Attachment 04 QASP.pdf
PDF 72 KB Posted
- Attached to
- Building 3 & 4 Exterior Brick Repair
- Solicitation number
- 12505B24R0020
About this file
This document is a Quality Assurance Surveillance Plan (QASP) for a Performance-Based Service Contract (PBSC) to repair the exterior brick on Buildings 3 and 4 at the USDA National Animal Disease Center in Ames, Iowa. The QASP outlines the roles and responsibilities of the Contracting Officer and Contracting Officer's Representative (COR) in monitoring the contractor's performance to ensure the contract requirements are met, including verifying the use of proper materials and methods, the application of masonry sealer, and the removal of debris. The COR will conduct periodic and final inspections to document compliance. The QASP is designed to ensure the Government only pays for acceptable services.
The related federal contract opportunity is Solicitation 12505B24R0020 for the Building 3 & 4 Exterior Brick Repair project. This is a total small business set-aside with a NAICS code of 238140 (Masonry Contractors) and a size standard of $19.0 million. The estimated magnitude of construction is between $500,000 and $1,000,000, with a 360-day period of performance. Offerors must be registered in SAM and are required to attend one of two scheduled site visits. All questions must be submitted by June 27, 2024, and the use of biobased products is required.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUALITY ASSURANCE SURVEILLANCE PLAN
FOR
BUILDING 3 AND 4 EXTERIOR BRICK REPAIR
1. PURPOSE. This Quality Assurance Surveillance Plan (QASP) is a Government developed and applied document used to make sure that systematic quality assurance methods are used in the administration of the Performance Based Service Contract (PBSC) standards included in this contract and in subsequent task orders issued there under. The intent is to ensure that the Contractor performs in accordance with performance metrics set forth in the contract documents, that the Government receives the quality of services called for in the contract and that the Government only pays for the acceptable level of services received.
The QASP has been developed by the requiring activity. It is designed to provide direction to personnel performing contract surveillance activities. Personnel surveying the contract terms and conditions and SOW requirements will periodically review the QASP throughout the life of the contract.
The Contracting Officer’s Representative (COR) will monitor the Building 3 and 4 Exterior
Brick Repair to monitor the materials and methods used to make the repairs in a satisfactory manner.
2. SCOPE. The QASP is put in place to provide Government surveillance oversight of the
Contractor’s quality control efforts to ensure the products/results specified in the PR&C or task order are delivered on time and meet the requirements of the PR&C or task order. The
QASP is not intended to duplicate the Contractor’s Management Plan.
3. GOVERNMENT RESOURCES. The following definitions for Government resources are applicable to this plan:
Contracting Officer. A person duly appointed with the authority to enter into, administer, or terminate contracts and make related determinations and findings on behalf of the
Government.
Contracting Officer’s Representative (COR). An individual designated in writing by the
Contracting Officer to act as his authorized representative to assist in administering a contract. The source and authority for a COR is the Contracting Officer. COR limitations are contained in the written letter of appointment.
4. RESPONSIBILITIES. The Government resources shall have responsibilities for the implementation of this QASP as follows:
Contracting Officer. The Contracting Officer ensures performance of all necessary actions for effective contracting, ensures compliance with the terms of the contract and safeguards the interests of the United States in the contractual relationship. It is the Contracting Officer that ensures the Contractor receives impartial, fair, and equitable treatment under the contract. The Contracting Officer is ultimately responsible for the final determination of the adequacy of the Contractor’s performance.
Contracting Officer’s Representative (COR). The COR is responsible for technical administration of the project and ensures proper Government surveillance of the Contractor’s performance. The COR is not empowered to make any contractual commitments or to authorize any contractual changes on the Government’s behalf. Any changes that the
Contractor deems may affect contract, price, terms, or conditions shall be referred to the
Contracting Officer for action.
Periodic Inspection. The COR shall conduct periodic inspections by verifying the conditions are appropriate for the materials and methods used to prepare repair the exterior brick surfaces of Building 3 and 4. The COR may take photos to document the progress when work is being completed for the potential tasks identified in the Performance Work
Statement, the COR typically performs the periodic inspection on a daily basis.
Final Inspection. The COR will schedule a final inspection with the contractor when all of punch-list items have been completed.
5. LEVELS AND STANDARDS OF SERVICE. The standards of services are held to and comply with the standards specified in the PR&C, commercial/industry, and military/government standards.
6. IDENTIFIED QA SURVEILLANCE ITEMS
Performance Requirements Required Services Performance Objective Performance Requirement
Provide close match brick to replace loose, deteriorated or cracked bricks.
Contractor shall use process described in Performance Work
Statement to remove existing brick and install ne close match brick.
Verify new installed brick are properly mortared in place and the completed sections are uniform in alignment, pattern and profile.
Application of masonry sealer.
Contractor shall provide a Silane based masonry sealer and apply two coats.
Verify the correct Silane based sealer is being used and two coats have been applied in a uniform manner without damaging surrounding surfaces not in the scope.
Left over material and debris removed from
Site appropriately.
Contractor shall remove all debris from the site and dispose of appropriately according to the
Performance Work Statement.
Verify no debris or garbage is left behind after the installation and it has been hauled away by contractor.
7. DOCUMENTATION. The COR shall, in addition to providing documentation to the
Contracting Officer, maintain a complete Quality Assurance file. All such records will be retained for the life of this contract.