Attach C_Project Special Conditions.pdf

PDF 239 KB Posted

Attached to
HHS0017654 - 24-119 LBL Fire Alarm Panel Upgrades
Solicitation number
HHS0017654
Issued by
Texas

About this file

This document is an Attachment C detailing Project Special Conditions for a Texas state and local construction contract related to HHS0017654 - 24-119 LBL Fire Alarm Panel Upgrades. The special conditions outline insurance requirements and liquidated damages provisions that modify the 2025 Texas Uniform General Conditions and Supplementary General Conditions. The contractor must provide umbrella liability insurance coverage of not less than $2,000,000, professional liability insurance with minimum limits of $1,000,000 per claim and $1,000,000 aggregate to cover negligent acts or omissions by contractor personnel and subcontractors, and cyber/privacy liability insurance with the same $1,000,000 per claim and aggregate limits to protect against electronic data loss, vandalism, viruses, and denial of service attacks. The professional liability policy must not exclude claims arising from bodily injury, property damage, habitational operations, pollution or mold, punitive damages, or design/build services.

The liquidated damages section establishes that failure to achieve substantial completion by the date specified in the Owner's Notice to Proceed will result in assessed damages of $300 per calendar day, or part thereof, that work remains incomplete. The Owner may withhold liquidated damages from contract payments or demand payment within 30 days, with authority to make claims against the performance bond if payment is not received. The Owner retains sole discretion to assess damages, and failure to assess damages in any instance does not constitute waiver of future assessment rights. Construction phases may be staged or fast-tracked with separate Notices to Proceed and substantial completion dates issued for each stage. Substantial completion dates and construction schedules represent essential contract elements, with time extensions available only through formal Change Order.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Template Updated: July 2026

Attachment C Project Special Conditions

Attachment C

Project Special Conditions

Article I. INSURANCE

1.1 Subsection 5.2.6.1.6 of the 2025 Texas Uniform General Conditions and Supplementary

General Conditions, is hereby amended by adding a new Subsection as follows:

5.2.6.1.6.1 Umbrella Liability Insurance Required Amount. Contractor shall provide Umbrella Liability Insurance coverage in the amount not less than $2,000,000.00.

1.2 Subsection 5.2.6.1 of the 2025 Texas Uniform General Conditions and Supplementary General

Conditions, is hereby amended by adding a new Subsection as follows:

5.2.6.1.7 Contractor's Professional Liability Insurance. Contractor’s Professional Liability Insurance with the minimum limits of coverage not less than shown below shall be provided by Contractor to cover the rendering of or failure to render professional services arising out of or in connection with any negligent act, error or omission of all Contractor personnel, including any subcontractor acting for, in combination with, on behalf of, or under the direction or control of the Contractor in the performance of any Services or Work required under this Contract. This policy shall not include any type of exclusion or limitation of coverage applicable to claims arising from: (i) bodily injury or property damage where coverage is provided on behalf of Contractor or its subcontractors; (ii) habitational or residential operations; (iii) pollution, mold and/or microbial matter and/or fungus and/or biological substance; (iv) punitive, exemplary or multiplied damages; (v) rendering of or failure to render professional services arising out of the negligence of Contractor’s personnel; or (vi) design/build services.

Professional Liability Insurance $1,000,000.00 Each Claim / $1,000,000.00 Aggregate.

1.3 Subsection 5.2.6.1 of the 2025 Texas Uniform General Conditions and Supplementary General Conditions, is hereby amended by adding a new Subsection as follows:

5.2.6.1.8 Cyber/Privacy Liability Insurance Policy. Contractor shall provide

Cyber/Privacy Liability Insurance to cover risk of loss to electronic data. The policy must include coverage for electronic vandalism to electronic data, including coverage for a third party's willful electronic alteration of data, introduction of viruses which impact electronic data, unauthorized use of electronic data, or denial of service to web site or email destinations.

Cyber Liability Insurance $1,000,000.00 Each Claim / $1,000,000.00 Aggregate.

Article II. LIQUIDATED DAMAGES

2.1 Subsection 9.11 of the 2025 Texas Uniform General Conditions and Supplementary General

Conditions, is hereby amended by adding new Subsections as follows:

9.11.1 Owner is entitled to full and beneficial occupancy and use of the completed Work. If Contractor fails to meet Substantial Completion of any portion of the Work in accordance with the approved Work schedule, Owner will sustain actual damages as a result of such failure.

9.11.2 Contractor agrees that:

(1) establishing the precise measure of damages in the event of default by the

Contractor may be (i) costly, (ii) time consuming, or (iii) difficult or impossible to calculate;

(2) the liquidated damage assessments in this section represent a good faith effort to quantify the damages that could reasonably be anticipated at the time of execution of the Contract;

(3) the liquidated damages in this section are just and reasonable and are not a penalty;

(4) nothing contained in this section shall be construed as relieving the Contractor from performing all Contract requirements whether or not said requirements are set forth herein; and

(5) All assessments of damages shall be within the sole discretion of the Owner.

9.11.3 Liquidated Damages Assessment. Once the Owner has determined that liquidated damages are to be assessed, the Owner shall notify the Contractor of the assessment(s). Failure to notify does not impact the Owner’s assessment of damage and is not a condition precedent thereto. The Owner will withhold liquidated damages from payments to the Contractor, or, if no payments have been made, the Owner will make demand of payment of liquidated damages. The Contractor must make payment within 30 days of the Owner’s demand. In the event the Contractor fails to pay within the 30-day period, the Owner may make a claim for payment against the performance bond, with or without notice to the Contractor. In the alternative and at Owner’s sole discretion, the Owner may deduct liquidated damages from the Contract Sum payable to Contractor as stated in the UGCs, Standard Construction Terms and Conditions, or Project Special Conditions.

9.11.4 Failure to Assess Liquidated Damages. The failure of the Owner to assess liquidated damages in any instance where the Owner is entitled to liquidated damages pursuant to the terms of this Contract shall not constitute waiver in any fashion of the Owner’s rights to assessment of liquidated damages.

9.11.5 Severability of Individual Liquidated Damages Clauses. If any portion of Section

9.11 is determined to be unenforceable, the other portions of Section 9.11 will remain in full force and effect.

9.11.6 Failure to Meet Substantial Completion Date. The failure of the Contractor to meet the Substantial Completion date for any portion of the Work in accordance with the approved Work schedule under Article 9, Construction Schedules, 2025 Texas Uniform General Conditions and Supplementary General Conditions, may result in the assessment of liquidated damages in the sum of $300.00 for each calendar day, or part of a day, after the Substantial Completion Date that the Work remains incomplete. This sum is not construed in any sense as a penalty

9.11.7 Time of Completion

9.11.7.1 The date for achieving Substantial Completion of the Project shall be set forth within the Owner’s Notice to Proceed.

9.11.7.2 The Construction Phase will be deemed to commence on the date specified in a Notice to Proceed issued by Owner.

9.11.7.3 Contractor will achieve Substantial Completion of the Work and Final

Completion of the Work on or before the dates set forth within the Notice to Proceed and the Contract, subject to time extensions granted by Change Order.

9.11.7.4 The times set forth for completion of the Work in the Notice to Proceed with

Construction are an essential element of the Contract. Owner may elect, at its option, to stage or “fast-track” portions of the Work. Owner will issue a separate Notice to Proceed or Change Order for each such stage and each such stage will have a separate substantial completion date.

(The Remainder of this Page is Intentionally Left Blank)