Attach D 659-22-100.pdf
PDF 179 KB Posted
- Solicitation number
- 36C24624R0027
About this file
This document provides the statement of work for project number 659-22-100 to install an energy management system on a campus. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 6 seeks final architectural and engineering design documents including AutoCAD drawings, specifications in Microsoft Word, a submittal list in Excel, and a cost estimate. The selected architect and engineering firm must submit one paper and three electronic copies of the final contract documents to the contracting officer's representative for review and approval. Deliverables are due by the specified dates in the statement of work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24624R0027.docx | DOCX document | |
| Attach C 659-22-100.pdf | ||
| Attach B 659-22-100.pdf | ||
| Attach A 659-22-100.pdf | ||
| Attach E 659-22-100.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
Project No. 659-22-100 Project Title: Install Campus Energy Management System
A/E SCOPE OF SERVICES
Updated 01/06/2020
Attachment D
Contract Document Submission Requirements
Expectation: Submit complete bid document for final review prior to solicitation. Continue to submit until all changes are incorporated by the A/E for final signature prior to solicitation. Upon approval duplicate copies as required.
Deliver the following (labeled with Contract Documents Submission) and include this attachment as a checklist with your submission:
1 sets of all drawings updating all previous comments required by project, produced on Auto CAD 2013/2019 software – for final VA review. If approved final sets to be submitted with signed off cover sheet.
1 copy of the Cover Sheet (AutoCAD) for final VA signatures. VA will return the signed Cover Sheet (CS) to AE. AE will scan CS post to AE FT Site
Upon signature approval, provide and deliver to COR (2) full size sets of final Contract Documents (complete with VA signed Cover Sheet). Provide and deliver to COR (3) ½ size sets of final drawings.
2 copies of final project specification (one bound; one loose) prepared in Microsoft Word 2010 software.
Include a master submittal list in the specifications.
Provide 2 CDs of entire submittal package with delivery of hard copy design layouts and documents
Posted to AE FT o All drawings in AutoCAD 2013/2019 and in PDF file. All CAD drawings are to be bound files with the engineering / architect stamps removed.
o All specifications in Microsoft Word o Submittal Spreadsheet via Excel spreadsheet – identifying all the submittals required to be submitted by the Contractor for review. The list shall be organized by division and specification.
o Final copy of itemized cost estimate by spec section or trade (labor, material, and equipment).
File details come from the government source that posted it. Updated .