Attachment 03_Mod D Statement of Work_Rev1.pdf

PDF 141 KB Posted

Attached to
SOLICITATION: DESIGN AND FIRST ARTICLES -- ASR-9 RADAR MULTIVOLTAGE POWER SUPPLY (MVPS) REPAIR KITS.
Solicitation number
6973GH-24-R-00158
Issued by

About this file

This document is a Statement of Work (SOW) for the procurement of ASR-9 Module D Power Supply Repair Kits for the Federal Aviation Administration (FAA). The SOW outlines the requirements for the contractor to design, construct, and test the repair kits, which are needed to mitigate obsolescence issues with the current power supply components.

The SOW specifies the delivery of two prototype units with complete test data packages, schematic drawings, and diagnostics to demonstrate conformance to the applicable specifications. The FAA will then analyze the prototype units to verify and ensure product conformance. The contractor must also provide various documentation, including overview, operation, repair procedures, parts list, and schematic drawings. The repair kits must be capable of functioning as a form, fit, and function replacement for the existing Module D power supplies. The solicitation for the design and first articles of these repair kits is described in the related federal contract opportunity.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Procurement of

ASR-9 Module D Power Supply Repair Kit P/N 852300

1. BACKGROUND

Radar Technical Program Support Group, AJW-L910, currently provides logistics support to 135 ASR-9 field radar sites. The Multivoltage Power Supply (MVPS) distributes the power to the different subsystems for the Receiver and Weather Cabinets for the ASR-9. The MVPS uses grouped power supply modules for the different output requirements. A single +15 V Module D (MOD D) power supply is contained in the MVPS in the Receiver Cabinet and a single +15 V MOD D power supply is contained in the Weather/SCIP Cabinet. The MOD D provides power to the Target I-F Panel Assembly, Target Receiver Assembly, Frequency Generator Rack, and Interface Panel in the Receiver Cabinet and the Weather I-F Panel Assembly, Weather Receiver Assembly, and Interface Panel for the Weather Cabinet. The internal components of the MOD D are obsolete and therefore can no longer be repaired unless the components are replaced. The Federal Aviation Administration (FAA) has determined it necessary to replace the internal components with a repair kit that updates the MOD D and mitigates the obsolescence issues.

This Statement of Work describes the procurement of MOD D Repair kits used to update and repair NSN 6130- 01-294-9189.

2. SCOPE OF WORK

The contractor must furnish all labor, facilities, equipment, and materials to produce the ASR-9 MOD D Repair Kits for the FAA as outlined in each section that follow. The specific quantities of units include the following:

1. Two (2) Prototype Module D Power Supply Repair Kits

3. REQUIREMENTS

3.1 Design, Construction, and Testing

The contractor shall design, construct, and test the repair kits in accordance with (IAW) the following:

I. ASR-9 Spec Sheet PDS 23698 II. ASR-9 Spec Sheet PDS 23699 III. ASR-9 Spec Sheet FAA-G-2100H IV. ASR-9 Spec Sheet 850144 V. ASR-9 Spec Sheet 852300 VI. ASR-9 Spec Sheet D852312

Specifically, the repair kit will allow the existing MOD D Power Supplies to be updated as a Form, Fit, Function (FFF) replacement. In addition to the requirements listed in the attachments, the MOD D power supply must be capable of the following in accordance with the Legacy (OEM) design:

• Voltage must be adjustable when installed

• Kit must be compatible when paired with Legacy units

• Kit must be able to carry full load if paired power supply fails

3.2 Prototype Unit Delivery

Contractor must deliver two (2) verification units with complete test data package, schematic and diagnostics, illustrating conformance to SCD 852300 (Attachment 5), PDS 23698 (Attachment 1), and PDS 23699 (Attachment 2) and test procedures therein. The complete Test Data Package (TDP) must include QTP (Qualification Test Procedure) and Acceptance Test Procedure (ATP) that complies with PDS23698 par. 5.1.2 and 5.1.1 and 850144. Each prototype unit must include a test data sheet showing the results of tests for input isolation, output isolation, panel meter monitor output voltage, loss of single phase (for 3 phase power supply), overvoltage transient response, under voltage transient response, output ripple, output regulation, remote sense, output voltage adjustment, load transient response, over current protection, over voltage crowbar, inrush current, cooling air temperature rise, UPS and BIT (built in test). Delivery shall occur no later than (NLT) 200 days at receipt of order (ARO).

3.3 Prototype Unit Analysis

Upon receipt of prototype units, FAA shall perform analysis to verify and ensure product conformance to requirements in PDS 23698 (Attachment 1) and PDS 23699 (Attachment 2). Operational performance shall be evaluated via bench testing and in-system testing in accordance with PDS 23698 (Attachment 1) and PDS 23699 (Attachment 2). System tests shall consist of installing the kit into the next higher assembly and all the applicable positions within the Multivoltage Power Supply and verifying performance.

3.5 Documentation

The contractor must provide all written documentation in Microsoft Office WORD or EXCEL format, 2013 or later version. All documentation must be provided with Prototype units to be eligible for approval. The contractor must provide all drawings of circuit board layouts and schematics. All PDF format documents must be searchable. At least one PDF format copy of all documents must be provided. The following documentation is to be provided by the contractor:

• Overview

• Operation

• Repair procedures

• Parts list

• Schematic drawings

4. PREPARATION FOR DELIVERY

4.1 Preservation, Packaging, and Packing

Preservation, packaging, and packing shall be IAW Provision 61.

5. Data Deliverables The following is an outline of the deliverables required to be supplied by the contractor along with the CLINs listed in Section 3:

A. Test Data Package B. Overview C. Operation D. Repair Procedures E. Parts list

F. Schematic drawings

File details come from the government source that posted it. Updated .