Attachment 05 AF 66.xlsx

XLSX spreadsheet 27 KB Posted

Attached to
Repair/Renovate Cleveland Commercial Gate
Solicitation number
FA481920R0009
Issued by

About this file

This document contains an AF Form 66 schedule of material submittals for the repair and renovation of the Cleveland Commercial Gate at Tyndall AFB. The schedule outlines 22 required submittals from the contractor organized by line item, including design documents, permits, reports, manuals, and as-built drawings. Key due dates are provided for each submittal ranging from 10 days prior to commencing work to final inspection plus 7 days. The related federal contract opportunity solicitation seeks to repair and renovate the Cleveland Commercial Gate and references this AF Form 66 and additional attachments for project details.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AF 66

SCHEDULE OF MATERIAL SUBMITTALSPROJECT NUMBERPROJECT TITLESOLICITATION/CONTRACT NO.
XLWU 20-8124REPAIR / RENOVATE CLEVELAND COMMERCIAL GATEFA4819-20-C-XXXX
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF COPIES REQUIRED
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALCERTIFICATEOF COMPLIANCESHOP DRAWINGSSAMPLESCOLOR SELECTIONMANUFACTURER'SRECOMMENDATIONSMANUFACTURER'SWARRANTYCATALOG DATAOPERATINGINSTRUCTIONSAS-BUILT DRAWINGS& DISKDOCUMENTATION ASREQUIREDREQUIRED SUBMISSION DATEDATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSDATE CONTRACTOR NOTIFIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS
APPROVEDDISAPPROVED
1Design Charrette1NTP + 14 DaysKick-Off Meeting
2Meeting Minutes (All Meetings)1Meeting + 2 Days
3Contractor Badging Applications1Award + 14 Days
4Project Schedule - AF Form 30641NTP + 14 Days
565% Design Submittal1NTP + 45 Days
695% Design Submittal1NTP + 75 Days
7100% Design Submittal1NTP + 90 Days
8Work Clearance Request / Digging Permit - AF Form 103110 Days Prior to Commencing Work
9HAZMAT Inventory Form 81 & 82114 Days Prior to Commencing Work
10Progress Report - AF Form 30651Weekly
11Material Approval - AF Form 30001111115 Days Prior to Order
12Regulatory Permit Application1Prior to submitting to Permitting Agency
13Construction Materials Testing Reports1Upon Receipt
14Welding/Burn Permit - As Required1Prior to Commencing Work
15Draft DD 1354 - Transfer & Acceptance of Military Real Property1NTP + 90 Days
16Pre-Final Inspection Report1Pre-Final + 3 Days
17Contractor Environmental Reporting Entry - TAFB Form 831Prior to Final Inspection
18Equipment Manuals and Parts Lists1Prior to Final Inspection
19Final DD 1354 - Transfer & Acceptance of Military Real Property1At Final Inspection
20Final Inspection Report1Final Inspection + 5 Days
21As-Built Drawings1Final Inspection + 7 Days
22Project Close Out Documents111111Final Inspection + 7 Days

&"Arial,Bold"&12AF Form 66