Attachment 002 - Statement of Work.pdf

PDF 1 MB Posted

Attached to
Blackrock Jackson Cabin Spray Foam Insulation Federal contract opportunity
Solicitation number
1282B125Q0025
Issued by
Department of Agriculture Forest Service

About this file

This Statement of Work describes a thermal insulation project for the Bridger-Teton National Forest involving the application of closed-cell spray foam insulation in the crawl spaces of ten housing units across three locations: Cottonwood Work Center, Rosencrans Lane, and Blackrock Work Center in Wyoming. The project aims to address recurring issues with water pipe freezing by insulating the bottom side of floor joists and interior of metal skirting in the crawl spaces of recently constructed Conestoga log cabins.

The specification requires high-density polyurethane spray foam insulation with specific performance characteristics, including an R-6.8 R-Value per inch at 2" thickness and air leakage less than 0.001 l/s/m2 at 75 Pa. The basis of design product is BASF Spraytite 178 closed-cell polyurethane foam. The project is scheduled to start on 6/16/2025 and will run through 9/30/2025, with qualified, experienced spray applicators required to perform the installation following detailed substrate preparation and application guidelines.

View the file

Other files for this federal contract opportunity

Other files attached to Blackrock Jackson Cabin Spray Foam Insulation, newest first.
File Type Posted
Attachment 005 - Larger House Drawings.pdf PDF
Amendment 0001 - SF-30 - 1282B125Q0025_S.pdf PDF
Attachment 004 - Smaller House Drawings.pdf PDF
Solicitation 1282B125Q0025 1147886.pdf PDF
Attachment 001 - Schedule of Items.pdf PDF
Attachment 003 - WD 2015-5409.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

GENERAL SPECIFICATIONS

0403 SERV NEW Blackrock Jackson Cabin Spray Foam

February 2025

1.1 SCOPE OF CONTRACT

A. The Bridger-Teton National Forest (Forest) is seeking a vendor to apply closed cell spray-foam insulation within the crawl spaces of ten (10) housing units. The Forest’s Jackson and Blackrock Ranger Districts have three (3) housing locations that are dedicated to current and future employees. Housing locations are further described in Project Location section below. All units are Conestoga log cabins with corrugated metal skirting sheets that line the foundation beneath the deck, also known as the crawl space. All the log cabins have been constructed within the past 3 years.

Although recently constructed, the fully constructed cabins do not have the adequate insulation required to maintain above-freezing water temperatures throughout the winter season. The water lines consistently freeze and the limited maintenance staff on the Forest manually thaws the water pipes in the crawl space in order address these issues at least once every year. Due to the consistency of resident complaints, the Forest is seeking the insulation service. The insulation shall be applied to bottom-side of the floor joists and the interior of the metal skirting, located within the crawl space of the units. See photo below.

Crawl space location, now covered with metal skirting

Figure 1 - Cottonwood Work Center Log Cabins

Attachment 002 - Statement of Work

1.2 PROJECT LOCATION

A. The project is located at three housing locations associated with the Bridger-Teton National Forest:

1. Cottonwood Work Center:

13000 South Fall Creek Road #450 Jackson, WY 83001

13000 South Fall Creek Road #452 Jackson, WY 83001 13000 South Fall Creek Road #454 Jackson, WY 83001 13000 South Fall Creek Road #456 Jackson, WY 83001

2. Rosencrans Lane:

27 Rosencrans Lane, Jackson, WY, 83001 29 Rosencrans Lane, Jackson, WY, 83001

35 Rosencrans Lane, Jackson, WY, 83001

3. Blackrock Work Center:

20255 East HWY 26/287 #625, Moran, WY 83013 20255 East HWY 26/287 #626, Moran, WY 83013

20255 East HWY 26/287 #627, Moran, WY 83013

Housing Area Locations for 0403 SERV NEW Blackrock Jackson Cabin Spray Foam

13000 South Fall Creek Road Units #450, #452, #454, #456

Latitude, Longitude: 43.293768, -110.796781

Directions: From the Town of Jackson, drive South on United States Highway 89 for approximately 13 miles. At the roundabout, take the first exit to continue on United States

Highway 89 for another 4 miles. Turn Right on South Fall Creek Road. Bear right onto S Fall Creek Road. Keep right until arrival at log cabins with green roofs.

27, 29, 35 Rosencrans Drive, Jackson WY 83001

Latitude, Longitude: 43.293768, -110.796781

Directions: From the Town of Jackson, navigate to Bridger-Teton National Forest Administrative Office/Information Center at 340 North Cache Street, Jackson, WY 83001. Turn right onto

Rosencrans drive. Continue on Rosencrans Drive for approximately 0.25 miles until arrival at log cabins with green roofs.

20255 East HWY 26/287 Units #625, #626, #627

Latitude, Longitude: 43.831711, -110.347490

Directions: From the Town of Jackson, drive North on United States Highway 89 for approximately 8 miles. At the roundabout take the second exit to continue on United Sates Hieghway 89 for approximately 32 miles. Turn left onto Forest Service Road. Continue on Forest Service Road for approximately 1 mile until arrival at log cabins with green roofs.

1.3 SITE INFORMATION AND LIMITATIONS

A. No work items will be government furnished. Information on access to facilities and crawl spaces can be made available upon request of the contractor. The contractor will need to coordinate access to the facilities, specifically if access is needed outside of regular business hours, 8:00am-4:30pm, Monday through Friday.

B. Utilities are available at the site for construction purposes.

C. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:

1. Items noted as under warranty by manufacturer.

1.4 STAGING AND STORAGE AREAS

A. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage trailers (work) on site.

1.5 INSPECTION OF WORKSITE

A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.

1.6 START DATE

A. Estimated 6/16/2025

1.7 Period of Performance

A. 6/16/2025 through 9/30/2025

USDA FOREST SERVICE, R-4

BRIDGER-TETON NATIONAL FOREST

JACKSON & BLACKROCK RANGER DISTRICTS

SECTION 072100 - THERMAL INSULATION

PART 1 – GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. High Density Spray Foam Polyurethane insulation – sprayed in beneath floor joists and inside of corrugated panels within the crawl space

1.2 SUBMITTALS

A. Product Data: For each type of product indicated.

1.3 QUALITY ASSURANCE

A. Source Limitations: Obtain each type of building insulation through one source from a single manufacturer.

B. Fire-Test-Response Characteristics: Provide insulation and related materials with the fire-test-response characteristics indicated, as determined by testing identical products per test method indicated below by UL or another testing and inspecting agency acceptable to authorities having jurisdiction. Identify materials with appropriate markings of applicable testing and inspecting agency.

1. Surface-Burning Characteristics: ASTM E 84.

2. Fire-Resistance Ratings: ASTM E 119.

3. Combustion Characteristics: ASTM E 136.

1.4 DELIVERY, STORAGE, AND HANDLING

A. Protect insulation materials from physical damage and from deterioration by moisture, soiling, and other sources. Store inside and in a dry location. Comply with manufacturer's written instructions for handling, storing, and protecting during installation.

1.5 MEASUREMENT AND PAYMENT

A. There will be no separate measurement or payment for work in this section. Payment will be included at the contract unit price as shown on the Schedule of Items.

PART 2 - PRODUCTS

2.1 SPRAY-IN-PLACE POLYURETHANE INSULATION

A. Polyisocyanurate Spray Foam Insulation Systems shall be applied by qualified, experienced spray applicators.

1. Basis of Design Product – BASF Spraytite 178 closed-cell polyurethane foam insulation and air barrier to meet the following standards:

a. R-6.8 R-Value per inch, 2” thick

b. Air Leakage <0.001 l/s/m2 @ 75 Pa at 1.5” thickness

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates and conditions, with Installer present, for compliance with requirements of Sections in which substrates and related work are specified and for other conditions affecting performance.

1. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Clean substrates of substances harmful to insulation or vapor retarders, including removing projections capable of puncturing vapor retarders or of interfering with insulation attachment.

3.3 INSTALLATION, GENERAL

A. Comply with insulation manufacturer's written instructions applicable to products and application indicated.

B. Install insulation that is undamaged, dry, and unsoiled and that has not been left exposed at any time to ice, rain, and snow.

C. Extend insulation in thickness indicated to envelop entire area to be insulated. Spray around obstructions and fill voids with insulation. Remove projections that interfere with placement.

D. Water-Piping Coordination: If water piping is located within insulated exterior walls, coordinate location of piping to ensure that it is placed on warm side of insulation and insulation encapsulates piping.

3.4 INSTALLATION OF GENERAL BUILDING INSULATION

A. Apply insulation units to substrates by method indicated, complying with manufacturer's written instructions.

B. Sprayed Polyurethane installation:

1. Substrate Preparation:

a. For optimum results, surfaces to receive polyurethane insulation should be clean and dry, free of dirt, oil, loose particles, frost, moisture, and other foreign matter. Primers are rarely used but should incorporated as follows;

1) Plywood, OSB, Structural Lumber; substrates shall be dry and free from contaminants, moisture, frost, and shall not have a moisture content above 15%. Generally a primer for these surfaces is not required. Heating and drying these surfaces during winter conditions generally brings these substrates into compliance. If a primer is required it shall be Acryprime – Substrate as manufactured by Resin Technology or equal.

2. Polyurethane Foam Insulation Application:

a. Apply Spray Foam Polyurethane Insulation, if possible, in full thickness lifts

b. Special care shall be taken to seal all penetrations of conduit, piping, coax, romex and other obstructions within the floor where they pass from cavity to the next cavity. Dead corners or blocked out framing areas shall be drilled and foam-filled to eliminate “hot/cold spots”. Areas of excessive blocked out areas shall be reported to the General Contractor for correction.

c. Follow manufacturers recommended procedures for temperatures and preparation of substrates.

3.5 PROTECTION

A. Protect installed insulation and vapor retarders from damage due to harmful weather exposures, physical abuse, and other causes. Provide temporary coverings or enclosures where insulation is subject to abuse and cannot be concealed and protected by permanent construction immediately after installation.

END OF SECTION

March 2025

Section C - Description/Specifications/Statement of Work
1. Items noted as under warranty by manufacturer.
1. High Density Spray Foam Polyurethane insulation – sprayed in beneath floor joists and inside of corrugated panels within the crawl space
1. Surface-Burning Characteristics: ASTM E 84.
2. Fire-Resistance Ratings: ASTM E 119.
3. Combustion Characteristics: ASTM E 136.
1. Basis of Design Product – BASF Spraytite 178 closed-cell polyurethane foam insulation and air barrier to meet the following standards:
1. Proceed with installation only after unsatisfactory conditions have been corrected.
1. Substrate Preparation:
2. Polyurethane Foam Insulation Application: