Text version

MAINTENANCE ENGINEERING ORDER

(AMCOM Reg. 750-2)

MEO NO.

DATE PAGE 1 of

TITLE Tolerances Unless otherwise noted, dimensions are in inches and tolerances are:

Fractional ………………… ± 1/32 Decimal ………………... ± 0.010 Angular ………………… ± ½°

APPLICABILITY CSI Critical Characteristic Affected?

Impact Statement Attached?

REFERENCES FOR RDECOM USE ONLY

DOCUMENT(S) AFFECTED

PURPOSE OR PROBLEM

PROJECT ENGINEER ENGINEERING REVIEW ENGINEERING RELEASE

MED FORM 15-DEC-09 1401-R-E

B 1222

Overhaul Inspection Procedure clarification for Piston Feedback Ring, P/N 70410-02506-101.

INTERIM USE OF THIS MEO IS AUTHORIZED

UNTIL AFFECTED DOCUMENT IS UPDATED.

NO

YES

UH60 DAA

DMWR 1-1560-290, dated 23 JULY 2010 MEC B160149

DOCUMENT CHANGE IS REQUIRED Verification: Hands-On Table-Top None

There is a measurement shown in OIP #12 that is not designated by a reference letter. This MEO will correct that.

LUU.DINH.Q

.1232215859

Digitally signed by

LUU.DINH.Q.1232215859

DN: c=US, o=U.S. Government, ou=DoD, ou=PKI, ou=USA, cn=LUU.DINH.Q.1232215859 Date: 2013.05.13 08:11:17 -05'00'

GONZALEZ.JAC

OB.A.145582119

Digitally signed by

GONZALEZ.JACOB.A.1455821190

DN: c=US, o=U.S. Government, ou=DoD, ou=PKI, ou=CONTRACTOR, cn=GONZALEZ.JACOB.A.1455821190 Date: 2013.05.10 13:30:45 -05'00'

Jacob Gonzalez

HORN.REINHOL

D.J.1087783495

Digitally signed by

HORN.REINHOLD.J.1087783495

DN: c=US, o=U.S. Government, ou=DoD, ou=PKI, ou=USA, cn=HORN.REINHOLD.J.1087783495 Date: 2013.05.13 08:14:38 -05'00'

Dinh Luu Ron Horn PUBLICATION CHANGE REQUEST: REQUEST THAT THE FOLLOWING DATA BE INCLUDED IN THE NEXT

CHANGE OR REVISION TO THE PUBLICATION IDENTIFIED ABOVE.

WP NO. PAGE

NO.

PARA-

GRAPH

FIGURE/

TABLE

NO.

CHANGES

(EXACT WORDING OF CHANGES MUST BE GIVEN)

3-26 OIP #12 ADD the following to Overhaul Inspection Procedure #12 (for P/N 70410-02506-101):

NO.: 6

REF LTR: D

CHARACTERISTIC: Width INSP METHOD: Measure REQUISITE: Must be 0.015 to 0.020

ADD the letter "D" to the diagram per page 2 of this MEO:

Formatted Cont. Sheet

May 17 2013

MAINTENANCE ENGINEERING ORDER

(AMCOM Reg. 750-2) Continuation Sheet

MEO NO.

PAGE of

MED FORM 15-DEC-09 1401-R-E

Click to insert figure

B 1222

Formatted Cont. Sheet

Airworthiness/Readiness Impact – Implement as soon as possible

B 1222 DMWR 1-1560-290, dated 23 JULY 2010 UH60

NO

Clarifies an OIP.

Jacob Gonzalez, 361-961-4422, jacob.a.gonzalez42.ctr@mail.mil.

GONZALEZ.

JACOB.A.14

55821190

Digitally signed by

GONZALEZ.JACOB.A.1455821190

DN: c=US, o=U.S. Government, ou=DoD, ou=PKI, ou=CONTRACTOR, cn=GONZALEZ.JACOB.A.14558211 Date: 2013.05.10 13:30:23 -05'00'

Jacob Gonzalez