Attach B Specifications Updated.pdf

PDF 605 KB Posted

Attached to
ITB Glenada Ridge and Yaquina Head - Comm Site Builds
Solicitation number
S-73000-00007266
Issued by
Klamath County, Oregon

About this file

This document is a Scope of Work for a wireless communications site construction project issued by the Oregon Department of Transportation (ODOT) Wireless Communications Section. The project involves replacing an existing communications building at the Yaquina Head site with a new prefabricated building, and adding a repurposed communications building to the existing Glenada Ridge site, including infrastructure upgrades on the existing tower. Key requirements include obtaining necessary permits, completing inspections, following construction reporting and scheduling, installing foundations, shelters, electrical and grounding systems, and fencing. The project sites are located in coastal areas and have specific requirements for corrosion resistance and coordination with local utilities.

The Scope of Work is related to an Invitation to Bid (ITB) issued by ODOT for the Glenada Ridge and Yaquina Head communications site construction project. This is a state-level contract opportunity in Oregon, with the work to be performed in Lane County and the City of Newport. The ITB seeks to establish a single contract for the specified construction activities at the two sites.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Oregon Department of Transportation Wireless Communications Section Communications Site Construction Scope of Work – Yaquina Head and Glenada Ridge

Oregon Department of Transportation Wireless Communications Section

Wireless Site Construction Scope of Work

Project: Yaquina Head Shelter Replacement and Glenada Ridge Shelter Addition

1. Wireless Communications Site Construction Requirements

1.1. Permits and Access

1.1.1. The Agency will obtain the following permits. Any additional permits are the responsibility of the Contractor.

1.1.1.1. Land Use Approval

1.1.1.2. Legal Access to the communication site from property Agency via Easements and Lease (additional permits may be required for material transport)

1.1.1.3. Building Permit

1.1.2. The Contractor is responsible for any repairs or maintenance to the site access roads during construction to ensure the roads remain in the before construction condition during and immediately following construction.

1.1.3. The Contractor is responsible for documenting the condition of the access road at the start of construction as any claims made against the Agency for damage to the road as a result of construction will be passed on to the Contractor to resolve.

1.1.4. Prior to and following construction the site requires an Agency escort or approval for access.

1.1.5. If construction occurs during fire season, all applicable fire regulation and restrictions must be adhered to.

1.2. Specifications

1.2.1. The applicable specifications for this project can be found in the General Notes section of the engineer plans for the project. Grounding is to be completed per the current at the time of construction Motorola R56 grounding guidelines.

1.3. Inspections

1.3.1. All Structural fill and foundations require special inspection by a 3rd party inspection and testing firm. The Agency will hire the inspection firm.

1.3.2. Additional aspects of the project may require inspection by the 3rd party inspection as required by the building permit. Refer to the permit package for the specifics.

1.3.3. An Agency Representative needs to inspect the following key aspects of the site:

1.3.3.1. Installation of fill including compaction of any non-structural fill

1.3.3.2. Below grade conduit installation

1.3.3.3. Below grade grounding

1.3.3.4. Ufer Grounds

1.3.3.5. Grounding installation above grade conformance to standards

1.3.3.6. Conformance to the site design

1.3.3.7. Ground System fall of Potential Test (required witness during test)

1.3.3.8. Fence post footings

1.3.3.9. Substantial Completion

1.3.3.10. Final Completion

1.3.4. Inspection requests must be submitted at least one week prior to the desired inspection date.

1.4. Project Schedules and Construction Reporting

1.4.1. The Contractor shall maintain an up-to-date project schedule submitting revisions on a weekly basis if needed. At a minimum the project schedule should include the following milestones when applicable to the project scope:

1.4.1.1. Construction Start

1.4.1.2. Each foundation concrete placement

1.4.1.3. Below grade grounding inspection

1.4.1.4. Tower Stack

1.4.1.5. Shelter set

1.4.1.6. Propane tank installation

1.4.1.7. Propane line test

1.4.1.8. Generator Commissioning

1.4.1.9. Commercial Power Installation

1.4.1.10. Fence installation

1.4.1.11. Substantial Completion

1.4.1.12. Final Completion

1.4.2. At the end of each week the Contractor shall submit to the Agency, their representatives, and the Engineer of Record a construction progress report that summarizes the work completed that week including photos documenting the progress.

1.5. Requests for Information During Construction

1.5.1. If clarification is needed in the plans or contract documents, the Contractor must submit their clarification questions in writing. Only the Agency can modify the contract documents and modifications require a Contract Change Order.

1.5.2. If there is conflicting information in the project documents, the Contractor shall submit in writing a request for clarification and direction from the Agency.

2. Civil Improvements

2.1. General Requirements

2.1.1. Contractor shall provide, install, and maintain all necessary sedimentation control and erosion prevention per the Plans.

2.1.2. Contractor shall install, for future use, pull strings in all conduits installed.

2.1.3. Contractor shall install appropriate termination at each end of all conduits.

2.1.4. High water levels may be encountered. Based on pre-Bid observation of the site, Contractor shall include sufficient time in the proposed construction schedule to accommodate dewatering that may be required. Should high water levels be encountered during construction, Contractor shall consult with Agency and Engineer to agree on a construction plan for dewatering the site. The dewatering plan and compensation, if applicable, must be implemented by a Contract Change Order (“CCO”).

2.1.5. Contractor is responsible for all public and private underground infrastructure and utility locates. The drawings may not reflect all below grade infrastructure. The Contractor is responsible for any damage to existing infrastructure and utilities that results from Contractor negligence.

2.1.6. The geotechnical report and engineer design identify what materials are acceptable for structural fill material. The Contractor shall abide by this design which may require importing fill material and exporting construction spoils.

2.1.7. If Contractor finds excavated materials to not match the design documents, the Contractor shall seek written approval from Agency for clarification on the use of the material.

2.1.8. If Contractor fails to appropriately schedule and execute the Work and to protect, preserve, and properly handle earth materials suitable for fill such that suitable soil materials become unusable, Contractor shall be responsible to provide suitable imported fill material at no cost to Agency.

2.1.9. All tree stumps, debris and slash resulting from clearing of the project site, and all excess excavation materials become property of Contractor. Contractor shall remove all tree stumps, debris, slash and all excess excavation materials from the project Site and dispose of them. Contractor shall make all arrangements for suitable disposal. Contractor shall not burn debris and slash on Site.

2.1.10. Contractor shall ensure site compound is free of vegetation upon Site completion.

2.1.11. Contractor shall coordinate with Agency’s Special Inspector for all concrete, soils density, proctor, and steel inspections. Contractor shall collect all Proctor samples for all proposed fill material (native and imported).

2.1.12. Contractor shall coordinate with the Agency at least 48 hours prior to need for inspection. The minimum required inspections include concrete, steel, soils density, grounding, erosion control, and periodic inspections. All required inspections are defined in the Plans and SOW.

2.1.13. Contractor shall inspect all installed equipment and structures for damages and quality, and shall document the installation with photos immediately upon final construction, installation or assembly. Contractor shall include sufficient photos in the Contractor’s Daily Progress Report to document the installation and sufficient photos in the Closeout Package to document the quality of the installation.

2.1.14. Trench backfill and areas of fill below foundations and structural areas require the fill to be tested. Contractor shall coordinate with Agency’s Special Inspector for these tests. If tests are not performed as required, Contractor shall excavate and refill the area with the tester on site at Contractor’s expense.

2.1.15. The Contractor is responsible for construction staking locating the new structure foundations and overall site layout.

2.2. Foundations

2.2.1. Contractor shall install foundations as depicted on Construction Drawings

2.2.2. Contractor shall cure foundations to the requirements in the Construction Drawings.

2.2.3. Contractor shall coordinate all inspections with the Special Inspector and the Agency at least 48 hours prior to need for inspection. Special Inspections (provided by Agency) and Agency inspections are required for all reinforced concrete with specified strength greater than 2500 psi. Concrete inspection required includes both reinforcing steel prior to pour and concrete during pour.

2.2.4. The Agency’s Special Inspector will provide up to eight (8) compression cylinders, tested (broken) on the following schedule: 3, 5, 7, 14, two at 28 days, and hold/56 days. The remaining cylinders are at the Contractor’s discretion for the test (break) days.

2.3. Tower, Steel Platforms, and Steel Installation

2.3.1. Contractor shall provide stainless steel or galvanized exterior hardware. Contractor shall hot-dip galvanize all Contractor-supplied steel parts.

2.3.2. All required field modifications to steel must be properly treated with cold galvanizing compound.

2.3.3. All exterior zip ties must be stainless steel. Protruding ends of all interior nylon zip ties must be flush cut. All interior zip ties must be black UV resistant nylon.

2.3.4. All exposed Unistrut and all-thread ends must be covered with appropriately sized rubber caps.

2.3.5. Contractor shall notify the Agency 48 hours in advance of beginning construction of the tower and 24 hours in advance of completing construction of the tower to full height.

2.4. Shelter and Shelter Improvements

2.4.1. Contractor shall perform all field assembly of shelters installed as part of this contract.

2.4.2. Shelter anchoring requires inspection to verify anchor installation to the foundation.

2.4.3. Shelters are to be transported to the site by the contractor from the storage location specified in the site specific section.

2.4.4. Contractor is responsible for field electrical connections for all newly installed shelters.

2.4.5. As substantial completion the shelter shall be clean, fully operational, and ready for use by the Agency.

2.4.6. New Heating, Ventilation, and Air Conditioning units require commissioning by a licensed

HVAC professional to be hired and provided by the Contractor.

2.5. Electrical

2.5.1. Contractor shall perform all electrical Work in compliance with the National Electric Code and the local jurisdiction requirements.

2.5.2. Contractor shall obtain any electrical permits required by the local jurisdiction.

2.5.3. Contractor shall install electrical Work per the Plans.

2.5.4. Contractor shall notify the Agency and the Agency 72 hours prior to Installation of a new power meter.

2.5.5. Electrical Work may be reviewed by the Agency in addition to jurisdiction inspections. The

Contractor shall provide access to all closed electrical boxes in which Contractor has performed Work.

2.5.6. For all new installed generators (including generators provided with a new building), Contractor shall coordinate generator commissioning with generator supplier.

Commissioning shall include generator preparation, installation of battery, start-up and a 1-hour load-bank test. Contractor shall also coordinate scheduling of the commissioning with the Agency and the Agency at least one week in advance of the commissioning.

Commissioning by supplier is at no charge to Contractor.

2.5.7. Contractor shall provide, construct, and install a solar and wind power generation system per the design and route all the wiring through the combiners and to the battery charge controller leaving a minimum of 48” of extra wire for the power system controller installation.

2.6. Grounding

2.6.1. Contractor shall install all new grounding and grounding upgrades required by the project

Plans and Statement of Work.

2.6.2. Contractor shall perform all grounding Work in accordance with the Plans, Statement of

Work, and current revision of the Motorola R56 Grounding Guidelines in addition to all applicable local, state, and national codes.

2.6.3. Contractor shall provide three-point fall of potential test of the installed ground ring upon site completion. This test shall be performed in accordance with Motorola’s procedures and recommendations. This test can be performed after the site is operational.

2.6.4. All below-grade grounding constructed as part of this Contract requires Agency inspection before backfilling.

2.6.5. In some jurisdictions, the jurisdiction may require inspecting aspects of the grounding in addition to the Agency inspection.

2.6.6. If there is a conflict between the Plans or Statement of Work and the Grounding Guidelines, Contractor shall request clarification through the Owner and the Owner.

2.6.7. New buildings, tower, ice bridge installations, and grounding upgrades require new ground bar installations as shown in the Plans. Ground bar locations are at the tower (“TGB”) and interior (“MGB”) and exterior (“EGB”) of the entry port.

2.6.8. The Plans may not give a full representation of all required grounding bonds. Contractor shall bond all exterior metal components and structures per R56 Guidelines.

2.7. Fences, Gates, Signs, and Site Security

2.7.1. Fence and gate post installation requires Agency inspection to verify footing diameter and depth.

2.7.2. All gates must swing freely and have a latch to hold them in the open position.

2.7.3. Contractor is responsible for providing all new signage and installing with tamper proof hardware.

2.7.4. If a site does not have a fence, the signs are to be installed on the building on or near the radio room door.

2.7.5. During construction the security of the project site and communications site compound is the responsibility of the contractor. If the scope requires removal of existing fencing, temporary fencing shall be installed unless otherwise noted.

3. Site Specific Scope

3.1. Yaquina Head

3.1.1. This site is to replace an existing two room communications building with a new prefabricated building of similar size. The new building is located at the ODOT Wireless Communications office in Salem Oregon.

3.1.2. The project site is within the Yaquina Lighthouse federal park and the access road is a hiking trail open to the public. Contractors should anticipate frequent general public on the access road and near the work site. Additional safety measures to ensure that any hazards to the public are clearly identified and means are in place to prevent accident injury are used. This includes, but is not limited to, flagging and barricading any open trenches, not leaving open trenches over weekends or multiple days that the contractor will not be on site, traveling as a safe speed on the access road, ensuring that any electrical equipment is secure from public access.

3.1.3. The current site is active and will require a temporary communications trailer to be parked at the site for the equipment during construction. The contractor shall provide temporary power for this trailer. The Agency has coordinated a plan with the local power utility for the existing power to be cut over to a Contractor installed construction power panel. For this to occur, the Contractor is going to need to coordinate with the Agency and the power company to minimize the amount of time the Agency’s equipment is without commercial power. It is expected that the construction power panel will be installed wired and set up to allow the cut over from the existing building to the construction power to happen within two hours.

3.1.4. The existing Agency Site and the neighboring sites have underground utilities that require a private utility locate service. The Contractor is responsible for all underground locates.

3.1.5. The building permit is issued through the City of Newport. The Contractor is responsible for any trade permits required for Electrical and Gas installation.

3.1.6. The Building is a Oregon Gold Sealed Building and the Generator is installed in the building.

Final wiring inside the building for connection to the commercial power will be required.

3.1.7. This is a coastal site therefore all exterior electrical boxes and conduits must be corrosion resistant either stainless steel or plastic. Coated steel is not acceptable. The Meter base must be stainless steel.

3.1.8. Coordination with the local utility (Central Lincoln PUD) is required for both the construction power and the final power installation. The new meter is to be located on the building, not down the road where the existing meter is located.

3.2. Glenada Ridge

3.2.1. This project is to add a repurposed communications building to the existing Central

Lincoln PUD (CLPUD) communications site and install infrastructure on the existing CLPUD tower.

3.2.2. The building is currently located at the Agency’s Glenwood Maintenance yard located in Eugene Oregon and will need to be transported by the Contractor to the site. The building has been refurbished by the Agency in the yard but will require field installation of hoods and exterior components.

3.2.3. The contractor is to install a new shed roof style membrane roof to direct rain water flow to the back side of the building.

3.2.4. Site access crosses timberland and forest roads for which the Agency has legal access across. The contractor is responsible for any wear, erosion, or damage to the roads during construction.

3.2.5. This is a coastal site therefore all exterior electrical boxes and conduits must be corrosion resistant either stainless steel or plastic. Coated steel is not acceptable. The Meter base must be stainless steel.

3.2.6. The permitting jurisdiction is Lane County. The Agency is obtaining the land use and building permit approvals. All other permits are the responsibility of the Contractor.

3.2.7. The Generator will be installed in the building at the ODOT yard, some final electrical connections will be required by the contractor for final field installation.

3.2.8. The new power service to the building will need to be coordinated with CLPUD. There is an existing utility pull box located just outside of the existing communications site fence.

This is the point of interconnection with CLPUD and will become a splice box for the power service. The Contractor is responsible for all the infrastructure required to get to this point of interconnection.

3.2.9. The Contractor shall procure and install the new HVAC system.

3.2.10. Extra care is required to ensure that the existing fill slope is not compromised by the installation of the propane tank foundation.

3.2.11. Lane County has required that the retaining wall be an engineered wall, therefore the design in the plans must be followed and installation will be inspected.

3.2.12. During relocation of the fence and gates, the Contractor shall maintain site security.

3.2.13. During construction neighboring sites must remain accessible.

3.2.14. The shelter weights approximately 14,000 lbs

3.2.15. As a separate line item on the bid include cost to install a single pitch shed roof onto the building after all the site work is completed if determined necessary by the Agency. This work will require a cost change order to approve and would likely happen after the main scope of the project is accepted and in service.

3.2.15.1. This building has anchors built into the manufactured roof for installation of an alpine roof. If this work were to be performed, the new shed roof would be a single pitch roof sloping to the back of the building.

3.2.15.2. The roof structure would be field constructed by the contractor using 2x6 framing, ½” exterior grade plywood sheeting, moisture barrier, and standing seam metal roofing. The roof would create a minimum of a 6” eave on the building. The pitch would be based on industry standards for a coastal site. The frame would need flashing and screened venting to prevent rodent and bug infestation and control water and wind infiltration during storms. The roof mounting anchors to the prefabricated building threaded mounts would need to be galvanized steel located in a structural corner of the roof frame anchoring both directions of framing to the building.

3.2.15.3. Prior to starting construction the Contractor’s plan and design would need to be approved by the Agency.