Attachment 0003 - Contractor Price Breakdown.xlsx
XLSX spreadsheet 27 KB Posted
- Solicitation number
- W15QKN-24-Q-A002
About this file
This document appears to be an attachment containing a contractor price breakdown worksheet related to a federal contract opportunity for the replacement of parking lot lighting at the Berry-Rosenblatt Armed Forces Reserve Center in West Hartford, CT.
The federal contract opportunity, solicitation number W15QKN-24-Q-A002, is seeking qualified contractors to complete the parking lot lighting replacement project, which involves the removal and installation of new LED lighting fixtures and poles, as well as all necessary electrical work. The period of performance is 120 calendar days after the notice to proceed. The estimated price range for the project is between $100,000 and $250,000. Proposals are due by 3:00 PM EST on September 4, 2024, and the government intends to make a single award to the responsible offeror whose proposal is technically acceptable and offers the lowest price.
The price breakdown worksheet provides a detailed cost estimate template for the two contract line items - the replacement of the parking lot lights (CLIN 0001) and the payment and performance bond (CLIN 0002). The worksheet includes fields for describing the work, quantities, unit measures, labor hours, equipment, materials, and total costs.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| ID | Sort | Type | Description (to include labor,equipment, material type and grade) | Quantity | Unit Measure | Labor in Manhours | Equipment | Material | Total Cost | ||||||||
| Crew (skill set) | Labor Hours | Total Hrs | City Cost Index | Unit Cost* | Total Labor Cost* | Unit Cost | Total Equipment Cost | City Cost Index | Unit Cost | Total Material Cost | |||||||
| CLIN 0001 -Replacement of Parking lot Lights - CT011 |
CLIN 0002 - Payment and Performance Bond - CT011
Totals SUBTOTAL $ - 0
| GENERAL CONTRACTOR | ||
| % | ||
| Overhead | $ - 0 | |
| $ - 0 | ||
| Profit | $ - 0 |
GRAND TOTAL CLINS 0001 & 0002 $ - 0
| Unit Cost* | Cost for one labor hour of the specified crew |