Attachment 001 Performance Work Statement and QASP.pdf

PDF 499 KB Posted

Attached to
Supply and Installation of Livestock Tire Tanks - El Reno OK
Solicitation number
1232SA25Q0218
Issued by

About this file

This is a Performance Work Statement (PWS) and Quality Assurance Surveillance Plan (QASP) for the supply and installation of livestock tire water tanks at USDA's OCPARC facility in El Reno, Oklahoma. The contractor must supply and install four recycled large construction vehicle tires (approximately 7 feet in diameter and 2 feet tall) with one sidewall removed to serve as water tanks, along with four Gallagher bottom-type float valves and various 1-inch PEX fittings. The government will provide 2,500 feet of 1-inch blue poly water line.

The period of performance is 30 days from Notice to Proceed, with 10 days allowed after award for submittal requirements. The contractor must provide proof of insurance within 5 calendar days of award per FAR 52.228-5 before receiving Notice to Proceed. All contractor personnel must be escorted by USDA personnel while on site at 7207 W. Cheyenne St., El Reno OK 73036. Installation locations are specified in the included site map appendix, and the contractor must install all necessary valves and connection fittings for the water system. The QASP requires 100% completion of all requirements within the specified timeframe.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Work Statement and QASP Supply and Install Livestock Tire Tanks

USDA El Reno OK

GENERAL INFORMATION

1. Scope of Work:

OCPARC in El Reno OK requires supply and installation of four (4) Livestock Tire Water Tanks. These tanks are recycled large construction type vehicle tires (approx. 7’ in diameter and at least 2’ tall) with one side wall cut off.

2. Site Details:

2.1. Location of work: USDA ARS OCPARC – El Reno, 7207 W. Cheyenne St., El Reno OK 73036

2.2. Period of Performance: 30 days from Notice to Proceed. 10 days after receipt of award will be allowed for single submittal requirement.

CONTRACTOR REQUIREMENTS

3. Technical Requirements/Tasks

3.1. Complete submittal. If submittal is not completed Notice to Proceed will not be issued.

Submittal Contract Reference Delivery

Format Due by

Proof of Insurance Clause at FAR 52.228-5, Insurance - Work on a Government Installation and section entitled Insurance Under Fixed-Price Contracts.

PDF to COR Within 5 calendar days of award.

3.2. Upon Notice to Proceed, Contractor shall schedule installation with the COR.

3.3. The Contractor shall supply:

3.3.1. Four (4) each “Tire Tanks” approximately 7 feet in diameter and approximately 2 feet tall with one side wall cut off. See Appendix A below for example.

3.3.2. 4 “Gallagher” bottom type float valves

3.3.3. Various 1-inch Pex fittings

3.4. The Government will supply 2500 feet 1” blue poly water line

3.5. The Contractor shall install Tire Tanks to locations specified on Appendix B Site Map, see below.

3.6. The Contractor shall install all necessary valves and connection fittings for 1 in. poly line, valves, fittings, and floats.

4. Security Requirements: All contractor personnel shall always be in the presence of a USDA escort while on location.

5. Performance Requirement Measures

5.1. The Government shall establish a Quality Assurance Surveillance Plan (QASP) as a means of evaluating whether the Contractor is meeting the performance standards/quality levels identified in the PWS to ensure that the government pays only for the level of services received.

5.2. See QASP table below:

Task Standard Acceptable Quality

Level (AQL) Completion of all requirements/tasks as described in Section 3 and 4

Task completed within the period of performance stated in Section

2.2

100%

6. Appendices:

APPENDIX A

APPENDIX B

SITE MAP

SUBJECT AREA:

File details come from the government source that posted it. Updated .