Attachment 002- Statement of Work.pdf

PDF 6 MB Posted

Attached to
GAOA Bessey Group Electrical
Solicitation number
1282B125R0009
Issued by

About this file

This is a Statement of Work detailing electrical upgrade requirements for campground facilities at the Bessey Ranger District in Halsey, Nebraska. The project involves removing existing electrical systems and RV pedestals at the Cedar Loop and Group campsites and installing new electrical systems with new campsite RV pedestals.

The work includes coordinating with Custer Public Power for transformer replacement, obtaining required permits and state electrical inspections, and following specific work restrictions such as limiting work hours to 7:30 AM - 6:00 PM Monday through Friday. The contractor must provide all labor, materials, equipment, licenses and permits. The location is at 40637 River Loop, Halsey, NE, approximately 12 miles east of Thedford. The contractor must submit various documentation including shop drawings, operation/maintenance manuals, and construction photographs. The government will allow use of one designated campsite with electrical hookup for the contractor's self-contained camper, subject to availability and timing. Questions are due by 5:00 PM MST on January 22, 2025 to heather.cole@usda.gov.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USDA Forest Service – Region 2 Bessey Group/Cedar Loop Campground Upgrade Halsey, Nebraska

011000 - 1 SUMMARY OF WORK

SECTION 011000 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Project information.

2. Work covered by Contract Documents.

3. Contractor's use of site and premises.

4. Work restrictions.

5. Specification and Drawing conventions.

6. Miscellaneous provisions.

B. Related Requirements:

1. Section 015000 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1.3 DEFINITIONS

A. Work Package: A group of specifications, drawings, and schedules prepared by the design team to describe a portion of the Project Work for pricing, permitting, and construction.

1.4 PROJECT INFORMATION

A. Project Identification: GAOA 22 Bessey Group/Cedar Loop Campground Electrical Upgrade project.

1. Project Address: 40637 River Loop, Halsey, NE 69142.

2. Project Location: This project is located at the Bessey Ranger District, located in

Thomas County Nebraska, 12 miles east of Thedford, NE on Highway 2.

3. Site Conditions: The elevation of the site is approximately 2,710 feet above mean sea level. The site experiences an average of 23.3 inches of precipitation per year with an average high of 86 degrees Fahrenheit in July and an average low of 34 degrees Fahrenheit in January.

Attachment 002- Statement of Work

Halsey, Nebraska

011000 - 2 SUMMARY OF WORK

B. Owner: United States Department of Agriculture Forest Service, Region 2; Nebraska National Forests and Grasslands; Bessey Ranger District.

1.5 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of Project is defined by the Contract Documents and includes, but is not limited to, the following:

1. The intent of the contract is to provide for the complete construction of the project as described in the contract and other Work indicated in the Contract Documents. The project requires the contractor to be responsible for supplying all labor, materials, equipment, miscellaneous items, freight, delivery, and all necessary valid licenses and permits required to complete work identified.

2. Work of this project consists of removing the existing electrical system and campsite RV pedestals that feed the Cedar Loop and Group campsites and installing a new electrical system with new campsite RV pedestals.

3. Contractor will need to coordinate with Custer Public Power for replacement of service transformer by the Utility.

B. Type of Contract:

1. Project will be constructed under a single prime contract.

1.6 CONTRACTOR'S USE OF SITE AND PREMISES

A. Use of Site: Contractor shall have full use of Project site for construction operations during construction period. Contractor's use of Project site is limited only by Government's special events in the fall that will be coordinated with contractor that may dictate construction starting schedule. The Government may close both campgrounds to public use during construction depending on timing of construction activities and the time of year they are occurring.

B. Limits on Use of Site: Limit use of Project site to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Full Government Occupancy: Government will occupy site and existing buildings during entire construction period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage.

Perform the work so as not to interfere with Government's day-to-day operations.

2. Driveways, Walkways and Entrances: Keep driveways parking areas, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or for storage of materials. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Government and authorities having jurisdiction.

011000 - 3 SUMMARY OF WORK

a. Schedule deliveries to minimize use of driveways and entrances by construction operations.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

C. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period.

Repair damage caused by construction operations.

1.7 WORK RESTRICTIONS

A. On-Site Work Hours: Limit work to between 7:30 a.m. to 6:00 p.m., Monday through Friday, unless otherwise indicated. Work hours may be modified to meet Project requirements if approved by Owner and authorities having jurisdiction.

B. Noise, Vibration, Dust, and Odors: Coordinate operations that may result in high levels of noise and vibration, dust, odors, or other disruption to Owner occupancy with Owner.

C. Nonsmoking Buildings: Smoking is not permitted within the buildings or within 25 feet of entrances, operable windows, or outdoor-air intakes.

D. Smoking and Controlled Substance Restrictions: Use of tobacco products, alcoholic beverages, and other controlled substances on Project site is not permitted.

E. Sanitary Facilities: Use of on-site Government sanitary facilities (vault style toilet located near the Group Campground) will be permitted. Contractor is responsible for cleaning said toilet facility periodically and at completion of project.

F. Overnight camping at one designated campsite with electrical hookup for a “self-contained” camper may be available for contractor use depending on timing of work.

Location and availability will be decided at the pre-work meeting when a schedule is established with the contractor.

G. Employee Screening: Comply with Government's requirements for drug and background screening of Contractor personnel working on Project site.

1. Maintain list of approved screened personnel with Contracting Officer (CO).

1.8 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

011000 - 4 SUMMARY OF WORK

2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

B. Division 00 Contracting Requirements: General provisions of the Contract, including General and Supplementary Conditions, apply to all Sections of the Specifications.

C. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

D. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:

1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.

2. Abbreviations: Materials and products are identified by abbreviations scheduled on Drawings.

3. Keynoting: Materials and products are identified by reference keynotes referencing Specification Section numbers found in this Project Manual.

1.9 MISCELLANEOUS PROVISIONS

A. Confine storage of materials to areas as approved by the Contacting Officer.

B. Provide adequate signing and barricades and take necessary safety measures to protect the public during all construction operations. Minimize disturbance of all undisturbed areas.

C. Field verify all new and existing dimensions affecting the work of this contract before ordering products.

D. Obtain permits for work required by County, State, or Federal laws or regulations.

E. State electrical inspection is required for this project. Obtain permits for electrical work if the State Electrical Inspector requires a permit to perform the inspection. Contractor is responsible for coordinating/scheduling inspections.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION

012600 - 1 CONTRACT MODIFICATION

PROCEDURES

SECTION 012600 - CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for handling and processing Contract modifications.

1.3 MINOR CHANGES IN THE WORK

A. Government will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time.

1.4 PROPOSAL REQUESTS

A. Government-Initiated Proposal Requests: will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.

1. Work Change Proposal Requests issued by Government are not instructions either to stop work in progress or to execute the proposed change.

2. Within 20 days, when not otherwise specified, after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.

a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

c. Include costs of labor and supervision directly attributable to the change.

d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

012600 - 2 CONTRACT MODIFICATION

B. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the Contract, Contractor may initiate a claim by submitting a request for a change to Government. Claim must be submitted prior to performing any proposed work.

1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.

2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

4. Include costs of labor and supervision directly attributable to the change.

5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

1.5 CHANGE ORDER PROCEDURES

A. On Government's approval of a Work Change Proposal Request, Government will issue a Change Order for signatures of Government and Contractor.

1.6 CONSTRUCTION CHANGE DIRECTIVE

A. Construction Change Directive: Construction Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.

1. Construction Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time.

B. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive.

1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.

1.7 WORK CHANGE DIRECTIVE

A. Work Change Directive: Work Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.

1. Work Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time.

012600 - 3 CONTRACT MODIFICATION

B. Documentation: Maintain detailed records on a time and material basis of work required by the Work Change Directive.

1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 012600

012600 - 4 CONTRACT MODIFICATION

PAGE INTENTIONALLY LEFT BLANK

012900 - 1 PAYMENT PROCEDURES

SECTION 012900 - PAYMENT PROCEDURES

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment.

B. Related Requirements:

1. Section 012600 "Contract Modification Procedures" for administrative procedures for handling changes to the Contract.

1.3 DEFINITIONS

A. Schedule of Values: A statement furnished by Contractor allocating portions of the Contract Sum to various portions of the Work and used as the basis for reviewing Contractor's Applications for Payment.

1.4 APPLICATIONS FOR PAYMENT

A. Each Application for Payment following the initial Application for Payment shall be consistent with previous applications and payments, as certified by Contracting Officer Representative and paid for by Government.

B. Application for Payment Forms: Invoices will be submitted through the Invoice Processing Platform (IPP). Each submission must include an invoice formatted to match the Schedule of Items, Certified Payroll and a Certification of Progress Payments form supplied by the Government. This process will be discussed at the pre-work meeting.

C. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Contracting Officer Representative will return incomplete applications without action.

1. Entries shall match data on the schedule of values and Contractor's construction schedule. Use updated schedules if revisions were made.

012900 - 2 PAYMENT PROCEDURES

D. Stored Materials: Include in Application for Payment amounts applied for materials or equipment purchased or fabricated and stored, but not yet installed. Differentiate between items stored on-site and items stored off-site.

1. Provide certificate of insurance, evidence of transfer of title to Government, and consent of surety to payment for stored materials.

2. Provide supporting documentation that verifies amount requested, such as paid invoices. Match amount requested with amounts indicated on documentation; do not include overhead and profit on stored materials.

3. Provide summary documentation for stored materials indicating the following:

a. Value of materials previously stored and remaining stored as of date of previous Applications for Payment.

b. Value of previously stored materials put in place after date of previous Application for Payment and on or before date of current Application for Payment.

c. Value of materials stored since date of previous Application for Payment and remaining stored as of date of current Application for Payment.

E. Transmittal: Submit as required by the Contracting Officer.

1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.

F. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following as applicable:

1. List of subcontractors.

2. Schedule of values.

3. Contractor's construction schedule (preliminary if not final).

4. Submittal schedule (preliminary if not final).

5. Copies of building permits.

6. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work.

7. Initial progress report.

8. Report of preconstruction conference.

9. Certificates of insurance and insurance policies.

10. Performance and payment bonds.

G. Application for Payment at Substantial Completion: After Government issues the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.

1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.

a. Complete administrative actions, submittals, and Work preceding this application, as described in Section 017700 "Closeout Procedures."

012900 - 3 PAYMENT PROCEDURES

H. Final Payment Application: After completing Project closeout requirements, submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:

1. Evidence of completion of Project closeout requirements.

2. Certification of completion of final punch list items.

3. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.

4. Updated final statement, accounting for final changes to the Contract Sum.

5. Evidence that claims have been settled.

6. Final meter readings for utilities, a measured record of stored fuel, and similar data as of date of Substantial Completion or when Owner took possession of and assumed responsibility for corresponding elements of the Work.

7. Final liquidated damages settlement statement.

8. Proof that taxes, fees, and similar obligations are paid.

9. Waivers and releases.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 012900

012900 - 4 PAYMENT PROCEDURES

013119 - 1 PROJECT MEETINGS

SECTION 013119 - PROJECT MEETINGS

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 specification sections apply to this section.

1.2 SUMMARY

A. This section specifies administrative and procedural requirements for project meetings including but not limited to:

1. Preconstruction conference.

2. Coordination meetings.

3. Progress meetings.

4. Construction schedule.

1.3 PRECONSTRUCTION CONFERENCE

A. The Contracting Officer will schedule a pre-construction conference and organizational meeting at the project site or other convenient location after execution of the Agreement between Government and Contractor and prior to commencement of construction activities. Government will conduct the meeting to review responsibilities and personnel assignments.

B. Attendees: The Contracting Officer, Contracting Officer's Representative, Contractor and superintendent, major subcontractors, and other concerned parties shall each be represented at the conference by persons familiar with and authorized to conclude matters relating to the work.

C. Agenda: Discuss items of significance that could affect progress, including such topics as:

1. Tentative construction schedule.

2. Critical work sequencing.

3. Designation of responsible personnel.

4. Procedures for processing field decisions and Change Orders.

5. Procedures for processing Applications for Payment.

6. Distribution of Contract Documents.

7. Submittal of shop drawings, product data, and samples.

8. Preparation of record documents.

9. Use of the premises.

013119 - 2 PROJECT MEETINGS

10. Office, work and storage areas.

11. Equipment deliveries and priorities.

12. Working hours.

13. Housekeeping.

D. The Contractor will record and issue pre-construction conference meeting minutes no later than five (5) calendar days after the conference.

1.4 COORDINATION MEETINGS

A. Contractor shall conduct project coordination meetings on an as-needed basis convenient for all parties involved. Project coordination meetings are in addition to specific meetings held for other purposes, such as regular progress meetings and special pre-installation meetings.

B. Contractor shall request representation at each meeting by every party currently involved in coordination or planning for the construction activities involved.

1.5 CONSTRUCTION PROGRESS MEETINGS

A. Contractor shall conduct construction progress meetings at the project site at intervals convenient for all parties involved. The meetings for the duration of the project will be regularly scheduled at the pre-construction conference and shall be coordinated with preparation of the payment request.

B. Attendees: In addition to the Contractor and Contracting Officer's Representative, each Subcontractor, or other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings by persons familiar with the project and authorized to conclude matters relating to progress.

C. Contractor's Construction Schedule: Review progress since the last meeting.

Determine where each activity is in relation to the Contractor's Construction Schedule, whether on time, ahead of, or behind schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so.

Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the contract time.

D. Review the present and future needs of each entity present, including such items as:

1. Interface requirements

2. Time

3. Sequences

4. Status of submittals

5. Deliveries

6. Off-site fabrication problems

7. Access

8. Site utilization

013119 - 3 PROJECT MEETINGS

9. Temporary facilities and services

10. Hours of work

11. Hazards and risks

12. Housekeeping

13. Quality and work standards

14. Change orders

15. Documentation of information for payment requests

16. Updating of Record Documents

E. Contractor shall record and issue meeting minutes for all construction progress meetings to all attendees and parties involved no later than five (5) calendar days after each meeting.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 013119

013119 - 4 PROJECT MEETINGS

013233 - 1 PHOTOGRAPHIC

DOCUMENTATION

SECTION 013233 - PHOTOGRAPHIC DOCUMENTATION

1.1 SUMMARY

A. Section includes administrative and procedural requirements for the following:

1. Preconstruction photographs.

2. Concealed Work photographs.

3. Periodic construction photographs.

4. Final Completion construction photographs.

B. Related Requirements:

1. Section 017700 "Closeout Procedures" for submitting photographic documentation as Project Record Documents at Project closeout.

1.2 INFORMATIONAL SUBMITTALS

A. Digital Photographs: Submit image files within three days of taking photographs.

1. Submit photos by emailing to the Contracting Officer’s Representative.

2. Identification: Provide the following information with each image description in web-based Project management software site:

a. Name of Project.

b. Name of Contractor.

c. Date photograph was taken.

d. Description of location, vantage point, and direction.

1.3 FORMATS AND MEDIA

A. Digital Photographs: Provide color images in JPG format, produced by a digital camera with minimum sensor size of 12 megapixels, and at an image resolution of not less than 3200 by 2400 pixels. Use flash in low light levels or backlit conditions.

B. Digital Images: Submit digital media as originally recorded in the digital camera, without alteration, manipulation, editing, or modifications using image-editing software.

C. File Names: Name media files with date, Project area and sequential numbering suffix.

013233 - 2 PHOTOGRAPHIC

1.4 CONSTRUCTION PHOTOGRAPHS

A. General: Take photographs with maximum depth of field and in focus.

B. Preconstruction Photographs: Before commencement of the Work, take photographs of Project site and surrounding properties, including existing items to remain during construction, from different vantage points, as directed by Contracting Officer's Representative.

1. Take photographs to show existing conditions adjacent to property before starting the Work.

2. Take photographs of existing buildings either on or adjoining property, to accurately record physical conditions at start of construction.

3. Take additional photographs as required to record settlement or cracking of adjacent structures, pavements, and improvements.

C. Concealed Work Photographs: Before proceeding with installing work that will conceal other work, take photographs sufficient in number, with annotated descriptions, to record nature and location of concealed Work, including, but not limited to, the following:

1. Underground utilities.

2. Underslab services.

3. Electrical conduit.

D. Periodic Construction Photographs: Take photographs as appropriate to provide the most beneficial evidence to the Government of installed products and layout. Select vantage points to show status of construction and progress since last photographs were taken.

E. Final Completion Construction Photographs: Take photographs after date of Substantial Completion for submission as Project Record Documents. Contracting Officer's Representative will inform photographer of desired vantage points.

F. Additional Photographs: Contracting Officer's Representative may request photographs in addition to periodic photographs specified.

1. Three days' notice will be given, where feasible.

2. In emergency situations, take additional photographs within 24 hours of request.

3. Circumstances that could require additional photographs include, but are not limited to, the following:

a. Special events planned at Project site.

b. Immediate follow-up when on-site events result in construction damage or losses.

c. Photographs are to be taken at fabrication locations away from Project site.

d. Substantial Completion of a major phase or component of the Work.

e. Extra record photographs at time of final acceptance.

013233 - 3 PHOTOGRAPHIC

PART 2 - PRODUCTS (Not Used)

END OF SECTION 013233

013233 - 4 PHOTOGRAPHIC

013300 - 1 SUBMITTAL PROCEDURES

SECTION 013300 - SUBMITTAL PROCEDURES

1.1 SUMMARY

A. Section Includes:

1. Submittal schedule requirements.

2. Administrative and procedural requirements for submittals.

B. Related Requirements:

1. Section 017700 "Closeout Procedures" for submitting closeout submittals and maintenance material submittals.

2. Section 017823 "Operation and Maintenance Data" for submitting operation and maintenance manuals.

1.2 DEFINITIONS

A. Action Submittals: Written and graphic information and physical samples that require Governments responsive action. Action submittals are those submittals indicated in individual Specification Sections as "action submittals."

B. Informational Submittals: Written and graphic information and physical samples that do not require Governments responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals."

1.3 SUBMITTAL SCHEDULE

A. Submittal Schedule: Submit, as an action submittal, a list of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates.

Include additional time required for making corrections or revisions to submittals noted by Government and additional time for handling and reviewing submittals required by those corrections.

1. Coordinate submittal schedule with list of subcontracts, the schedule of values, and Contractor's construction schedule.

2. Final Submittal Schedule: Submit concurrently with the first complete submittal of Contractor's construction schedule.

a. Submit revised submittal schedule as required to reflect changes in current status and timing for submittals.

013300 - 2 SUBMITTAL PROCEDURES

3. Format: Arrange the following information in a tabular format:

a. Scheduled date for first submittal.

b. Specification Section number and title.

c. Submittal Category: Action; informational.

d. Name of subcontractor.

e. Description of the Work covered.

f. Scheduled date for Government final release or approval.

1.4 SUBMITTAL FORMATS

A. Submittal Information: Include the following information in each submittal as applicable:

1. Project name.

2. Date.

3. Name of Contractor.

4. Name of firm or entity that prepared submittal.

5. Names of subcontractor, manufacturer, and supplier.

6. Unique submittal number, including revision identifier. Include Specification

Section number with sequential alphanumeric identifier and alphanumeric suffix for resubmittals.

7. Category and type of submittal.

8. Submittal purpose and description.

9. Number and title of Specification Section, with paragraph number and generic name for each of multiple items.

10. Drawing number and detail references, as appropriate.

11. Indication of full or partial submittal.

12. Location(s) where product is to be installed, as appropriate.

13. Other necessary identification.

14. Remarks.

15. Signature of transmitter.

B. Deviations and Additional Information: On each submittal, clearly indicate deviations from requirements in the Contract Documents, including minor variations and limitations; include relevant additional information and revisions, other than those requested by Government on previous submittals. Indicate by highlighting on each submittal or noting on attached separate sheet.

C. Electronic Submittals: Prepare submittals as PDF package, incorporating complete information into each PDF file. Name PDF file with submittal number.

1.5 SUBMITTAL PROCEDURES

A. Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification Sections.

013300 - 3 SUBMITTAL PROCEDURES

1. Email: Prepare submittals as PDF package and transmit to Contracting Officer's Representative by sending via email. Include PDF transmittal form. Include information in email subject line as requested by Contracting Officer's Representative.

a. Contracting Officer's Representative will return annotated file. Annotate and retain one copy of file as a digital Project Record Document file.

B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule.

3. Submit action submittals and informational submittals required by the same Specification Section as separate packages under separate transmittals.

C. Processing Time: Allow time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Contracting Officer's Representative receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.

1. Initial Review: Allow 15 days for initial review of each submittal.

2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Resubmittal Review: Allow 10 days for review of each resubmittal.

D. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.

1. Note date and content of previous submittal.

2. Note date and content of revision in label or title block, and clearly indicate extent of revision.

3. Resubmit submittals until they are marked with approval notation from action stamp.

E. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

F. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from action stamp.

013300 - 4 SUBMITTAL PROCEDURES

1.6 SUBMITTAL REQUIREMENTS

A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard published data are unsuitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's catalog cuts.

b. Manufacturer's product specifications.

c. Standard color charts.

d. Statement of compliance with specified referenced standards.

e. Testing by recognized testing agency.

f. Application of testing agency labels and seals.

g. Notation of coordination requirements.

h. Availability and delivery time information.

4. For equipment, include the following in addition to the above, as applicable:

a. Wiring diagrams that show factory-installed wiring.

b. Printed performance curves.

c. Operational range diagrams.

d. Clearances required to other construction, if not indicated on accompanying

Shop Drawings.

B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:

a. Identification of products.

b. Schedules.

c. Compliance with specified standards.

d. Notation of coordination requirements.

e. Notation of dimensions established by field measurement.

f. Relationship and attachment to adjoining construction clearly indicated.

g. Seal and signature of professional engineer if specified.

C. Test Reports:

1. Field Test Reports: Submit written reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.

013300 - 5 SUBMITTAL PROCEDURES

1.7 CONTRACTOR'S REVIEW

A. Action Submittals and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to Contracting Officer's Representative.

B. Contractor's Approval: Indicate Contractor's approval for each submittal with indication in web-based Project management software. Include name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

1. Contracting Officer's Representative will not review submittals received from Contractor that do not have Contractor's review and approval.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 013300

013300 - 6 SUBMITTAL PROCEDURES

013591 - 1 HISTORIC TREATMENT

SECTION 013591 - HISTORIC TREATMENT PROCEDURES

1.1 SUMMARY

A. Section includes general protection and treatment procedures for designated historic spaces, areas, rooms, and surfaces in Project.

1.2 DEFINITIONS

A. Consolidate: To strengthen loose or deteriorated materials in place.

B. Dismantle: To disassemble or detach a historic item from a surface, or a nonhistoric item from a historic surface, using gentle methods and equipment to prevent damage to historic items and surfaces; disposing of items unless indicated to be salvaged or reinstalled.

C. Historic: Spaces, areas, rooms, surfaces, materials, finishes, and overall appearance that are important to the successful preservation as determined by Contracting Officer's Representative.

D. Match: To blend with adjacent construction and manifest no apparent difference in material type, species, cut, form, detail, color, grain, texture, or finish as approved by Contracting Officer's Representative.

E. Refinish: To remove existing finishes to base material and apply new finish to match original, or as otherwise indicated.

F. Reinstall: To protect removed or dismantled item, repair and clean it as indicated for reuse, and reinstall it in original position, or where indicated.

G. Remove: To take down or detach a nonhistoric item located within a historic space, area, or room, using methods and equipment to prevent damage to historic items and surfaces; disposing of items unless indicated to be salvaged or reinstalled.

H. Repair: To correct damage and defects, retaining existing materials, features, and finishes while employing as little new material as possible. This includes patching, piecing-in, splicing, consolidating, or otherwise reinforcing or upgrading materials.

I. Replace: To remove, duplicate, and reinstall entire item with new material. The original item is the pattern for creating duplicates unless otherwise indicated.

J. Replicate: To reproduce in exact detail, materials, and finish unless otherwise indicated.

013591 - 2 HISTORIC TREATMENT

K. Reproduce: To fabricate a new item, accurate in detail to the original, and from either the same or a similar material as the original, unless otherwise indicated.

L. Restore: To consolidate, replicate, reproduce, repair, and refinish as required to achieve the indicated results.

M. Retain: To keep an element or detail secure and intact.

N. Reversible: New construction work, treatments, or processes that can be removed or undone in the future without damaging historic materials unless otherwise indicated.

O. Salvage: To protect removed or dismantled items and deliver them to Government ready for reuse.

P. Stabilize: To provide structural reinforcement of unsafe or deteriorated items while maintaining the essential form as it exists at present; also, to reestablish a weather-resistant enclosure.

Q. Strip: To remove existing finish down to base material unless otherwise indicated.

1.3 MATERIALS OWNERSHIP

A. Historic items, relics, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, antiques, and other items of interest or value to Government that may be encountered or uncovered during the Work, regardless of whether they were previously documented, remain Owner's property.

1. Coordinate with Government's archaeologist who will establish special procedures for dismantling and salvaging.

PART 2 - PRODUCTS - (Not Used)

PART 3 - EXECUTION

3.1 PROTECTION

A. Protect persons, motor vehicles, surrounding surfaces of building, building site, plants, and surrounding buildings from harm resulting from historic treatment procedures.

B. Temporary Protection of Historic Materials:

1. Protect existing historic materials with temporary protections and construction.

Do not remove existing materials unless otherwise indicated.

013591 - 3 HISTORIC TREATMENT

3.2 GENERAL HISTORIC TREATMENT

A. Have historic treatment work performed only by qualified historic treatment specialists.

B. Ensure that supervisory personnel are present when historic treatment work begins and during its progress.

C. Record existing work before each procedure (preconstruction), and record progress during the work. Use digital preconstruction documentation photographs. Comply with requirements in Section 013233 "Photographic Documentation."

END OF SECTION 013591

013591 - 4 HISTORIC TREATMENT

015000 - 1 TEMPORARY FACILITIES AND

CONTROLS

SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS

1.1 SUMMARY

A. Section includes requirements for temporary utilities, support facilities, and security and protection facilities.

B. Related Requirements:

1. Section 011000 "Summary of Work" for work restrictions and limitations on utility interruptions.

1.2 USE CHARGES

A. Installation, removal, and use charges for temporary facilities to be included in the Contract Sum unless otherwise indicated. Allow other entities engaged in the Project to use temporary services and facilities without cost, including, but not limited to, Government construction forces, testing agencies, and authorities having jurisdiction.

B. Water Service from Existing System: Water from Government existing water system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations.

Facilities are required to be cleaned and maintained by contractor to a condition acceptable to Contracting Officer's Representative. At Substantial Completion, restore the facilities to condition existing before initial use.

C. Sanitary Facilities: Use of on-site Government sanitary facilities (vault style toilet located near the Group Campground) will be permitted. Contractor is responsible for cleaning said toilet facility periodically and at completion of project.

D. Electric Power Service from Existing System: Electric power from Government existing system is available for use without metering and without payment of use charges.

Provide connections and extensions of services as required for construction operations. All wiring and equipment will be at contractor's expense.

E. Telephone: the contractor is responsible for providing telephone service deemed necessary for the duration of the construction.

F. Waste Disposal Facilities: Provide waste-collection containers in sizes adequate to handle waste from construction operations. Containerize and clearly label hazardous, dangerous, or unsanitary waste materials separately from other waste. Use of Government waste facilities is not permitted.

015000 - 2 TEMPORARY FACILITIES AND

1.3 INFORMATIONAL SUBMITTALS

A. Site Utilization Plan: Show temporary facilities, temporary utility lines and connections, staging areas, construction site entrances, vehicle circulation, and parking areas for construction personnel.

1.4 QUALITY ASSURANCE

A. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA 70.

PART 2 - PRODUCTS

2.1 TEMPORARY FACILITIES

A. Field Offices:

1. Prefabricated or mobile units with serviceable finishes, temperature controls, and foundations adequate for normal loading.

2.2 EQUIPMENT

A. Fire Extinguishers: Portable, UL rated; with class and extinguishing agent as required by locations and classes of fire exposures.

PART 3 - EXECUTION

3.1 INSTALLATION, GENERAL

A. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required by progress of the Work.

1. Locate facilities to limit site disturbance as specified in Section 011000 "Summary of Work."

B. Provide each facility ready for use when needed to avoid delay. Do not remove until facilities are no longer needed or are replaced by authorized use of completed permanent facilities.

3.2 TEMPORARY UTILITY INSTALLATION

A. General: Install temporary service or connect to existing service.

015000 - 3 TEMPORARY FACILITIES AND

1. Arrange with utility company, Government, and existing users for time when service can be interrupted, if necessary, to make connections for temporary services.

B. Sanitary Facilities: Provide wash facilities, safety shower and eyewash facilities, and drinking water for use of construction personnel. Comply with requirements of authorities having jurisdiction for type, number, location, operation, and maintenance of fixtures and facilities.

3.3 SUPPORT FACILITIES INSTALLATION

A. Traffic Controls: Comply with requirements of authorities having jurisdiction.

1. Protect existing site improvements to remain, including curbs, pavement, and utilities.

2. Maintain access for fire-fighting equipment and access to fire hydrants.

B. Parking: Use designated areas of existing parking areas for construction personnel.

C. Storage and Staging: Use designated areas of Project site for storage and staging needs.

3.4 SECURITY AND PROTECTION FACILITIES INSTALLATION

A. Protection of Existing Facilities: Protect existing vegetation, equipment, structures, utilities, and other improvements at Project site and on adjacent properties, except those indicated to be removed or altered. Repair damage to existing facilities.

B. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction as required to comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

C. Barricades, Warning Signs, and Lights: Comply with requirements of authorities having jurisdiction for erecting structurally adequate barricades, including warning signs and lighting.

3.5 OPERATION, TERMINATION, AND REMOVAL

A. Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and abuse, limit availability of temporary facilities to essential and intended uses.

B. Maintenance: Maintain facilities in good operating condition until removal.

C. Termination and Removal: Remove each temporary facility when need for its service has ended.

015000 - 4 TEMPORARY FACILITIES AND

017300 - 1 EXECUTION

SECTION 017300 - EXECUTION

1.1 SUMMARY

A. Section includes general administrative and procedural requirements governing execution of the Work, including, but not limited to, the following:

1. Installation.

2. Progress cleaning.

3. Starting and adjusting.

4. Protection of installed construction.

5. Correction of the Work.

B. Related Requirements:

1. Section 011000 "Summary of Work" for coordination of and limits on use of Project site.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.1 EXAMINATION

A. Existing Conditions: The existence and location of underground and other utilities and construction indicated as existing are not guaranteed. Before beginning sitework, investigate and verify the existence and location of underground utilities, mechanical and electrical systems, and other construction affecting the Work.

1. Before construction, verify the location and invert elevation at points of connection of sanitary sewer, storm sewer, gas service piping, and water-service piping; underground electrical services; and other utilities.

2. Furnish location data for work related to Project that must be performed by public utilities serving Project site.

B. Examination and Acceptance of Conditions: Before proceeding with each component of the Work, examine substrates, areas, and conditions, with Installer or Applicator present where indicated, for compliance with requirements for installation tolerances and other conditions affecting performance. Record observations.

1. Examine roughing-in for electrical systems to verify actual locations of connections before equipment and fixture installation.

017300 - 2 EXECUTION

C. Proceed with installation only after unsatisfactory conditions have been corrected.

Proceeding with the Work indicates acceptance of surfaces and conditions.

3.2 PREPARATION

A. Field Measurements: Take field measurements as required to fit the Work properly.

Recheck measurements before installing each product. Where portions of the Work are indicated to fit to other construction, verify dimensions of other construction by field measurements before fabrication. Coordinate fabrication schedule with construction progress to avoid delaying the Work.

B. Space Requirements: Verify space requirements and dimensions of items shown diagrammatically on Drawings.

C. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents, submit a request for information to Contracting Officer's Representative. Include a detailed description of problem encountered, together with recommendations for changing the Contract Documents.

3.3 INSTALLATION

A. Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.

1. Make vertical work plumb and make horizontal work level.

2. Where space is limited, install components to maximize space available for maintenance and ease of removal for replacement.

B. Comply with manufacturer's written instructions and recommendations for installing products in applications indicated.

C. Install products at the time and under conditions that will ensure the best possible results. Maintain conditions required for product performance until Substantial Completion.

D. Conduct construction operations, so no part of the Work is subjected to damaging operations or loading in excess of that expected during normal conditions of occupancy of type expected for Project.

E. Attachment: Provide blocking and attachment plates and anchors and fasteners of adequate size and number to securely anchor each component in place, accurately located and aligned with other portions of the Work. Where size and type of attachments are not indicated, verify size and type required for load conditions with manufacturer.

1. Mounting Heights: Where mounting heights are not indicated, mount components at heights directed by Contracting Officer's Representative.

2. Allow for building movement, including thermal expansion and contraction.

017300 - 3 EXECUTION

3. Coordinate installation of anchorages. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be embedded in concrete or masonry. Deliver such items to Project site in time for installation.

3.4 PROGRESS CLEANING

A. Clean Project site and work areas daily, including common areas. Enforce requirements strictly. Dispose of materials lawfully.

1. Comply with requirements in NFPA 241 for removal of combustible waste materials and debris.

2. Do not hold waste…