Annex C – Transportation Performance Requirement Standards (PRS)
Task/Requirement Standard Sampling Method, Lot & Acceptable Quality Level (AQL)
Lot size: Unless specified, all Lots are since the last Government performed inspection or 90 days, whichever is shorter.
TRANSPORTATION - GENERAL
5.26.3 Provide reports and statistical data
Timeliness: Reports and statistical data delivered by the due date.
Quality: IAW DLRS ITD-01 Accurate and complete
Surveillance activity report
Lot: Inspect reports submitted per quarter.
AQL: 95%
PERSONAL PROPERTY OPERATIONS
5.27.1 Provide disposition instructions to current DPM contractor for shipments on-hand after expiration of previous DPM contract period.
Timeliness: Disposition documents will be completed prior to the 180th day following the end of the current contract.
Quality: Disposition instructions for shipments on-hand after the end of contract period will be complete and accurate.
Surveillance activity report
LOT: All shipment remaining after expiration of current contract at time of surveillance.
AQL: 100%
5.27.1 Process Incentive Payments and Reimbursements.
Timeliness: Payments and reimbursements will be submitted to the Government rep, within 3 business days of receipt.
Approved payments and reimbursements will be forward to BMO daily and to DFAS weekly.
Quality: Incentive payments and reimbursements will be accurately prepared using applicable government rates in effect at the time of the move and a complete copy will be provided to QAE upon request.
Weights will be entered accurately and completely into AIS.
Random sampling
Lot: Each reimbursement completed at time of surveillance.
AQL: 100%
5.27.1 Statement of Accessorial Services performed.
Timeliness: Submit 619 receipt from TSP statement of accessorial services performed will be submitted to government rep, within 5 business days of receipt and to QAE upon request.
Random sampling
Lot: Each statement of accessorial services performed at time of surveillance.
AQL: 100%
Quality: Shipment documents will correspond to the appropriate shipment record.
5.27.1 Process payments for additional services.
Timeliness: Approved SF 1034 submitted to DFAS within 3 business days of receipt from Government representative.
Quality: Services performed are verified as rendered. SF 1034 is accurate and complete.
Random sampling
Lot: Each SF 1034 completed at time of surveillance.
AQL: 100%
5.27.1 Process certified NTS quarterly invoices from TSP.
Timeliness: Invoices will be submitted to the appropriate DFAS and BMO within 3 business days of receipt from Government representative.
Quality: NTS Quarterly invoice will be accurate, current, and complete.
Random sampling
Lot: Each invoice in process or completed at time of surveillance.
AQL: 95%
5.27.1 Statement of Accessorial Services performed
Timeliness: Approved SF 1034 submitted to DFAS within 3 business days of receipt from Government representative.
Quality: Services performed are verified as rendered. SF 1034 is accurate and complete.
Random sampling
Lot: Each SF 1034 completed at time of
5.27.2 Counsel customers
Timeliness: In conjunction with shipment application and/or movement request.
Quality: Customers will be counseled IAW DTR Part IV, and/or service guidance. Copy will be provided to QAE on request.
Random sampling
Lot: Counseling completed at the time of surveillance.
AQL: 99%
5.27.2 Counsel personnel on entitlements and procedures for pickup, delivery and/or
Timeliness: Personnel counseled with 3 hours of arrival/walk-in time and/or 1 hour of appointment time
Lot: Percent of personnel counseled within 3 hours of arrival/walk-in time;
percent counseled within 1 hour of appointment time.
storage of personal property/household goods
AQL: 90%
5.27.3 Provide Specialized, Expedited Assistance for Sensitive circumstances
Timeliness: To meet member/family member’s needs.
Quality: Blue Bark shipments will be handled IAW DTR Part IV, 410-E, and a complete copy will be provided to QAE on request.
Random sampling
Lot: Blue Bark/Sensitive shipments Completed at the time of surveillance.
AQL: 100%
5.27.4 Route and award personal property shipments for pick up.
Timeliness: Personal Property will be routed and awarded prior to pick up date in shipment application.
Quality: IAW DTR Part IV requirements
Random sampling
Lot: Each shipment or storage lot offered for acceptance.
AQL: 100%
5.27.6 Prepare shipment applications and personally procured movement (PPM) Requests.
Timeliness: Assist DPS customers when required.
Quality: Will be completed IAW DTR Part IV and governing service regulations and a complete copy will be provided to QAE on request.
Random sampling
Lot: Shipments applications and self-movement requests completed at the time of surveillance.
AQL: 95%
5.27.8 Conduct Quality Control inspections for personal property movements
Timeliness: Conduct in person QC inspections on a minimum of 100% percent of personal property movements (Physical or telephonic) during pack-out or move-in. Conduct QC inspections on 100 percent of Blue Bark and Gold Star Shipments
Random sampling
Percent of in-person QC inspections conducted.
AQL: 75%
5.27.9 Collect Excess Costs.
Timeliness: DD 139 prepared within the same week excess costs are discovered / determined; approved 139 will be submitted to DFAS as required. DD1131 prepared in the same week monies are received;
submitted to Government rep, for deposit weekly.
Random sampling
Lot: Collection forms completed at time of surveillance.
DD Form 139 or DD Form 1131 will be prepared and maintained completely and accurately. Provide a copy to QAE upon request.
5.27.9 Process request for extension of travel and transportation entitlements.
Timeliness: Review and forward to Government rep, within 5 business days of receipt.
Approved requests will be returned to the requestor the next business day.
Quality: Requests will be reviewed for eligibility. Requests forwarded to ITO will be complete, accurate, and contain all appropriate supporting documents/copies required by the JTR and an approval/recommendation letter for ITO signature and provide a copy to QAE upon request.
Random sampling
Lot: Each extension in process or completed at time of surveillance.
AQL: 90%
5.27.9.1 Process change in destination Requests.
Timeliness: Initiate tracer action Diversions: Initiate diversion immediately upon notice of change in destination.
Delivery from SIT/DPM Warehouse:
Coordinate the release from warehouse within 5 days of receipt of request for shipment.
Quality: Certificates of diversion, Certificates for Long Delivery-Out-of- SIT, and DPM reshipment instructions prepared, completed, approved and distributed accurately and completely and a complete copy will be provided to QAE on request.
Random sampling
Lot: Each change In destination in process or completed at time of surveillance.
AQL: 95%
MOTOR POOL OPERATIONS
5.29.1 Timeliness: By COB daily notify COR
upon discovery.
Control & Account for GSA vehicles, keys, and credit cards report loss/abuse
Quality: Complete & accurate Lot: Each GSA vehicle hand receipt completed at time of surveillance.
AQL: 99%
5.29.1 Maintain hand receipts on GSA vehicles
Timeliness: Hand receipts updated annually, as a minimum.
Quality: Complete & accurate
Random sampling
Lot: Each GSA vehicle hand receipt completed at time of surveillance.
AQL: 98%
5.29.1 Pick up and deliver vehicles
Timeliness: Vehicles pickup within (5) business days when notified.
Quality: Pick up & delivery to designated area.
Random sampling
Lot: Each vehicle requiring pickup and delivery completed at time of surveillance.
AQL: 98%
5.29.1 Maintain a copy of justification on each motor vehicle utilized for official use and notify users when it is due to expire excluding LSEV.
Timeliness: Annually
Quality: Justification must meet the requirements of AR 58-1.
Random sampling
Lot: GSA vehicle justifications prepared each year.
AQL: 100%
5.29.3 Receive requests for motor transportation
Timeliness: Requests reviewed and submitted to government rep, by COB.
Quality: Requests are complete and accurate prior to government rep, manual or telephonic approval.
Random sampling
Lot: Each request for motor transportation completed at time of surveillance.
AQL: 99%
5.29.3 Inspect & dispatch GSA vehicles and GSA credit cards
Timeliness: Vehicle inspected at time of dispatch and upon return. LSEV inspected and dispatch quarterly.
FORSCOM decal affixed prior to initial dispatch
Quality: Inspection shall be performed accurately
Random sampling
Lot: Each GSA vehicle dispatch in process or completed at time of surveillance.
5.29.4 Operate buses and other non-tactical vehicles
Timeliness: To meet mission requirements.
Quality: Vehicles operated safely.
Random sampling
Lot: Each special mission requirement completed at time of surveillance.
AQL: 99%
5.29.11 Schedule for Maintenance of GSA vehicles.
Timeliness: Users notified 5 business days prior to scheduled maintenance date
Quality: Scheduled maintenance performed.
Surveillance activity checklist
Lot: Each GSA vehicle requiring maintenance completed at time of surveillance.
AQL: 95%
UNIT MOVEMENTS
5.30.1 Provide necessary assistance to the Unit Movement Coordinator (UMC) with unit movement data maintenance and movement planning.
Timeliness: Meet UMC’s processing times.
Quality: All unit moves completed as required.
Surveillance activity checklist
Lot: Each unit move
AQL: 97%
5.30.1 Document loaded equipment Properly
Timeliness: Upon completion of loading.
Quality: Load data will be obtained complete and accurate.
Random sampling
Lot: Each piece of equipment loaded in process or completed at time of surveillance
AQL: 99%
5.30.1 Utilize Radio Communications
Timeliness: At all times during unit movement.
Quality: Radios are operational during unit movements.
Random sampling
Lot: Inspect transportation operation in process or completed at time of
AQL: 95%
5.30.2 Timeliness: Meet UMC’s processing
times.
Assist and advise unit movement planning and coordination
Quality: Assist and advise UMO training 100 percent of the time
Lot: Each unit move
CARGO MOVEMENTS
5.31.1 Route military cargo and equipment.
Timeliness: To meet mission requirements
Quality: Shipment will be routed IAW DTR PART II. Data entry into ETA/FAST/GFM CMOS will be accurate and complete.
Random sampling
Lot: Each shipment competed at time of surveillance.
AQL: 100%
5.31.2 Hazardous materials, oversized, sensitive items properly identified, documented, marked, labeled, and/or placarded
Timeliness: Prior to preparation of
GBL/CBL.
Quality: Certified HazMat preparers are verified; documents are complete and accurate.
Random sampling
Lot: Each hazardous materials, oversized, sensitive shipments in process or completed at time of surveillance.
AQL: 100%
CONTAINER YARD OPERATIONS
5.33.1 Download, upload, reposition, retrieve, and transport containers
Timeliness: To meet training exercise/deployment requirements with no additional commercial charges being incurred.
For non-deployment movement, when current scheduled workload permits support.
Quality: Containers placed safely and correctly at designated location.
Random sampling
Lot: Each container transported in process or completed at time of surveillance.
AQL: 99%
5.33.1 Issue & Receive ISO containers
& MILVANS
Timeliness: Control document prepared for each asset at the time of transfer.
Quality: Completely & accurately.
Random sampling
Lot: Each control document in process or completed at time of surveillance.
AQL: 100%
5.33.1 Timeliness: NLT 2 1/2 years from date
of last certification.
Inspect & certify ISO containers.
Quality: To meet international CSC standards.
Lot: Each ISO container in process or completed at time of surveillance.
AQL: 95%
5.33.1 Arrange for scheduled and/or emergency maintenance of light sets.
Timeliness: Scheduled: IAW manufacturer’s recommendation Emergency: Same day
Quality: Required maintenance scheduled.
Random sampling
Lot: Each light set scheduled for maintenance at time of surveillance.
AQL: 100%
5.33.1 Reposition or retrieve light sets
Timeliness: Within 48 hours of directive.
Quality: Lights sets relocated safely to designated location.
Random sampling
Lot: Number of light sets repositioned/retrieved or completed at time of surveillance.
AQL: 95%
5.33.2 Conduct inventory of ISO containers and light sets
Timeliness: Containers: Inventoried & reported quarterly.
Light sets: Reported NLT 5th business day of each month.
Quality: Completely & accurately
Random sampling
Lot: Each inventory completed at time of surveillance.
AQL: 99%
5.33.2 Manage containers
Timeliness: 100 percent of containers used for movement are ISO compliant prior to use
Random sampling
AQL: 90%
RAIL OPERATIONS
5.34.1 Perform operator level maintenance on on-hand government owned locomotives
Timeliness: IAW applicable maintenance manuals and to meet mission requirements.
Quality: Complete & accurate
Random sampling
Lot: Each maintenance inspection completed at time of surveillance.
AQL: 100%
5.34.1 Order all required petroleum liquids and lubricants for locomotives.
Timeliness:
Fuel: Ordered when on hand fuel reaches 1000 gallons minimum.
Oil: Ordered when on hand oil reaches 110 gallons minimum.
Surveillance Activity Checklist
Lot: Inspect fuel order request per quarter.
Oil sample: submitted every 25 hours of operation or 90 days, whichever occurs first.
Quality: fuel & petroleum levels maintained at or above level of ordering.
AQL: 97%
5.34.1 Take oil samples for oil test
Timeliness: oil sample: submitted every 25 hours of operation or 90 calendar days, whichever occurs first.
Quality: Completely, efficiently, and effectively.
Random sampling
Lot: Inspection completed at time of surveillance.
AQL: 100%
5.34.1 Coordinate for track repairs & foliage/debris removal.
Timeliness: Second and fourth week of each month.
Quality: Completely, efficiently, and effectively.
Random sampling
Lot: Track coordination performed and complete at time of surveillance.
AQL: 95%
5.34.1 Control Government and/or Commercial Security Seals
Timeliness: To meet mission requirements.
Quality: Security seals will be properly requisitioned, received, controlled, and utilized.
Surveillance Activity Checklist
Lot: Inspect security seals inventory
AQL: 99%
5.34.1 Process inbound freight documentation
Timeliness: SF 361, Discrepancy report, and necessary reshipment will be completed within 30 calendar days of receipt of shipment.
Quality: Misconsigned and/or mismarked shipments will be correctly re-consigned inbound shipment documentation processed, recorded, and reviewed promptly and accurately.
Random sampling
Lot: Each inbound shipment received, or completed at time of surveillance.
AQL 95%
5.34.1 Movement of DODX Railcars
Timeliness: Disposition instructions from SDDC will be requested within 2 business days of notification of completion of mission. Coordinate with TSP to meet SDDC timelines. CBL will be provided to TSP at the time of pick up.
Quality: DODX cars will be completely and safely moved. Random sampling
Lot: Each request for DODX railcar movement completed at time of surveillance.
AQL: 99%
5.34.2 Provide loaded/empty rail car numbers to TSP, UMC, & SDDC;
release rail cars to TSP.
Timeliness: Within 4 hours of interchange.
Quality: Information & release order is complete and accurate.
Surveillance activity checklist
Lot: Inspect rail car load plan completed at time of surveillance.
AQL: 99%
5.34.3 Coordinate interchange with
TSP
Timeliness: Coordination completed not less than 24 hours prior to arrival/departure of railcars.
Quality: To meet mission requirements.
Surveillance activity checklist
Lot: Inspect interchange completed at time of surveillance.
AQL: 97%
5.34.3 Protect Rail Crossings
Timeliness: Prior to Locomotive approach at pedestrian/vehicle crossing.
Quality: Completely and safely.
Flagmen will possess PPE which is visible in day and night.
Surveillance activity checklist
Lot: Each track crossing protected at time of surveillance.
AQL: 100%
5.34.3 Perform Interchange with rail carrier. Clear obstructions on track.
Timeliness: Arrive 30 minutes prior to scheduled interchange. Obstructions cleared to allow timely arrival at interchange.
Quality: Safely and efficiently.
Surveillance activity checklist
Lot: Inspect interchange with Carrier.
AQL: 98%