 | 0 | $0.00 | ||||
| 10 | Project Superintendant | days | 0 | $0.00 | 0 | $0.00 | ||||
| Totals: | $0.00 | $0.00 | $0.00 | $0.00 |
| CLIN 02 | |
| Total Material Cost: | $0.00 |
| Total Labor Cost: | $0.00 |
| Direct Cost: | $0.00 |
| Total Line Item Cost: | $0.00 |
| Overhead: | 0% | $0.00 |
| Subtotal: | $0.00 |
| Profit: | 0% | $0.00 |
| Subtotal: |
| Bond: | 0.0% | |||||||||||||
| Total Contract Price: | ||||||||||||||
| CLIN 03 | ||||||||||||||
| Reference | Line No. | Item | Unit of Measure | Quantity | Material Costs | Labor Costs | Direct Cost | Line Total | Notes | |||||
| Unit Cost (Means) | Total | Labor Hours per Unit (Means) | Labor Cost per Unit (Means) | Labor-Hours | Avg. Rate ($/hr) | Total | Notes |
| 1 | Demo Fire Hydrants | EA | 0 | $0.00 | $0.00 | 0 | $0.00 | $0.00 | ||
| 2 | Install New Fire Hydrant | EA | 0 | $0.00 | $0.00 | 0 | $0.00 | $0.00 | ||
| 3 | Install Isolation Valve | EA | 0 | $0.00 | $0.00 | 0 | $0.00 | |||
| 4 | Install New Thrust Block | EA | 0 | $0.00 | $0.00 | 0 | $0.00 | |||
| 5 | Paint | SF | 0 | $0.00 | $0.00 | 0 | $0.00 | |||
| 6 | Flow Test | EA | 0 | $0.00 | $0.00 | 0 | $0.00 | |||
| 7 | New Water Pipe | LF | 0 | $0.00 | $0.00 | 0 | $0.00 | |||
| SUPERVISION | ||||||||||
| 8 | Project Manager | days | 0 | $0.00 | 0 | $0.00 | ||||
| 9 | Project Superintendant | days | 0 | $0.00 | 0 | $0.00 | ||||
| Totals: | $0.00 | $0.00 | $0.00 | $0.00 |
| CLIN 03 | |
| Total Material Cost: | $0.00 |
| Total Labor Cost: | $0.00 |
| Direct Cost: | $0.00 |
| Total Line Item Cost: | $0.00 |
| Overhead: | 0% | $0.00 |
| Subtotal: | $0.00 |
| Profit: | 0% | $0.00 |
| Subtotal: |
| Bond: | 0.0% | |||||||||||||
| Total Contract Price: | ||||||||||||||
| CLIN 04 | ||||||||||||||
| Reference | Line No. | Item | Unit of Measure | Quantity | Material Costs | Labor Costs | Direct Cost | Line Total | Notes | |||||
| Unit Cost (Means) | Total | Labor Hours per Unit (Means) | Labor Cost per Unit (Means) | Labor-Hours | Avg. Rate ($/hr) | Total | Notes |
| Abate concrete asbestos | SQ | 0 | $0.00 | $0.00 | 0 | $0.00 | $0.00 | |||
| 1 | Demo Fire Hydrants | EA | 0 | $0.00 | $0.00 | 0 | $0.00 | $0.00 | ||
| 2 | Install New Fire Hydrant | EA | 0 | $0.00 | $0.00 | 0 | $0.00 | $0.00 | ||
| 3 | Install Isolation Valve | EA | 0 | $0.00 | $0.00 | 0 | $0.00 | |||
| 4 | Install New Thrust Block | EA | 0 | $0.00 | $0.00 | 0 | $0.00 | |||
| 5 | Paint | SF | 0 | $0.00 | $0.00 | 0 | $0.00 | |||
| 6 | Flow Test | EA | 0 | $0.00 | $0.00 | 0 | $0.00 | |||
| 7 | New Water Pipe | LF | 0 | $0.00 | $0.00 | 0 | $0.00 | |||
| SUPERVISION | ||||||||||
| 8 | Project Manager | days | 0 | $0.00 | 0 | $0.00 | ||||
| 9 | Project Superintendant | days | 0 | $0.00 | 0 | $0.00 | ||||
| Totals: | $0.00 | $0.00 | $0.00 | $0.00 |
| CLIN 04 | |
| Total Material Cost: | $0.00 |
| Total Labor Cost: | $0.00 |
| Direct Cost: | $0.00 |
| Total Line Item Cost: | $0.00 |
| Overhead: | 0% | $0.00 |
| Subtotal: | $0.00 |
| Profit: | 0% | $0.00 |
| Subtotal: |
| Bond: | 0.0% | |
| Total Contract Price: | ||
| Total Contract Price: | ERROR:#VALUE! |
File details come from the government source that posted it. Updated .