This document is a two-page architectural floor plan and scope of work for renovation at the Defense Contract Management Agency (DCMA) Pease Air National Guard Base (ANGB). The work involves restoration of an office area (176 SF), conference room (231 SF), and corridor, with specific renovation tasks including:

Office Area Requirements: Jack up workstations to replace carpeting, install a new floor-to-ceiling wall with gypsum board, paint both wall sides with acrylic latex, install a new 3'0" door with matching hardware, and install commercial grade carpet tile and vinyl cove base. Conference Room Requirements: Infill missing rigid foam insulation, install new gypsum wall board, paint walls, remove damaged carpet, install commercial grade carpet tile, install vinyl cove base, repair or replace damaged metal ceiling grid components, and replace approximately 20 missing or damaged ceiling tiles. Corridor Area Work: Install new commercial grade carpet tile and new vinyl cove base. The detailed renovation plan is specifically for the DCMA Pease ANGB location, focusing on comprehensive interior restoration and repair.

View the file

Other files

File Type Posted
Site Visit Sign-in Sheet 07.02.25_FE.pdf PDF
AMND 02.pdf PDF
AMND 01.pdf PDF
FORMSF-25A PAYMENT BOND.pdf PDF
PAST PERFORMANCE QUESTIONNAIRE (2).pdf PDF
SICG030-25.pdf PDF
FORM SF-25 PERFORMANCE BOND.pdf PDF
ACH Vendor Enrollment Form 2022.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11·-4· 0 0

OFFICE

e:::: 176 SF

II

e::::

CONFERENCE ROOM

10'-8"

231 SF

21'-2"

DCMA PEASE ANGB

WORK TO BE PERFORMED

OFFICE:

JACK UP WORKSTATIONS TO REPLACE CARPETING

PROVIDE & INSTALL NEW WALL FROM FLOOR TO CEILING GRID WITH i" GYPSUM WALL BOARD BOTH SIDES FINISH, PRIME & PAINT BOTH SIDES OF NEW WALL COMPLETE WITH 2 COATS OF ACRYLIC LATEX PAINT

....J PROVIDE & INSTALL NEW 3'0 DOOR IN NEW WALL WITH HARDWARE TO MATCH OTHERS IN THE SPACE

PROVIDE & INSTALL NEW COMMERCIAL GRADE CARPET TILE

PROVIDE & INSTALL NEW VINYL COVE BASE AROUND PERIMETER FLOOR

CONFERENCE ROOM:

PROVIDE & INFILL MISSING RIGID FOAM INSULATION

PROVIDE & INSTALL NEW i" GYPSUM WALL BOARD WHERE MISSING, FINISH & PRIME

PAINT CONFERENCE ROOM COMPLETE WITH 2 COATS OF ACRYLIC LATEX PAINT

REMOVE DAMAGED CARPET WHERE APPLICABLE CARPETING

PROVIDE & INSTALL COMMERCIAL GRADE CARPET TILE

PROVIDE & INSTALL VINYL COVE BASE AROUND PERIMETER FLOOR

PAINT OR REPLACE DAMAGED METAL CEILING GRID COMPONENTS

PROVIDE & REPLACE MISSING OR DAMAGED CEILING TILES (APPX 20)

CORRIDOR AREA � PROVIDE & INSTALL NEW NEW COMMERCIAL GRADE CARPET TILE

PROVIDE & INSTALL NEW VINYL COVE BASE