Attachment 0011 - PWS 11 RFAAP Facility Ops and Production Reporting_12_2025_Draft.docx

DOCX document 47 KB Posted

Attached to
Radford Army Ammunition Plant - DRAFT Solicitation #2
Solicitation number
W519TC-26-R-00003
Issued by

About this file

This is a Performance Work Statement (PWS 11) for Facility Operations and Production Reporting at Radford Army Ammunition Plant (RFAAP). The contractor is required to submit comprehensive reporting on facility operations, production activities, and modernization efforts across the entire installation within 120 calendar days of contract award, with reporting formats to be collaboratively developed and approved by the Procuring Contracting Officer. The facility operations reporting requirements include annual incurred cost reports itemized by PWS and Department of Defense production item with labor, materials, ODCs, subcontracts, and indirect cost breakdowns; annual utility consumption and cost reports by month for all metered facilities; annual maintenance cost reports by operational capability broken down by maintenance type; and monthly operational availability reports for all production areas. The contractor must utilize Enterprise Resource Planning (ERP) systems for data population rather than manual entry into Microsoft Excel templates.

Production status reporting requires daily production status reports to local Army staff and Project Lead Joint Services by 1000 each morning detailing planned versus actual production with reasons for any shortfalls; weekly production reports by Tuesday 1000 with part numbers and production area groupings; monthly projected annual goals with descriptions of deviations greater than ±5%; and weekly production and delivery schedules for all orders including government, third-party government, third-party defense, and commercial contracts. Additionally, the contractor must submit annual project status reports for funded activities, establish and track a minimum of three Key Performance Indicators (KPIs) measuring performance and efficiency with monthly submissions and adjustment strategies when trending negative, and provide detailed KPI calculation methods and improvement targets subject to government approval.

View the file

Other files

File Type Posted
RFAAP Draft RFP2 QandA - W519TC26R0003 04Jun2026.pdf PDF
Attachment 0001 - PWS 01 RFAAP Environmental_Draft_02_2026.docx DOCX document
Attachment 0006 - PWS 06 RFAAP Security and Antiterrorism_11_2025_Draft.docx DOCX document
Attachment 0002 - PWS 02 Facility Planning_Draft_02_2026.docx DOCX document
Attachment 0018 - PWS 18 - GROUND WATER MONITORING AND INSTALLATION RESTORATION PROGRAM SUPPORT_12_2025_Draft.docx DOCX document
Exhibit C - PWS 7 Att B JMC BUILDER Sustainment Guide.pdf PDF
Request for Information - Transfer of Spare Parts.docx DOCX document
Attachment 0007 - PWS 07 RFAAP Maintenance_12_2025_Draft.docx DOCX document
Attachment 0002 - PWS 02 Facility Planning_Draft_02_2026.docx DOCX document
Attachment 0028 - COCO SECURITY STATEMENT OF WORK 2025.docx DOCX document
W519TC-26-R-0003.pdf PDF
Exhibit B - PWS 7 - RFAAP Maintenance FIandE -- Clean DEC 2024 V1.docx DOCX document
Attachment 0003 - PWS 03 Fire Protection and ES_11_2025_Draft with ET rev 12_2025.docx DOCX document
Attachment 0012 - PWS 12 - ARMS_12_2025_Draft.docx DOCX document
Attachment 0005 - PWS 05 Occupational Health_11_2025_Draft.docx DOCX document
Attachment 0001 - PWS 01 RFAAP Environmental_Draft_02_2026.docx DOCX document
Attachment 0013 - PWS 13 RFAAP Technology and Cyber Security_Draft_02_2026.docx DOCX document
Attachment 0017 - PWS 17 RFAAP Transition Out_Draft_02_2026.docx DOCX document
Attachment 0015 - PWS 15 - ALTESS SUPPORT SERVICES_12_2025_Draft.docx DOCX document
Exhibit A - CDRLs.pdf PDF
Attachment 0031 - Final FY25 Ammo Plant Mod.pdf PDF
Attachment 0025 - CDRL Instructions.pdf PDF
Attachment 0022 - SAMPLE OPSEC ACQUISITIONS PLAN.pdf PDF
Attachment 0030 - Non-Disclosure Agreement NEPSCO.docx DOCX document
Attachment 0029 - Non-Disclosure Agreement Azimuth.docx DOCX document
Attachment 0036 - Past Performance Questionnaire.docx DOCX document
Attachment 0021 - OPSEC SOW.docx DOCX document
Attachment 0004 - PWS 04 Property PWS_11_2025_Draft.docx DOCX document
Attachment 0006 - PWS 06 RFAAP Security and Antiterrorism_11_2025_Draft.docx DOCX document
Attachment 0009 - PWS 09 - Safety_Draft_02_2026.docx DOCX document
Attachment 0010 - PWS 10 RFAAP Energy and Utilities_Draft_02_2026.docx DOCX document
Attachment 0023 - DD254 Contract Security Classification Specification.pdf PDF
Attachment 0026 - Hazardous Material Classification Specification.xlsx XLSX spreadsheet
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RADFORD ARMY AMMUNITION PLANT

PERFORMANCE WORK STATEMENT (PWS)

PWS 11: FACILITY OPERATIONS AND PRODUCTION REPORTING

NOVEMBER 2025

1. GENERAL INFORMATION

1.1. INTRODUCTION

1.1.1. The objective of this PWS is to identify contractor reporting requirements for facility operations, production activities, and modernization efforts.

1.2. BACKGROUND

1.2.1. The contractor shall submit the herein required facility operations costs, production status reports, and modernization costs for efforts executed in accordance with the RFAAP Facility Use and any companion contracts. The contractor shall utilize the CDRLs for identification of the required elements, format, frequency, and distribution for each report.

1.3. SCOPE

1.3.1. Reports should include facilities within the entire boundary of the installation.

1.4. APPLICABLE DOCUMENTS OR CITATIONS

1.4.1. PWS 7 governs the maintenance of facilities at RFAAP.

1.4.2. PWS 10 governs the operation of utility infrastructure and energy management at RFAAP

1.4.3. Companion contracts.

2. WORK REQUIREMENTS

2.1. TECHNICAL REQUIREMENTS

2.1.1. The contractor shall have 120 calendar days from contract award to work with the Government on the format for all reports. The report format (pivot tables, dashboards, etc.) shall be approved by the Procuring Contracting Officer (PCO). The contractor shall host working meetings until this has been achieved. The contractor shall provide report examples during each working meeting. The Government will work with the contractor to refine and finalize report formatting and work through any issues that occur.

2.2. FACILITY OPERATIONS REPORTING:

2.2.1. The contractor shall prepare and submit annual reports for actual costs incurred for all facility operations and production activities. The cost reports shall be itemized for each PWS and Department of Defense production item, and include a breakdown by labor, materials, other direct cost (ODCs), subcontracts, etc. The breakdown should also include all actual indirect rate burdens such as, but not limited to, fringe, overhead, and G&A. The actual running rate for indirect cost should be displayed within the report (e.g., G&A 9.5%, fringe 40%, etc.). The report shall also include total direct hours, and all indirect hours associated with managing PWS. For PWS requirements, the incurred cost report shall also reference the work breakdown structure for each cost incurred and respective cost center. The report shall be in Microsoft Excel format. The raw data shall be in proper tabular format within the Microsoft Excel document. The raw data shall be populated by the Contractor's Enterprise Resource Planning (ERP) system and not be populated by manual entry into the spreadsheet. (CDRL A11-001)

2.2.2. The contractor shall provide an annual report for utility consumption and cost for all metered facilities. The annual report should have utility consumption by month. The contractor shall ensure that all metering data is operational, calibrated, and accurate. If the data frequency is available, reports should show daily usage rates with a roll-up for the entire month. All metered utilities will be included (natural gas, steam, water, electricity, compressed air, wastewater, etc). If additional meters come online, they will be included. Additional metering efforts will be performed through individual modernization projects, not this PWS. Report should be clearly labeled in tabular Microsoft Excel format. (CDRL A11-002)

2.2.3. The contractor shall provide an annual report for maintenance costs by operational capability to include but not limited to Legacy Nitrocellulose, New Nitrocellulose, Nitroglycerin, Greenlines, Finishing Area, Rolled Powder, Rocket Manufacturing, Acids, Steam Generation & Distribution, Water Intake, Water Filtration & Distribution, Industrial Wastewater Treatment, Compressed Air, etc. that is broken down by maintenance type (preventative, corrective, etc.), labor, materials, subcontracts, overhead, etc. Report should be clearly labeled in tabular Microsoft Excel format. (A11-003)

2.2.4. The Contractor shall provide an annual report that indicates Operational Availability (OA) for all production areas. The annual report should have OA by month. This report should be broken down by process equipment and organized by manufacturing area. It shall also indicate the portion of OA that is attributed to maintenance and all other downtime indicators (e.g., staffing issues, material planning issues, etc.) to formulate the total OA for each manufacturing area. The major production areas are defined as, but not limited to, Nitrocellulose, Greenlines (SB, MB, and High Energy Line broken out separately), Finishing Area, Rolled Powder, Rocket Area, Nitroglycerine, and Acid Area. It should also include the Incinerator, Contaminated Waste Processor, Steam Turbines, and Water Intake Pumps. The data should include all raw data relevant for the OA calculations within the report. Report should be clearly labeled in tabular Microsoft Excel format. (A11-004)

2.3. PRODUCTION STATUS REPORTS:

2.3.1. The contractor shall provide a daily production status report to the local Army staff and Project Lead Joint Services by 1000 that indicates the status of each production facility including but not limited to Acid, Legacy NC, New NC, NG, Rolled Powder, Rocket, Greenlines, Finishing Area. The report shall include planned production for the previous day, actual production for the previous day, production goal for the week, actual production for the week, and reasons why the production goal was not reached each day (e.g., maintenance issues, staffing downtime, weather, etc.). (A11-005)

2.3.2. The contractor shall provide a weekly production report to the local Army staff and Project Lead Joint Services by each Tuesday by 1000 for each type of product produced in each production line from the previous week. The report shall be in Microsoft Excel format. The raw data shall be in proper tabular format within the Microsoft Excel document. The report shall include the part number of the product, description and be grouped by production area. The raw data shall be populated by the contractor's production accounting system and not be populated by manual entry into the spreadsheet. The Contractor should ensure that data reported is accurate. (CDRL A11-006)

2.3.3. The contractor shall provide a projected annual goal for each production area and product type each calendar year and provide updated projections monthly. Significant deviations from the projected monthly burn rate greater than +/- 5% change should include a description of the cause and intended corrective action to return to projection. (CDRL A11-007)

2.3.4. The contractor shall provide a weekly production and delivery schedule to the local Army staff and Project Lead Joint Services by each Tuesday by 1000 to include all orders on contract (including direct Government, third-party Government, third-party defense, and commercial orders) with a request for facility use reference number, purchase order award date, purchase order number, customer, delivery location, CLIN number, contractual delivery date, actual delivery date, total contractual quantities, actual quantity delivered, and price. The report should be in tabular Microsoft excel format. The raw data shall be populated by the contractor's ERP system and not be populated by manual entry into the spreadsheet. (A11-008)

2.3.4.1. The contractor shall provide a monthly report in tabular Microsoft Excel format (A11-009):

2.3.4.1.1. The total number of pounds/units of each item produced for all direct Government, third-party Government, third-party defense, and commercial contracts. This shall include the part number, description and type (e.g., single base, multi-base, rolled powder, nitrocellulose, etc.).

2.3.4.1.2. Total cost to produce all production items for all direct Government, third-party Government, third-party defense, and commercial contracts. This should be the actual production cost pulled from the Contractor’s ERP system for the reporting period. It shall include the part number, description and include all cost elements broken out (direct labor, direct material, direct ODC, fringe, OH, G&A, etc.).

2.4. PROJECT STATUS REPORTS:

2.4.1. The contractor shall prepare and submit annual reports for actual costs incurred for all funded project activities. The cost reports shall be itemized for each contract, task order, and/or PWS; and include a breakdown by labor, materials, ODCs, subcontracts, etc. The breakdown should also include all actual indirect rate burdens such as, but not limited to, fringe, overhead, and G&A. The actual running rate for indirect cost should be displayed within the report (e.g., G&A 9.5%, fringe 40%, etc.). The report shall also include total direct hours, and all indirect hours associated with managing the project. For each CLIN requirement, the incurred cost report shall also reference the work breakdown structure for each cost incurred and respective cost center. The report shall be in Microsoft Excel format. The raw data shall be in proper tabular format within the Microsoft Excel document. The raw data shall be populated by the Contractor's ERP system and not be populated by manual entry into the spreadsheet. (CDRL A11-010)

2.4.2. KPI TRACKING

2.4.2.1. In addition to any KPIs specified in this PWS, the Contractor shall identify a minimum of three (3) KPIs that measure performance, effectiveness, timeliness, and/or efficiency of Facilities Operations and Production Reporting efforts at RFAAP. These additional KPIs shall be included in a PWS 11 KPI report (CDRL A11-011). The initial submission shall be submitted to the Government for approval 30 calendar days after transitioning as the Operating Contractor and monthly thereafter.

2.4.2.2. The Contractor shall define the calculation method for each KPI and any sub-KPIs in the first submission of the PWS 11 KPI report ACA for Government approval.

2.4.2.3. The PWS 11 KPI Report shall provide targets for improvement for each KPI, with justification as to why the target was determined. Targets may be based on industry standards or baseline data acquired in the first quarter of performance tracking. Targets may be adjusted on an annual basis or sooner, if necessary, with Government approval.

2.4.2.4. When KPIs are trending negative or consistently below target (for at least three consecutive months), the Contractor shall provide a plan or strategy adjustment to work back towards the target. The plan and/or strategy shall include details on actions to be performed, timeline for improvement and personnel responsible to achieve the target.

2.4.2.5. While the government reserves the right to assess contractor compliance with specific requirements of this PWS, the primary measure of the contractor’s success in performing the PWS will be determined by KPI goal attainment.