Attachment 0003 - S280C Technical PUBS SOW.pdf

PDF 228 KB Posted

Attached to
Solicitation_S-280C/G Vehicle Mounted Shelter
Solicitation number
W912CH-26-R-A096
Issued by

About this file

This is a Statement of Work (SOW) for development and production of equipment publications for the S-280C Shelter Technical Manual (TM 10-5411-207-13&P), dated December 15, 2018.

The contractor shall develop and produce an Operator Manual for the S-280C Shelter, converting the TM number from 13&P to 12&P format in accordance with MIL-STD-40051-2E. The contractor must also submit a Validation Plan and Validation Report. All documents shall comply with applicable military standards, regulations, and the attached TM Content Selection Matrix. The manual must include all procedures necessary to operate and maintain the equipment, including PMCS, troubleshooting, and maintenance procedures, with full illustrations, references, and a working table of contents. The contractor is responsible for conducting hands-on validation of all procedural tasks, with Government observers participating. The contract requires four submission phases: Initial, Second, Third, and Final Reproducible Copy (FRC), each consisting of two hard copies, one compiled PDF file, XML source files with embedded graphics, individual graphics files in 300 DPI .EPS or .TIFF format, and a graphics worksheet. All graphics must follow specific naming conventions, sizing limitations, and quality standards. The Validation Plan must identify validation location, dates, subject matter experts, a Fault Insertion List with methods and symptoms, task schedules, and tools required. The Validation Report must document the validating entity, dates, validation methods, changes identified, and signed certification that validation occurred per the approved plan. All submissions must conform to MIL-STD-40051-2E and will be rejected if they contain out-of-sequence or prohibited content items. The Government will not accept email submissions and will provide distribution statements and warning icons at the Logistics Guidance Conference.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

As of 15 December 2018 1 Technical Publications

STATEMENT OF WORK (SOW)

FOR

DEVELOPMENT AND PRODUCTION

OF EQUIPMENT PUBLICATIONS

FOR

S-280C SHELTER

TECHNICAL MANUAL

TM 10-5411-207-13&P

1. SCOPE. The Contractor shall develop and produce an Operator Manual for the S-280C Shelter (TM 10- 5411-207-13&P) (CDRL A012). The contractor will convert the TM number from a 13&P to a 12&P in accordance with MIL-STD-40051-2E. The Contractor shall also submit a Validation Plan and a Validation Report for the Operator Manual. The stated documents shall be developed and produced in accordance with this Statement of Work (SOW), applicable military standards (MIL-STDs) and regulations, and the attached TM Content Selection Matrix (Attachment 1, Content Selection Matrix). The Contractor shall reference other Army Technical Manuals as appropriate throughout the technical manual submissions in accordance with MIL-STD guidance.

CDRL Authority Title SOW

Para.

A012 MIL-STD-40051-2E,

including all changes

Operator Manual for the S-280C Shelter TM 10-5411- 207-13&P

4.1

A013 DI-CMAN-80792A

DI-MISC-80711A

Validation Plan and Validation Report for Operator Manual for the S-280C Shelter

4.2

2. APPLICABLE DOCUMENTS (TM).

Document ID Title

AMC PAM 25-31 Preparation of Plans for Technical Publications Verification http://www.apd.army.mil/ProductMap.asp Click DA Pamphlets and then, click 25 Information Management.

AR 25-30 The Army Publishing Program http://www.apd.army.mil/ProductMap.asp Click Army Regulations and then, click 25 Information Management.

DA PAM 25-40 Army Publishing: Action Officers Guide http://www.apd.army.mil/ProductMap.asp Click Army Regulations and then, click 25 Information Management.

http://www.apd.army.mil/ProductMap.asp http://www.apd.army.mil/ProductMap.asp http://www.apd.army.mil/ProductMap.asp

As of 15 December 2018 2 Technical Publications

Document ID Title

DI-CMAN-80792A Validation Report http://quicksearch.dla.mil/

MIL-STD-40051-2E,

including all changes

Department of Defense Standard Practice, Preparation of Digital Technical Information for Page-Based Technical Manuals https://www.logsa.army.mil/mil40051/menu.cfm

DI-MISC-80711A Scientific and Technical Reports http://quicksearch.dla.mil/

DOD Directive 5230.24 Distribution Statements on Technical Documents, 23 August 2012 http://www.dtic.mil/whs/directives/corres/pdf/523024p.pdf

DOD FAR Supplement, paragraph 252.246-7001

MIL-HDBK-1222F

(For Guidance Only)

MIL-HDBK-2361C

(For Guidance Only)

Warranty of Data http://www.acq.osd.mil/dpap/dars/dfars/index.htm

Department of Defense Handbook, Guide to the General Style and Format of U.S. Army Work Package Technical Manuals, 30 November 2012.

http://quicksearch.dla.mil/

Army Digital Publications Development Implementation Guide, 15 January 2012.

http://quicksearch.dla.mil/

The following items will provided by AMSTA-LCS-EB (TACOM ILSC) at the Logistics Guidance Conference/Start of Work Meeting:

Warning Icons https://www.logsa.army.mil/web2/resources/documents/tmss/ICONAP.doc

XML DTD, Revision 5.0 or later https://www.logsa.army.mil/mil40051/menu.cfm

Extensible Markup Language (XML) stylesheet https://www.logsa.army.mil/mil40051/menu.cfm

Distribution Statement Distribution Statement C, “Distribution authorized to U.S. Government Agencies and their contractors” is specified for this publication. The Distribution Statement is to be placed as directed by MIL-STD 40051-2D.

http://quicksearch.dla.mil/ https://www.logsa.army.mil/mil40051/menu.cfm http://quicksearch.dla.mil/ http://www.dtic.mil/whs/directives/corres/pdf/523024p.pdf http://www.acq.osd.mil/dpap/dars/dfars/index.htm http://quicksearch.dla.mil/ http://quicksearch.dla.mil/ https://www.logsa.army.mil/web2/resources/documents/tmss/ICONAP.doc

As of 15 December 2018 3 Technical Publications

3. PUBLICATION REQUIREMENTS. The Contractor shall produce an Operator Manual for the S-280C Shelter (TM 10-5411-207-13&P) in accordance with this SOW and the appropriate TM Content Selection Matrix (Attachment 1) in accordance with this SOW. Development of the TM will be supported by a Contractor-managed Validation effort. The Contractor shall develop a Validation Plan and Validation Report for the Operator Manual in accordance with this SOW and CDRLs A013 and A014.

3.1. Technical Manual. The Contractor shall produce an Initial, Second, Third and Final Reproducible Copy

(FRC) Submission of TM 10-5411-207-13&P. Content shall include, as required, and as applicable, all procedures necessary to operate and maintain the LMS, to include PMCS, Troubleshooting, and maintenance procedures. All submissions must conform to format and content requirements outlined in the applicable military standards and specifications detailed in paragraph 2 and requirements detailed in this SOW, and must be fully illustrated, referenced, and have a working table of contents.

3.2. TM Content Selection Matrix Compliance. The TM Content Selection Matrix from MIL-STD-40051-2E, (CDRL A012 - Attachment 1, Content Selection Matrix), shall be used to organize and develop technical manual content.

a) All items marked “R” in the matrix are required to support the equipment and shall be included in the order established in the matrix.

b) All shaded items shall be included as required to support the equipment. If shaded items are included, they shall be provided in the order established in the matrix.

c) All items marked “P” in the attached matrix are prohibited and shall not be included in the manual.

Note: Submissions with out-of-sequence or prohibited content items will be rejected.

3.3. Maintenance Allocation Chart (MAC). The Government will provide a Maintenance Allocation Chart

(MAC) for use in structuring content within the Operator Manual. Inclusion of the MAC in the Operator Manual is prohibited.

3.4. Illustrations. All technical manual submissions shall be fully illustrated IAW this SOW and MIL-STD

40051-2C. Digital photography, computer graphics, and line art are acceptable illustration media to support procedural and descriptive text.

3.4.1. Photographic Support. The Contractor shall use photographs as required by the Government to ensure text is sufficiently supported with accurate and clear illustration. In producing the TM as outlined in this SOW, the Contractor shall ensure that personnel in photographs, when visible, will be attired in proper and current U.S. Army work/utility uniform. All personnel, when photographed, will be wearing all safety equipment necessary to perform the procedure being illustrated, and will be photographed complying with all safety requirements as specified in the procedural text; to comply with this requirement, photographed personnel may not be depicted wearing watches, rings, or any other visible jewelry.

3.4.2. Graphics Worksheet. The Contractor will deliver a graphics worksheet in electronic format (MS-Word or equivalent format) with each submission. This worksheet sequentially lists all graphics used in the technical manual and, as a minimum, will list in tabular format, the following information: WP identification number (see 4.8.9.1. in MIL-STD-40051-2E), WP sequence number (see 4.8.9.2. in MIL-

As of 15 December 2018 4 Technical Publications

STD-40051-2E), Figure Number, Figure Title, Unique Illustration Number (see paragraph 7.6 in this SOW), Width in inches (reprowid), Height in inches (reprodep).

4. DELIVERY REQUIREMENTS.

4.1. Technical Manual Submissions.

4.1.1. Initial Submission TM. The Initial Submission of the Operator Manual for the S-280C Shelter (TM 10-5411-207-13&P), CDRL A012, will consist of: (1) Two hard copy TMs for distribution,

(2) One compiled digital PDF file, (3) the XML source file with all of the graphics embedded, (4) All source graphics files developed and delivered separately (individually) in 300 DPI .EPS or .TIFF format, and (5) a Graphics worksheet (MS Word or equivalent) as determined in the SOW.

The Initial Submission of the Operator Manual, for the S-280 (10-5411-207-13&P) will not be accepted unless it is accompanied by the Validation Plan (CDRL A013)

4.1.2. Second Submission TM. The Second Submission of the Operator Manual, for the S-280 (TM 10-5411-207-13&P), CDRL A012, shall include resolution of all comments and recommendations made as a result of the Contractor Validation, Government review, evaluation of Product Support Assessments, and any changes made as a result of the provisioning process. The Second Submission will consist of: (1) Two hard copy TMs for distribution, (2) One compiled digital PDF file, (3) the XML source file with all of the graphics embedded, (4) All source graphics files developed and delivered separately (individually) in 300 DPI .EPS or .TIFF format, and (5) a Graphics worksheet (MS Word or equivalent) as determined in the SOW. This document will support the Government managed Logistics Demonstration (LD).

4.1.3. Third Submission TM. The Third Submission of the Operator Manual, for the S-280 (10-5411- 207-13&P), CDRL A012, shall include final resolution of all comments, recommendations, and direction made as a result of the LD conference and the master markup documenting that event.

The Third Submission will consist of: (1) Two hard copy TMs for distribution, (2) One compiled digital PDF file, (3) the XML source file with all of the graphics embedded, (4) All source graphics files developed and delivered individually in 300 DPI .EPS or .TIFF format, and (5) a Graphics worksheet (MS Word or equivalent) as determined in the Statement of Work (SOW). This document will support the Government-managed TM Verification Conference.

4.1.4. Final Reproducible Copy (FRC). The FRC Submission of the Operator Manual, for the S-280C Shelter (10-5411-207-13&P), CDRL A012, shall include final resolution of all comments and recommendations made as a result of the Verification Conference and the master markup documenting that event. The FRC deliverables will consist of: (1) Two hard copy TMs for distribution, (2) One compiled digital PDF file, (3) The XML source file with graphics embedded,

(4) All source graphics files provided separately (individually) in 300 DPI .EPS or .TIFF format, and (5) a Graphics worksheet (MS Word or equivalent) as determined in this SOW.

4.2. Validation Submissions.

4.2.1. Validation Plan. The Contractor will develop and submit a Validation plan for Government

As of 15 December 2018 5 Technical Publications review and approval for the TM (10-5411-207-13&P) for the LMS IAW CDRL A013. The Validation Plan shall reflect compatibility with the overall maintenance and support plan, outline the Contractor’s recommended validation procedure, and indicate the scope of the validation effort.

All procedural tasks included in the TM must be validated hands-on; that is, actually performed as written. Intention to provide validation by analysis or otherwise simulate or desktop validate any procedures will be sufficient cause to reject the Validation Plan submission. Specific questions about the validation plan may be addressed at the Logistics Guidance conference. Government representative(s) are to participate as observers during the TM validation. Contractor must notify the Government 30 days in advance in order to schedule attendance. The plan shall include, at a minimum:

a) Location, dates and time of validation.

b) List of subject matter experts attending validation.

c) A Fault Insertion List (FIL). The FIL will identify the following:

o Method of insertion.

o Symptom.

o Malfunction.

o Conclusion/Faulty Component or Assembly.

All identified faults must be resolved through hands on Validation using the Troubleshooting Procedures within the TM.

d) List of tasks to be performed. A schedule of dates and approximate times of each task validation must be provided.

e) Detailed description of how tasks will be validated. For example, if performance of a portion of one task provides the setup for performance of another task, this must be indicated in the Validation Plan.

f) List of all tools and equipment to be used for each task.

4.2.2. Validation Report. The Validation Report for the TM shall identify the Contractor as the validating entity, dates of the Validation effort, a summary of all information validated, validation methods used, and a summary of all changes identified as a result of Contractor validation, and any additional information necessary to satisfy the data requirements listed in Block 10 of DI-CMAN-80792A; this includes signed certification by the Contractor’s responsible officer(s) that the TM was validated IAW with the approved Validation Plan (CDRL A013).

5. ACCEPTANCE/REJECTION OF DELIVERABLES.

5.1. Acceptance/Rejection of TM Submissions. The Government shall evaluate and determine acceptance of the Initial, Second, Third, and FRC submissions, in accordance with CDRL A012, as applicable. If any submission is found to be in error, insufficient, or otherwise does not meet the requirements in this SOW and the associated CDRLs, the submission shall be rejected and considered a draft until the Contractor corrects the errors. If the Government rejects a submission, it will remain in rejected status until the Government approves that submission. No scheduled submission requirement shall be considered to have been met until the Government has accepted the submission.

As of 15 December 2018 6 Technical Publications

5.1.1. Letter of Acceptance/Rejection of Technical Manual Submissions. The Government will provide a written notification of acceptance or rejection to the Contractor identifying the discrepancies.

5.2. Acceptance/Rejection of Validation Submissions.

5.2.1. Acceptance/Rejection of the TM Validation Plan. The Validation Plan will be reviewed by the Government for acceptability and suitability to the equipment under validation. The Validation Plan will be rejected and considered a draft if the Government deems the plan insufficient or inadequate to provide a thorough and accurate validation of the procedures in the supported TM.

5.2.2. Acceptance/Rejection of the Validation Report. The Validation Report will be reviewed by the attending

Government observer for accuracy. The Validation Report will be rejected and considered a draft if the reported data elements are insufficient or incomplete, if the attending Government observer does not concur that the report is accurate, or if the Validation is not certified by the Contractor’s responsible officer(s) in the Validation Reports.

5.2.3. Letter of Acceptance/Rejection of the Validation Plan and Validation Report. The Government will provide written notification of acceptance or rejection to the Contractor through the Government Contracting Office.

6. TM-RELATED MEETINGS/CONFERENCES.

6.1. Logistics Guidance Conference/Start of Work Meeting. This meeting shall take place at a mutually agreed-upon Government location and date to clarify all matters relating to development, preparation, and submission of data deliverables. The Contractor shall be prepared to identify all questions and discuss all TM requirements. Follow-on meetings between the Contractor and Government representatives may be held at the request of either party to discuss specific document requirements as they relate to the development of equipment publications for this contract. The Contractor shall be prepared to discuss all development and source file requirements at this time. The Contractor shall also provide a sample graphics file in electronic format to the Program Manager via e-mail no later than 2 days prior to the Logistics Guidance Conference for review in order to ensure compliance with MIL-STD-40051-2E. The sample graphics file shall include layered callouts, Additional guidance will be available through scheduled and ad hoc In-Process Review meetings.

6.2. In-Process Reviews (IPR). IPR teleconferences will be held, if necessary, as agreed to by both the

Government and the Contractor at the Logistics Guidance Conference/Start of Work Meeting. During preparation of equipment publications, these IPRs will be used to clarify requirements and provide guidance to the Contractor, ensuring the publications are written to conform to this SOW, the appropriate MIL-STD, and the TM Content Selection Matrix. Either the Contractor or the Government may request additional IPRs by teleconference or in person as required for development and delivery of the TMs.

6.3. Validation.

6.3.1. Scope of Validation. Validation is the responsibility of the Contractor. Operating and maintenance procedures including all PMCS and troubleshooting will be validated against the system equipment

As of 15 December 2018 7 Technical Publications through actual demonstration. Theory and principals of operation and system/component descriptions shall be validated against the current engineering source data.

6.3.2. Validation Schedule. The Contractor shall conduct a validation of TM (10-5411-207-13&P) according to the Contractor-proposed, Government-approved Validation Plan. The validation shall be held at the Contractor’s facilities unless otherwise agreed to by the Government.

6.3.3. Validation Criteria. The TM shall not be considered validated until the following conditions have been fulfilled:

a) TM content reflects configuration of the system/equipment and includes all engineering changes to date.

b) Procedural instructions are readily understandable by the intended user and adequate to perform all operations and maintenance functions.

c) Adequacy of data is checked to ensure that it supports the approved maintenance and support plans.

d) The validation has been conducted according to the Contractor-proposed, Government-approved

Validation Plan. No validation efforts or events will be considered as having been conducted if the Validation Plan has not been approved and accepted by the Government technical publications representative(s).

e) The validation has been observed by the Government; specifically, representatives from technical publications and an ILSC equipment specialist at a minimum.

f) All identified faults in the Fault Insertion List (FIL) must be resolved through hands on Validation using the Troubleshooting Procedures within the TM.

g) The TM is not considered validated until Government accepts the Validation Report (paragraph 4.2.2).

6.3.4. Contractor Responsibilities for Validation. Validation is the responsibility of the Contractor. The

Contractor will coordinate scheduling to ensure attendance by the Government technical writer/editor.

The Contractor shall provide supporting materials to facilitate meaningful Government observation, including procedural text. The Contractor’s responsible officer(s) shall certify the TM has been validated IAW paragraph. 6.3.

6.3.5. Government Responsibilities for Validation. The Government technical publications writer/editor shall observe the Contractor Validation. The Government observer shall not direct, conduct, execute or otherwise place themselves in a position other that of observer during the course of the Validation; the Government observer may advise the Contractor on the course of the Validation if requested by the Contractor. The Government observer shall not provide any manner of certification for the Validation, either by verbal or written instrument, other than acceptance of the Validation Reports following the conclusion of the Validation event.

As of 15 December 2018 8 Technical Publications

6.4. Verification.

6.4.1. Scope of Verification. Verification is the responsibility of the Government, specifically the technical publication element of the proponent command. Operating and maintenance procedures including all PMCS and troubleshooting will be verified IAW AR 25-30 and AMC PAM 25-31.

6.4.2. Verification Plan. The Government will draft and submit for review a verification plan IAW AMC PAM 25-31. The Contractor will review the plan for accuracy, applicability, and availability of personnel and support, and will provide any commentary to the Government.

6.5. Government Responsibilities for Verification. Verification is the responsibility of the Government. The

Government shall coordinate the necessary personnel, facilities, equipment, tools, test equipment, supplies, and pertinent documents required for Verification. The Verification Conference will be scheduled in accordance with Government technical publications writer/editor’s Verification Plan and schedule.

Verification will take place at a Government facility unless otherwise specified. IAW AR 25-30, the technical publication element of the proponent command is responsible for providing guidance to the Contractor and for review, verification, and acceptance of deliverable products. Guidance and direction from any source other than the responsible AMSTA-LCS-E representative cannot be accepted by the Contractor as legitimate and contractually binding guidance for the content or format of either subject TM.

6.6. Contractor Responsibilities for Verification. The Contractor shall support the verification with the

Contractor personnel identified in the Government Verification plan. The Contractor shall take corrective action resulting from the Verification and incorporate it into the TM FRC submission.

7. OTHER REQUIREMENTS.

7.1. TM Over-pack Requirements. The Contractor shall over-pack one copy of the Government furnished

Department of the Army-authenticated Operator Manual with each end item of contracted hardware delivered to the Government as prescribed on the applicable DD Form 1423.

7.2. TM Deliverable Submission Format. The Government will not accept e-mail submissions. TM submittals will be delivered IAW paragraph 4 of this SOW.

7.3. Validation Submission Format. The Government will not accept e-mail submissions. The Contractor shall submit the Validation Plan and Report submissions as a hardcopy document and electronic file (PDF) on a compact disk (CD) in accordance with paragraph 4.2 of this SOW.

7.4. Source Files. The Contractor shall submit source files of all text and graphics. Digital graphics shall be produced so that black and white print production will not result in any loss of resolution. The digitized data shall reflect the content of the text and graphics contained in the FRC Submission delivered to the Government.

7.4.1. XML Source File. The Contractor will submit a valid flattened XML source file in accordance with

MIL-HDBK-2361C, with all graphics files, and graphics worksheet included with each submission. The submitted XML file will parse and compose using Arbortext Editor version 6.0 (or later) and the AMC

LOGSA DTD.

As of 15 December 2018 9 Technical Publications

7.4.2. XML Illustration and Entity References. The flattened XML source file cannot reference any files or illustrations which are not part of the submitted FRC.

7.5. Portable Document Format (PDF). The Contractor shall submit editable PDF files (Adobe Acrobat or equivalent) of all Submissions (Initial, Second, Third, and FRC) in accordance with MIL-STD-40051-2D.

The PDF submissions shall be a single composed file. The final PDF file shall reflect all content of the text and graphics contained in the FRC Submission accepted by the Government. All PDF submissions shall have all fonts embedded.

7.6. Graphics, Illustrations, Symbols, Icons, and Assignment of Unique Illustration Numbers.

7.6.1. Format and Quality. Graphics are normal images used in figures in technical manuals. Illustrations are graphics used in a TM which appear “in-line” and do not have a figure number or title. They are typically small equations, or images imbedded in paragraphs or tables. Symbols are custom made graphics for symbols not found in one of the standard ISO symbol sets. Icons are used in Warnings and Cautions to illustrate or depict hazards. File format for all graphics, illustrations, symbols and Icons shall be Contractor proposed and Government approved at the guidance conference IAW paragraph 7.4 using a Contractor-provided sample graphics file. File format for line art must be in EPS format. All graphics file formats must support layers, for example, all callouts, text, legends or other items in a graphics file must be on a separate layer from the base image. Image quality (resolution) of all graphics, illustrations, symbols, and icons will be at least 300 DPI. Font size used in graphics and illustrations for callouts will be all caps, sans serif and 10 PT size. Font size used in graphics and illustrations for legends will be sans serif, 10 PT size and the first letter of the first word shall be uppercase. An exception is equations which may require use of specific font types or symbol sets.

7.6.2. Graphic Size Limitations. To account for margins and figure titles, maximum graphic image size used for compatibility with XML graphic tags for A4 style pages will be 8”H x 7”W. Maximum image size for foldout style pages will be 8”H x N”W with N” equaling the overall final width of the foldout page minus mandatory margin and apron space (not to exceed 45 inches in width). Margin white pace surrounding the graphic can be no greater than ¼ inch.

7.6.3. Unique Illustration Numbering. All graphics will be assigned a unique illustration number IAW MIL-

STD-40051-2D, paragraph 4.8.27.4.6; this number will appear in the lower right corner of the graphic.

The font of this number will be of a size and style to readily identify it as not being part of the other text in the graphic and small enough to be unobtrusive but large enough to be legible. For tracking purposes, symbols and illustrations will be assigned an illustration number for file naming purposes, but because of their size and use, this number will not be included as part of the image itself. Graphics, illustrations, and symbols will be assigned unique illustration numbers based on the following example:

G06032700001.tif

• 1st Digit: G=Graphic I=Illustration S=Symbol

• 2nd and 3nd Digit: Natick Proponent Writing Group: 03= Shelters and Tents

• 4th through 7th digits: Four-digit TM sequence number: 0327

• 8th through 12th digit: Graphic sequence number: 00001

7.6.4. Proponent Writing Group. Proponent writing group for graphics and illustrations on this contract will be

As of 15 December 2018 10 Technical Publications

03.

7.6.5. Graphics Worksheet. The Contractor will provide a graphics worksheet (electronic or paper format) with each TM submission IAW with paragraph 7.6.5 of this SOW.

7.6.6. Icons. Standard warning and hazmat icons will NOT be assigned graphic control numbers. They should be a consistent size throughout the manual. For continuity, a reprowid and reprodep of 0.5 x 0.5 inches is recommended. The Government will provide electronic copies of commonly used hazard icons as GFI at the Logistics Guidance Conference.

7.7. Distribution Statement. The Government will provide the correct Distribution Statement language at the

Logistics Guidance Conference.

END OF REQUIREMENTS FOR DEVELOPMENT OF THE TECHNICAL MANUAL (TM)