This document includes a schedule of material submittals for a federal solicitation to repair ground radio transmit and receive antennas. Key details include a requirement for the contractor to provide engineering, furnishing, installation and testing of three new high frequency spiral-cone antennas and installation of new radio frequency cabling and manhole and duct systems. The work also includes a phased approach to limit operational impacts and utilization of a design-build team consisting of a general contractor and architecture and engineering firm. The schedule outlines fifteen required submittals with deadlines ranging from two weeks after notice to proceed to seven days after final inspection. Submittals include pricing schedules, meeting minutes, project schedules, design plans, permit applications, testing reports, as-built drawings and closeout documents. The solicitation was issued by the Department of the Air Force Air Combat Command.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
XLWU 20-8182
REPAIR GATR HF ANTENNAS
SCHEDULE OF MATERIAL SUBMITTALS
PROJECT NUMBER SOLICITATION/CONTRACT NO.
FA4819-20-C-XXXX
NO. OF COPIES REQUIRED
L I N E
N U M B E R
ITEM OR DESCRIPTION OF ITEM, CONTRACT
REFERENCE, TYPE OF SUBMITTAL
C E
R T
IF
IC
A T
E
O F
C O
M P
L
IA
N C
E
S H
O P
D R
A W
IN
G
S
S A
M P
L E
S
C O
L O
R S
E L
E C
T
IO
N
M A
N U
F A
C T
U R
E R
'S
R E
C O
M M
E N
D A
T
IO
N S
M A
N U
F A
C T
U R
E R
'S
W A
R R
A N
T Y
C A
T A
L O
G D
A T
A
O P
E R
A T
IN
G
IN
S
T R
U C
T
IO
N S
A S
-B U
IL
T
D R
A W
IN
G
S
D
IS
K
D O
C U
M E
N T
A T
IO
N
A S
R E
Q U
IR
E
D
R E
Q U
IR
D
U
B M
IS
S
IO
N
D A
T E
D A
T
C
E
IV
E D
I N
C
O N
T R
A C
T
IN
G
D A
T E
T O
C
IV
IL
G
IN
E E
R
IN
G
R E
T U
R N
S U
S P
E N
T
E
S U
B M
IT
T
A L
N U
M B
E R
S
DATE CONTRACTOR NOTIFIED
C O
N T
R A
C T
S
U B
M
IT
T A
L
F
IN
A L
A P
P R
O V
A L
REMARKS
APPROVED DISAPPROVED
1 Pricing Schedule With Bid
2 Meeting Minutes (All Meetings) Meeting + 2
Days
3 Contractor Badging Applications Award + 14
Days
4 Project Schedule - AF Form 3064 NTP + 14 Days
5 50% Design Submittal NTP + 45 Days
6 95% Design Submittal NTP +70 Days
7 100% Design Submittal NTP + 90 Days
Work Clearance Request / Digging Permit - AF
Form 103
10 Days Prior to Commencing
Work
9 HAZMAT Inventory Form 81 & 82 14 Days Prior to
Commencing Work
Progress Report - AF Form 3065 Weekly
Material Approval - AF Form 3000 1 1 1 1 5 Days Prior to
Order
Regulatory Permit Application
Prior to submitting to
Permitting Agency
Construction Materials Testing Reports Upon Receipt
Welding/Burn Permit - As Required Prior to
Commencing Work
Draft DD 1354 - Transfer & Acceptance of Military Real Property
NTP + 90 Days
1 1
SCHEDULE OF MATERIAL SUBMITTALS
PROJECT TITLE
XLWU 20-8182 REPAIR GATR HF ANTENNAS
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
AF Form 66
PROJECT NUMBER SOLICITATION/CONTRACT NO.
FA4819-20-C-XXXX
NO. OF COPIES REQUIRED
L I N E
N U M B E R
ITEM OR DESCRIPTION OF ITEM, CONTRACT
REFERENCE, TYPE OF SUBMITTAL
C E
R T
IF
IC
A T
E
O F
C O
M P
L
IA
N C
E
S H
O P
D R
A W
IN
G
S
S A
M P
L E
S
C O
L O
R S
E L
E C
T
IO
N
M A
N U
F A
C T
U R
E R
'S
R E
C O
M M
E N
D A
T
IO
N S
M A
N U
F A
C T
U R
E R
'S
W A
R R
A N
T Y
C A
T A
L O
G D
A T
A
O P
E R
A T
IN
G
IN
S
T R
U C
T
IO
N S
A S
-B U
IL
T
D R
A W
IN
G
S
D
IS
K
D O
C U
M E
N T
A T
IO
N
Q U
IR
E
D
R E
Q U
IR
U
B M
IS
S
IO
N
D A
T E
D A
T
C
E
IV
E D
I
C
N
T R
A C
T
IN
G
D A
T E
T O
C
IV
IL
G
IN
E E
R
IN
G
R E
T U
R N
S U
S P
E N
T
E
S U
B M
IT
T
A L
N U
M B
E R
S
DATE CONTRACTOR NOTIFIED
C O
N T
R A
C T
S
U B
M
IT
T A
L
F
IN
A L
A P
P R
O V
A L
REMARKS
APPROVED DISAPPROVED
SCHEDULE OF MATERIAL SUBMITTALS
PROJECT TITLE
XLWU 20-8182 REPAIR GATR HF ANTENNAS
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
Pre-Final Inspection Report Pre-Final + 3
Days
Contractor Environmental Reporting Entry - TAFB Form 83
Prior to Final Inspection
Equipment Manuals and Parts Lists Prior to Final Inspection
Final DD 1354 - Transfer & Acceptance of Military Real Property
At Final Inspection
Final Inspection Report Final
Inspection + 5 Days
As-Built Drawings Final
Inspection + 7 Days
Acceptance/Installation 1 With Final Inspection Request
Project Close Out Documents 1 Final
Inspection + 7 Days
1 1 1 1 1
1 1 1 1 1
AF Form 66