ATTACH_4_-_Construction_Schedule.docx
DOCX document 19 KB Posted
- Attached to
- SYNAR AML Reclamation Construction
- Solicitation number
- 140S0326B0002
About this file
This is a construction schedule document for SYNAR AML (Abandoned Mine Land) reclamation work under solicitation 140S0326B0002, issued by the Department of the Interior Office of Surface Mining Reclamation and Enforcement. The schedule outlines a 15-day project timeline for site preparation and environmental remediation activities associated with project code CC-023-005.
The construction activities are sequenced across the 15-day period and include mobilization, site clearing and grubbing, installation of an air incinerator, earth fill placement, fence construction (5-wire), traffic-bound surface course application, erosion control measures (straw wattle and rock check dams), and rip rap type IA installation at 12-inch depth. The schedule also incorporates soil stabilization and agricultural reclamation components, including gradient terraces, deep disking, and application of agricultural amendments (lime, nitrogen, phosphorus, and potassium), concluding with seeding operations. This schedule represents the typical sequencing and phasing required for a comprehensive mine reclamation project combining both engineering controls and environmental restoration activities.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Date:
| Feature |
| Item |
| Day: |
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
| 6 |
| 7 |
| 8 |
| 9 |
| 10 |
| 11 |
| 12 |
| 13 |
| 14 |
| 15 |
| CC-023-005 |
| Mobilization |
Clearing and Grubbing
Air Incinerator
Earth Fill
Fence (5 wire)
Traffic Bound Surface Course
Straw Wattle
Rock Check Dam
Rip Rap Type IA (12”)
Gradient Terrace
Deep Disking
Agriculture Lime
Nitrogen
Phosphorus
Potassium
Seeding