Attachment 0013 SOW FOR THE INERT MODELS 07-06-2022.pdf

PDF 781 KB Posted

Attached to
M772 & M776 Mechanical Time Super Quick (MTSQ) Fuzes
Solicitation number
W519TC-23-R-0030
Issued by

View the file

Other files

File Type Posted
Attachment 0015 LOT ACCEPTANCE SHIPPING DOCUMENTATION PROCESS 05-16-2023.pdf PDF
Solicitation W519TC-23-R-0030 Amendment 0001.pdf PDF
Attachment 0004 REDUCED LAT AND FAT TESTING 05-16-2023.docx DOCX document
Attachment 0002 GUIDANCE ON DOCUMENTATION OF CDRLS 01-02-2023.pdf PDF
Attachment 0003 CONFIGURATION CHANGE MANAGEMENT DOCUMENTATION 01-02-2023.rtf RTF text file
Attachment 0005 GFP LIST 11-22-2022.xlsx XLSX spreadsheet
Attachment 0006 OPSEC COVER SHEET 06-23-2022.pdf PDF
Attachment 0012 ALTERNATE SAMPLING PLAN 10-26-2022.pdf PDF
Attachment 0015 LOT ACCEPTANCE - SHIPPING DOCUMENTATION PROCESS 02-11-2021.pptx PPTX presentation
Attachment 0004 REDUCED LAT AND FAT TESTING 10-26-2022.docx DOCX document
Attachment 0009 MIL-STD-1916 DOD TEST METHOD STANDARD 04-01-1996.PDF PDF
Attachment 0008 AMMUNITION REQUIREMENTS FORM 11-22-2022.docx DOCX document
Exhibit A CONTRACT DATA REQUIREMENTS LIST 01-02-2023.pdf PDF
Attachment 0001 PRICE MATRIX 01-19-2023.xlsx XLSX spreadsheet
Attachment 0011 ASC FORM 715-7 COVER SHEET FOR HAZARDOUS MATERIAL 01-24-2023.docx DOCX document
Attachment 0014 COCO SECURITY SOW 01-24-2023.docx DOCX document
Solicitation W519TC-23-R-0030.pdf PDF
Attachment 0007 SOW FOR OPSEC CYBER SECURITY 06-23-2022.pdf PDF
Attachment 0010 DETAIL STATISTICAL PROCESS CONTROL REQUIREMENTS 10-26-2022.docx DOCX document
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CUI

Statement of Work

For the

Inert Models of the M772 & M776 MTSQ Timing Fuze

Prepared by:

CCDC AC Fuze Division

06 July 2022

7 /6 /2 0 2 2

X S hala P enev olpe

S igned by : P EN EV O L P E .S H AL A .M .1 2 3 9 7 1 9 9 2 5

CCDC Armaments Center

Electrical Engineer, Fuze Division, GS-12

Indirect Fires Fuzing Branch

973-724-1324

Shala.m.penevolpe.civ@army.mil

Controlled by: DEVCOM-AC

CUI Category: PROCURE

Distribution Statement: D

POC: Shala M. Penevolpe, FCDD-ACM-FF, Picatinny Arsenal, NJ

Attachment 0013 mailto:Shala.m.penevolpe.civ@army.mil

STATEMENT OF WORK

INERT M772/M776 MTSQ Fuze Models

1. OBJECTIVE

The objective of this Statement of Work (SOW) is to enable the U.S. Government to purchase INERT cutaway models and full-up INERT models in support of ongoing PM CAS contracts. Deliverables under the base contract will be for INERT Cutaway models and INERT models, part of CLINs 000X and 000X

2. BACKGROUND

The U.S. Government requires INERT models of the fuze to brief the fuze design to team members, program management, and the user community under the production base contract being awarded.

3. APPLICABLE DOCUMENTS

3.1 DRAWINGS

The MTSQ fuze models shall be fabricated in accordance with the following drawings:

12624567 Fuze, MTSQ, M772 Assembly

12361000 Fuze, MTSQ, M776

4. REQUIREMENTS

4.1 Inert Cutaway Models

4.1.1 The contractor shall fabricate and deliver to the Government inert cutaway models.

4.1.2 The inert cutaway model shall consist of a full-up assembled fuze with a 90-degree cross section of material removed to expose internal features and subassemblies. The cross section shall be oriented to minimize destruction of internal features. Unnecessary lubricants or adhesives shall be omitted.

Components which are difficult to install or cross section, such as O-rings, shall be omitted upon

Government approval. Explosives shall be replaced with inert, non-hazardous, compatible materials with an equivalent final form. Components or features which when present reveal sensitive data or permit reverse engineering, shall be altered or omitted to prevent disclosure of sensitive data; Government approval of the altered design is required. The model shall be engraved or have a non-removable permanent marking to identify the assembly as inert per Government policy. The model shall be delivered with a display stand fixture to securely hold and display the model. The model shall not be permanently attached to the fixture. The final design shall be compliant with the security classification guide and approved by the Government prior to fabrication.

4.1.3 The contractor shall modify drawings as necessary for fabrication of the cutaway inert models. The contractor shall deliver the modified drawings to the Government for review and approval before work is started on the sectioned models.

4.2 Inert Models

4.2.1 The contractor shall fabricate and deliver to the Government inert models.

4.2.2 The inert model shall consist of the functional full-up assembled fuze with compatible, mass equivalent, inert material used in place of explosive materials. Components or features which when present reveal sensitive data or permit reverse engineering, shall be altered or omitted to prevent disclosure of sensitive data; Government approval of the altered design is required. The model shall be engraved or have a non-removable permanent marking to identify the assembly as inert per Government policy. The final design shall be compliant with the security classification guide and approved by the

Government prior to fabrication. The models shall be delivered in standard fuze packaging in accordance with the drawing.

4.2.3 The contractor shall modify drawings as necessary for fabrication of the inert models. The contractor shall deliver the modified drawings to the Government for review and approval before work is started.

5. GFM

GFM will not be provided during the performance of this inert model SOW

6. SHIPPING INSTRUCTIONS

When quantities of each model are requested, items shall be shipped to the address specified on the associated modification.

File details come from the government source that posted it. Updated .