Attachement 0004- Scope of Work (SOW) Air Compressor Inspection Form.xlsx

XLSX spreadsheet 13 KB Posted

Attached to
Ingersoll Rand Air Compressors- Preventative Maintenance and Remedial Repair
Solicitation number
W519TC24Q2270
Issued by

About this file

This document is a Scope of Work (SOW) for an Air Compressor Inspection Form. The SOW outlines the inspection and maintenance requirements for Ingersoll Rand air compressors at the Rock Island Arsenal, Joint Manufacturing and Technology Center (RIA-JMTC). The inspection form includes details on checking various air compressor components and systems, such as line pressure, package discharge pressure and temperature, airend discharge temperature, inlet filter condition, coolant filter condition, separator pressure drop, and electrical checks. The SOW also requires oil sample analysis, motor inspection, and recording of IR30 shock pulse readings, motor current and voltage, and IGBT temperatures.

The related federal contract opportunity is a solicitation (W519TC24Q2270) issued by the Department of the Army Materiel Command Contracting Command Rock Island Arsenal for preventative maintenance and remedial repair of Ingersoll Rand air compressors at the RIA-JMTC. The resultant award will be a firm fixed price (FFP) contract. The solicitation is restricted to All Equipment Co. and is issued under FAR Part 12 for commercial items and FAR Part 13.5 for simplified procedures for certain commercial products and services.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

AIR COMPRSSOR INSPECTION

RIA LOCATIONID #
COMPRESSOR TYPEDATE OF INSPECTION
MODELSERIAL NO.
TECHNICIAN
Inspect and check the following (if applicable):
1Line PressureRecent Faults (Yes/No)
2Package Discharge Pressure (off line/on line)
3Package Discharge Temperature
4Total hours/Loaded hours
5Airend Discharge Temperature
6Injection Temperature
7Inlet Filter ConditionLast Change Hrs
8Coolant Filter ConditionLast Change Hrs
9Separator Pressure Drop (PSIG)Last Change Hrs
10Sump Pressure
11Coolers
AOil In°FOil Out°F
BClean After coolerYesNoClean Oil coolerYesNo
12Check Coolant LevelYesNoChange Date & Hrs
13Oil Sample Taken for analysisYesNoDate
14Inspect Main MotorYesNoLast Greased Date/Hrs
15Electrical
ACheck Electrical Connections
BSafety Switches are all operational
16IR30 Shock Pulse Readings(---One Stage---)(---Two Stage---)
MBRLPM1LPM2HPM1HPM2
Loaded (dBm)25 | 35
17Motor Currentamps
Motor Voltagevac
Input VoltagevacPARTS USED:PARTS NEEDED:
DC Bus VoltagevdcP/NDESCRIPTION
Interstage Pressurepsi□□
□□
18IGBT Temps:□□
U□□
V□□
W□□
□□
19Input Rect. Temp□□

20 Reset Maintenance Timer Yes No

21 Actions Taken

22 Action Needed Yes No Urgent Yes No

Sheet2

Sheet3

File details come from the government source that posted it. Updated .