Attachment 0001 - Request for Information.pdf

PDF 114 KB Posted

Attached to
Dirab Airbase (Saudi Arabia) Construction & Repair Federal contract opportunity
Solicitation number
W90BRJ-22-R-0005
Issued by
Department of the Army Materiel Command Contracting Command Rock Island Arsenal

View the file

Other files for this federal contract opportunity

Other files attached to Dirab Airbase (Saudi Arabia) Construction & Repair, newest first.
File Type Posted
Attachment 0012_SOW_Titled_Dirab Airbase Follow on Repair and Modification_17 February 2022.pdf PDF
B08_RFP Amendment.0004.pdf PDF
Attachment 0013_Industry Questions Following Amendment 0003.pdf PDF
Attachment 0010 - Addendum to Dirab AB Repair SOW.pdf PDF
Dirab Amendment 0003_SIGNED.pdf PDF
Attachment 0011 - B000-DAB-AB-C-671-01_concrete survey.pdf PDF
Attachment 0008- picture (2 of 6)_ 03 Feb 2022 Site Visit Photos W90BRJ-22-R-0005.pdf PDF
Attachment 0008- picture (3 of 6)_ 03 Feb 2022 Site Visit Photos W90BRJ-22-R-0005.pdf PDF
Attachment 0008- picture (4 of 6)_ 03 Feb 2022 Site Visit Photos W90BRJ-22-R-0005.pdf PDF
Attachment 0008- picture (5 of 6)_ 03 Feb 2022 Site Visit Photos W90BRJ-22-R-0005.pdf PDF
Attachment 0008- picture (6 of 6)_ 03 Feb 2022 Site Visit Photos W90BRJ-22-R-0005.pdf PDF
Attachment 0008- picture (1 of 6)_ 03 Feb 2022 Site Visit Photos W90BRJ-22-R-0005.pdf PDF
Attachment 0009- Questions and Answers.pdf PDF
Attachment 0007- Engineer Drawings.pdf PDF
RFP Amendment.0002.pdf PDF
22-R-0005 DRAWINGS.zip ZIP file
RFP W90BRJ-22-R-0005.pdf PDF
Attachment 0005 - Dirab Statement Of Work.pdf PDF
Attachment 0002 - Submittal Registry.pdf PDF
Attachment 0006 - Clause Addendum_Dirab.pdf PDF
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contract Number: Date RFI No.

RFI Description Specification Section Drawing Number

Cost Impacts Associated with this RFI Yes No Maybe Time Impacts Associated with this FRI Yes No Maybe

Submitted by:

Date:

COR

Date

CO

Date

Response from Contracting Officer (if necessary)

Approved Denied

Requested Information:

Recommended Action:

Response from Contracting Officers Representative

Approved Denied

Request for Information

Project Name:

Attachment 1 rolando.u.belong Highlight