This is a Contractor Work Surveillance Checklist specifically for Industrial Cleaning Services (ICS) CLINs 1002SV-1004SV & 1007SV-1009SV, which is part of a hazardous waste removal contract for the San Joaquin region.
The checklist enables government representatives to monitor contractor compliance across eight key areas: timely arrival, required equipment presence (including a 3,500-gallon vacuum truck with 300 feet of hoses, heated power washing unit, liquid transfer pump, and PPE), proper documentation of truck weight, government inspection completion, tank cleanliness and chemical compatibility, RCRA compliance for waste residue, equipment operation without delays, and overall work satisfaction. The form includes spaces for recording surveillance dates, times, government representative information, yes/no/N/A responses, comments, and an official signature.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attach 12_20D0012 Usage Report_REV1.xlsx | XLSX spreadsheet | |
| Attach 12_Usage for SJ 20D12.pdf | ||
| Attach 6_San Joaquin_PUP_Jan24.xlsx | XLSX spreadsheet | |
| Attach 3_Additional Contract Terms and Conditions.docx | DOCX document | |
| Attach 4_Addenda to 52.212‐1 Instructions.docx | DOCX document | |
| Attach 10_San Joaquin_KTR Work Surveillance ROB.pdf | ||
| Attach 2_San Joaqui_PWS_REV12042024.docx | DOCX document | |
| Attach 5_Addenda to 52.212‐2 Evaluation.docx | DOCX document | |
| Attach 1_San Joaquin Price Schedule_REV.xlsx | XLSX spreadsheet | |
| Attachment 11_Provision Fill-ins.pdf | ||
| Attach 8_WD 1996_0223_v63_07222024.pdf | ||
| Attach 7_PPI Questionnaire.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contractor Work Surveillance Checklist
Industrial Cleaning Services (ICS) – CLINs 1002SV-1004SV & 1007SV-1009SV
Date(s) of Work Surveillance: _________________ Start Time: ___________ Stop Time: ___________
Name of Designated Government Representative: ___________________________________________
Title of Designated Government Representative: ____________________________________________
Phone Number of Designated Government Representative: (______) ________-___________
Yes No N/A Description of Contractor Work Surveillance
Did the work crew arrive on site at the scheduled time and date?
Did the crew arrive on site with all of the requisite equipment, including
- One standard vacuum truck (3,500-gal capacity) w/ 300 feet of hoses,
- One self-contained heated power washing unit,
- One liquid transfer pump w/ 300 feet of hoses, and
- All appropriate PPE and tools?
Did the vacuum truck driver provide a weight ticket showing the empty (tare) weight of the vacuum truck?
Was the vacuum truck inspected by a designated Government representative prior to use?
Did the vacuum truck arrive with a clean tank and hose fittings that were constructed of material that that was chemically compatible with the waste to be removed?
Did the vacuum truck arrive free of visible waste residue unless the truck was being used for multiple removals from the same project involving the same waste stream
(in which case it arrived as meeting definition of RCRA empty per 40 CFR 261.7)?
Did all of the equipment operate properly without causing delay in work?
Was the work performed to the satisfaction of the designated Government representative?