Attach 3 - Specifications - 828_ 2012_ 2125_ 2313.pdf

PDF 7 MB Posted

Attached to
Generator Replacement Federal contract opportunity
Solicitation number
FA670325B0006
Issued by
Department of the Air Force Reserve Command

About this file

This document is a technical specification for replacing and studying generators at multiple facilities on Dobbins Air Reserve Base in Georgia. The project involves installing new 24-hour diesel/JP8 fuel generators with double-walled tanks at four specific locations: Buildings 828 (Lift Station), 2012 (ILS Glideslope West), 2125 (ILS Localizer East), and 2313 (Lift Station). Additionally, a 150kW Cummins C150D2RE Mobile Generator will be provided as a portable unit.

The specification details technical requirements including installation of four or three-pole bypass-capable Automatic Transfer Switches (ATS) with switched neutral, equipment grounding, concrete pads, and site preparations. All newly installed generators must meet the latest U.S. Environmental Protection Agency air quality and emission requirements for diesel generators. The project also includes removing and disposing of existing generators, real property installed equipment, and associated fuel tanks. Specific technical requirements cover electrical connections, surge protection, camlock connectors, and equipment ground testing, with a comprehensive set of technical specifications and quality control standards governing the installation process.

View the file

Other files for this federal contract opportunity

Other files attached to Generator Replacement, newest first.
File Type Posted
Attendance Roster.pdf PDF
Solicitation Amendment FA670325B00060001 SF 30.pdf PDF
Questions Answers - Generator Replacement.xlsx XLSX spreadsheet
Attach 2 - Drawings - 550_ 1001_ 2021_ 2300.pdf PDF
Attach 1 - Specifications -550_1001_ 2021_ 2300.pdf PDF
Attach 4 - Drawings - 828_ 2012_ 2125_ 2313.pdf PDF
Solicitation - FA670325B0006.pdf PDF
Attach 5 - Wage Determination.pdf PDF
Attach 6 - Financial Institution Reference Sheet.pdf PDF
Attach 7 - Submittal Register.xlsx XLSX spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Specifications Replace/Study/Add Generators at Facilities 828, 2012, 2125 & 2313

Final Submittal

Submitted to:

94 CONF/LGC, Dobbins ARB

Contract Number:

P15PC00467

Submitted by:

Croft & Associates, Inc.

3400 Blue Springs Rd, Suite 200

Kennesaw, GA 30144

Telephone: (770) 529-7714

Dobbins ARB, GA

July 2020

Attach 3 FA670325B0006

Dobbins ARB – Replace/Study/Add Generators DOBBINSGEN

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 01 00 GENERAL REQUIREMENTS

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 45 00.00 10 QUALITY CONTROL

01 56 00 DOBBINS ENVIRONMENTAL REQUIREMENTS

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DEMOLITION AND DECONSTRUCTION

02 82 00 ASBESTOS REMEDIATION

02 83 00 LEAD REMEDIATION

DIVISION 03 - CONCRETE

03 30 00.00 CAST-IN-PLACE CONCRETE

DIVISION 09 - FINISHES

09 90 00 PAINTS AND COATINGS

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 31 13.00 40 METAL DUCTS

DIVISION 26 - ELECTRICAL

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS

26 05 00.00 40 COMMON WORK RESULTS FOR ELECTRICAL

26 05 74 ARC FLASH PROGRAM

26 24 16.00 40 PANELBOARDS

26 32 14.00 10 DIESEL-GENERATOR SET, STATIONARY 15-400 KW, STANDBY

APPLICATIONS

26 36 00.00 10 AUTOMATIC TRANSFER SWITCH AND BY-PASS/ISOLATION SWITCH

26 36 01 3-WAY MANUAL TRANSFER SWITCH

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK

31 11 00 CLEARING AND GRUBBING

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION 010100 Page 1

Dobbins ARB – Replace/Study/Add Generators DOBBINSGENS

SECTION 01 01 00

GENERAL REQUIREMENTS

PART 1 GENERAL

1.1 PROJECT INFORMATION

1.1.1 Contract Drawings and Specifications

1.2. SUBMITTALS

Submittals shall be submitted in accordance with Section 01 33 00, SUBMITTALS.

NOTE: The contractor shall obtain Government approval of all materials and equipment requiring submittals prior to bringing these materials and equipment onto

Dobbins ARB for installation and incorporation into the work. The contractor shall follow section 01 30 00 of the basic contract in obtaining Government approval.

1.2.1. Administrative or Close-out Submittal

a. Construction Phasing (ref: paragraph 3.2.1)

b. Daily Progress reports to Contracting Officer within 2 hours of shift completion

c. Quality Control Plan, (ref: paragraph 3.17.6)

d. As-built drawings & Record Drawings (After construction complete)

e. DD Form 1354 INTERIM – Required prior to final inspection for each site.

Coordinate requirements with COR prior to submission

GENERAL DESCRIPTION

1.3.1. Location

The project is located at buildings 828, 2012, 2125 & 2313 on Dobbins ARB, Georgia.

1.3.2. Project Description

The facilities included in this project as well as the associated scope is provided below.

Coordinate any scope discrepancies with the Contracting Officer prior to beginning work.

New generator work shall include accommodating 24 hour generator diesel/JP‐8 fuel double walled tank capacity, four or three pole by‐pass capable ATS installation with switched neutral, equipment grounding, concrete pad, and new site preparations. Site will require additional concrete if generator is larger in size than shown on the drawings. Surge protection will be required for utility, generator, and load side of equipment. Either fuel source could be interchangeably used. All newly installed generators must meet the latest U.S. Environmental Agency air quality/emission requirements tier rating for diesel generators.

• Install new generator, Bypass Isolation Automatic Transfer Switch (ATS) with switched neutral, 3-Way manual transfer switch (MTS), and surge protection.

o 828 - Lift Station - Use integral fuel tank o 2012 - ILS Glideslope West - Use integral fuel tank o 2125 – ILS Localizer East - Use integral fuel tank o 2313 – Lift Station - Use integral fuel tank o 150kW - Cummins C150D2RE Mobile Generator - Portable Generator Only

1.3

SECTION 010100 Page 2

All real property installed equipment generators, ATS, and fuel tanks removed will be the general contractor’s responsibility for disposal, unless noted otherwise. The contractor is responsible for disposing of fuel appropriately. Dobbins ARB Environmental personnel will provide direction for reclaiming and disposing of fuel. Cam‐lock connectors will be installed for all 3-Way MTS installation to connect portable generators.

Cam‐Lock connectors shall not be rated greater than 200 amps per connector. Equipment grounds need to be tested for proper resistance value.

1.4 GOVERNMENT INSPECTOR

The Base Civil Engineer, or his authorized representative, is designated as the representative of the Contracting Officer for the purpose of technical surveillance of workmanship and inspection of materials for work being performed under this contract. This clause does not authorize anyone other than the Contracting Officer to commit the Government to changes in the terms of the contract.

1.5 ORAL STATEMENTS

No oral statement by any government official shall in any manner or degrees modify or otherwise affect the terms of this contract.

1.6 NO GOVERNMENT WAIVER

The failure of the Government in any one or more instances to insist upon strict performance to any of the terms of this contract or to exercise any option herein conferred will not be construed as a waiver or relinquishment to any extent of the right to assert or rely upon such terms or option on any future occasion.

1.7 AS-BUILT RECORDS

1.7.1 As-Built Drawings

Maintain at the jobsite 2 sets of full-size contract drawings. Any deviations from the contract drawings shall be marked legibly and accurately with a red pen. These drawings shall be available for review by the Contracting Officer at all times. Submit one marked set of prints to the Contracting Officer no later than 30 calendar days after work is deemed substantially performed or beneficial occupancy is taken.

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION

3.1 BASE REGULATIONS

The Contractor and his employees and subcontractor shall become familiar with and obey all base regulations, including fire, traffic, airfield, safety, environmental, and security regulations. Regulations are available upon request. All personnel employed on subject contract shall keep within the limits of the work and avenues of ingress and egress. Do not enter any restricted areas unless previously cleared for such entry. The Contractor's equipment shall be conspicuously marked for identification.

3.2 WORK SCHEDULE

The Contractor shall schedule his work to cause the least amount of interference with base

SECTION 010100 Page 3 operations. Work schedules shall be subject to the approval of the Contracting Officer.

Under no circumstances shall fire water system be out of service for more than 5 calendar days. Permission to interrupt any base roads and/or utility service shall be requested in writing a minimum of 10 calendar days prior to the desired date of interruption.

Interruption shall not take place without specific approval from the Contracting Officer.

3.2.1 Construction phasing

Thirty (30) days prior to commencing work, provide to the Contracting Officer, for approval, a plan, which indicates the Timeline of start to completion of each construction phase.

3.3 WORK HOURS

The normal hours of work for the performance of this contract will be from 7:30 AM to 5:00

PM except as otherwise expressly provided in this contract. The workdays will be Monday through Friday, with Federal holidays excluded. Alternate work hours require written permission of the Contracting Officer. The contractor must submit a written request for permission to work to the Contracting Officer at least 2 working days in advance of the date when the contractor desires to deviate from the normal hours and days. Permission to deviate will be predicated on complete justification for the request after due consideration to a larger work force and more equipment during normal hours, and providing the contractor defrays the additional costs to the Government including, but not limited to, inspection computed in accordance with existing Government regulations. If permission is granted by the Contracting Officer, written authority will be furnished to the contractor prior to the date the contractor desires to deviate from the normal hours or days. The Contracting Officer may also direct performance as authorized by the General

Provisions by reference clause entitled “Schedule for Construction Contract.”

3.4 OPERATIONS ON THE AIRFIELD

Special requirements and guidelines will have to be adhered to for sites located behind the Flight-line fence. Coordinate specific requirements with the Contracting Officer

Representative and Airfield Manager prior to beginning work. Requirements and coordination items may include, but are not limited to: airfield driving, FAA waivers, and airfield operations waivers.

3.5 EXISTING WORK

The removal or altering in any way of existing work shall be carried on in such a manner as to prevent personal injury or damage to any portions of the existing work that remains.

3.6 SANITATION

Adequate sanitary conveniences of a type approved for use by persons employed on the work shall be provided. Sanitary conveniences shall be properly secluded from public observation, and maintained by the Contractor in such a manner as required or approved by the Contracting Officer. Maintain these conveniences at all times without nuisance. Upon completion of the work, the contractor shall remove the conveniences from the premises, leaving the premises clean and free from nuisance.

3.7 UTILITIES

All reasonable quantities of government provided utilities shall be made available to the contractor without charge. Any temporary telephone service shall be requested by the contractor from the local Telephone Company providing service to Dobbins ARB. The contractor shall not tamper with, connect or access any Government communication facility, equipment or cable without express written consent from the Contracting Officer. Any temporary connections or lines that may be required shall be installed, maintained, and

SECTION 010100 Page 4 removed by the Contractor at his expense and in a manner satisfactory to the Contracting

Officer. Contractor shall remove all temporary connections and lines prior to final acceptance of the construction.

3.8 UTILITY SERVICE INTERRUPTION

The Government shall not be held responsible for interruptions of utility services and shall not be liable for Contractor delays, damages, or increased costs occasioned by any such interruption of services.

3.9 OPTIONAL REQUIREMENTS

Where a choice of materials or methods, or both, is permitted in this contract, the

Contractor will be given the right to exercise the option unless otherwise required by the specification or plans.

3.10 MATERIAL APPROVAL SUBMITTAL PREPARATION

"Material and Workmanship" shall be accomplished on and in accordance with the instructions to AF Form 3000, Material Approval Submittal. Material Approval Submittals shall contain complete information for the product proposed. The information shall be in enough detail to allow the Government to determine acceptability. Information to be provided includes, but is not limited to: a description of all salient features of the product, descriptive literature and manufacturer's cut sheet (if available), plus an explanation as to precisely why and how the material or item submitted meets or exceeds all required functions, performance and quality specifications.

3.11 MATERIAL DISPOSITION

3.11.1 Material/Equipment Title

Title to materials and equipment to be demolished, except Government salvage and historical items, is vested in the Contractor upon receipt of notice to proceed. The Government will not be responsible for the condition, loss or damage to such property after notice to proceed.

3.11.2 Contractor Salvage

Contractor shall salvage items and materials to the maximum extent possible. Material salvaged for the Contractor shall be stored as approved by the Contracting Officer and removed from Government property before completion of the contract. The contractor shall not sell salvaged material on the site.

3.12 CLEAN-UP & SPILL RESPONSE

Remove and transport debris in a manner that prevents spillage on streets or adjacent areas.

Local regulations regarding hauling and disposal shall apply. The contractor shall maintain a clean and orderly work site.

The contractor is required to have spill response materials and the capability to properly respond to the any spills caused during the course of this work.

3.13 SAFETY REQUIREMENTS

The contractor shall initiate and maintain programs that comply with the provisions of 29

CFR parts 1926 and 1910 of the Occupational Safety and Health Standards. These programs shall include the education and training of employees and subcontractors’ personnel in the recognition, avoidance, and prevention of unsafe conditions and practices.

SECTION 010100 Page 5

3.14 FIRE PROTECTION

The contractor shall be responsible for furnishing adequate and proper fire protection during all phases of work on site. Contact the base Fire Department in the event of emergency.

3.15 FACILITIES AND SERVICES

The contractor is responsible for storage of all materials. Storage areas shall be shown on the site plan and approved by the Contracting Officer.

3.16 RESTRICTIONS

3.16.1 Radio Transmitter Restrictions

The contractor shall conform to the restrictions and procedures for the use of radio transmitting equipment, as directed. Two transmitters shall be provided by the government to the contractor for use during construction.

3.16.2 Materials Burning

Burning of trash, timber and any other debris on government property is not permitted.

3.17 REQUIRED CONTRACTOR ACTIONS

3.17.1 Base Permits

Obtain these pursuant to paragraph 3.1 of this specification. Permits are required for, but are not necessarily limited to, welding, and digging. Airfield waivers will be required for sites located behind the Flight-line fence. Coordinate specific requirements for these waivers with the Contracting Officer.

3.17.1.1 Government Digging Permits

The requirement for digging or excavation permits (AF Form 103) shall be applicable for

Government-owned utilities such as water, gas, electrical, sewer, fiber optics, telephone cable and communication cables for radar, weather and navigational aids cable.

3.17.1.1.1 Procedures for Government Digging Permits

Contractor shall not dig or penetrate the grade anywhere on Dobbins ARB without a government approved, signed AF Form 103, Dig Permit. It is the contractor’s responsibility to initiate and renew the dig permit as required for the construction location.

Contractor initiates the dig permit process by contacting Georgia 811. Contractor should coordinate with the Contracting Officer Representative (COR) for proper procedures.

Contractor shall mark the area on site where digging is to occur. This shall be done the same day the dig permit is initiated. Utility locator’s have 14 days to sign the initial digging permit.

Contractor shall maintain all markings during construction performance period.

Contractor will maintain a signed copy of AF Form 103, Dig Permit, on site during digging.

If, during the life of the digging permit, utility markings are removed by the contractor or his subcontractor the contractor shall be responsible for replacing all markings.

SECTION 010100 Page 6

3.17.1.2 UPC Digging Permits

The procedures set forth for Government-owned utilities shall not apply to utilities which are governed by the Utilities Protection Center (UPC) under the auspices of the State of

Georgia. UPC utilities on Dobbins ARB include television cable, telephone cables, data cables, etc. Procedures for utilities governed by the UPC shall be followed in accordance with Georgia Utility Facility Protection Act (GUFPA). The contractor is required to obtain a UPC digging permit prior to digging on Dobbins ARB. The government is not responsible for issuing or monitoring UPC digging permits.

3.17.1.3 Utility Damage

The Contractor must immediately notify the Government technical representative and UPC in the event that utility damage occurs. If damage to utilities is due to contractor non-compliance with permit instructions or contract requirements, repairs required shall be at the contractor’s expense. Fiber optic cables, which cannot be repaired to meet the minimum allowable decibels, will be replaced at the contractor’s expense.

3.17.1.4 Welding Permits

Obtain welding permits on a daily basis from the Base Fire Department.

3.17.2 Severe Weather Protection

In the event of severe weather, the contractor shall take precautions to minimize any danger to persons, and protect the work and any nearby Government property. Precautions shall include, but are not limited to, closing openings; removing loose materials, tools and equipment from exposed locations; and removing or securing scaffolding and other temporary work.

3.17.3 Clean Tire Policy

Dobbins ARB has a clean tire policy at work sites. The purpose of this policy is to reduce or eliminate the transport of mud from the work area onto public rights-of-way by motor vehicles leaving the site or by runoff from the site. Clean and remove mud from the wheels of vehicles prior to entrance to public rights-of-way. The site exit shall be maintained in order to prevent tracking or flow of mud onto public rights-of-way. Immediately remove all materials spilled, dropped, washed or tracked from any vehicle or site onto any roadway or into any storm drain. Compliance with the clean tire policy, by Contractor and Sub-contractor personnel, shall be the sole responsibility of the Contractor.

3.17.4 Erosion and Sediment Control

Take positive steps to minimize siltation and erosion during the work. Comply with the requirements of Section 015600, drawings and all other related specification sections. The contractor must submit a completed Erosion, Sedimentation, and Pollution Control Plan (form attached behind this specification) to the DARB COR prior to beginning work. The contractor must use GA SWCC Best Management Practices (BMPs) and these BMPs will need to be installed prior to any clearing or grubbing.

3.17.5 Environmental Requirements

The Contractor and all work to be performed on Dobbins ARB shall comply with the requirements of Section 01 56 00.

SECTION 010100 Page 7

3.17.6 Quality Control Plan

The contractor shall be required to institute a comprehensive Quality Control Program in order to assure himself and the Government that all materials and workmanship are in strict accordance with the provisions of the specifications. Within 10 calendar days after receipt of Notice to Proceed, the contractor shall submit his Quality Control Program Plan to the

Contracting Officer for review and approval. The plan shall contain, at a minimum, identification of procedures for quality control, the type and model of major pieces of equipment to be used on-the-job, ordering procedures for materials, and procedures to ensure adequate progress.

3.17.7 Hazardous Spill Reporting

The contractor shall report any spill of oil or hazardous substances to the Fire

Department service desk at Ext. 911 from a government phone, or (678) 655-4840 from a commercial phone (24 hours per day, 7 days per week). The contractor shall take every reasonable precaution to prevent the spillage of oil or other hazardous substances.

3.18 DD FORM 1354

Completion of a DD1354 Package is required for this project. A separate DD1354 form will be required for each site. Copies of the DD1354 form and its instructions are included in the project manual. Electronic copies will be available from the COR. Follow the instructions given for executing the DD1354 and coordinate it’s submission with the COR.

-- End of General Requirements --

Dobbins ARB - Replace/Study/Add Generators at Facilities DOBBINSGENS

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

08/15

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

View Location Map; G

Progress and Completion Pictures; G

1.3 VIEW LOCATION MAP

Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.

1.4 PROGRESS AND COMPLETION PICTURES

Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten views from points located by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures. Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file. Include a date designator in file names. Cross reference submittals in the appropriate daily report. Photographs

SECTION 01 30 00 Page 1 provided are for unrestricted use by the Government.

1.5 MINIMUM INSURANCE REQUIREMENTS

Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by law.

1.6 FIRST TIER CONTRACTOR REQUIREMENTS FOR ASBESTOS CONTAINING MATERIALS

Accomplish all contract requirements of Section assigned to the directly with a first tier subcontractor.

1.7 SUPERVISION

1.7.1 Minimum Communication Requirements

Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of contract work. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication skills.

1.7.2 Superintendent Qualifications

The project superintendent must have a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

1.7.2.1 Duties

The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.

The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.

1.7.3 Non-Compliance Actions

The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion.

Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

SECTION 01 30 00 Page 2

1.8 PRECONSTRUCTION

After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work must also attend. All pre-construction submittals must be submitted and approved prior to the commencement of any work on site.

1.9 PARTNERING

To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government, the Contractor and their Subcontractors. Key personnel from the Supported Command, the End User (who will occupy the facility), the Government Design and Construction team and Subject Matter Experts, the Installation, the Contractor and Subcontractors, and the Designer of Record will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in an effort to achieve a project that is without any safety mishaps, conforms to the Contract, and stays within budget and on schedule.

The Contracting Officer will provide Information on the Partnering Process and a list of key and optional personnel who should attend the Partnering meeting.

1.10 ELECTRONIC MAIL (E-MAIL) ADDRESS

Establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 days after contract award, provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats. Multiple email addresses are not allowed.

It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of any changes to this email address.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

SECTION 01 30 00 Page 3

SECTION 013300 Page 1

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 REFERENCES: (NOT USED)

1.2 DEFINITIONS

1.2.1 Submittal Definition, Shop drawings, product data, samples, administrative and closeout submittals, and additional data presented for review and approval by the

Government.

1.3 SUBMITTAL TYPES

1.3.1Material Submittals

Submittals for which review and approval will be made to ensure that the materials installed and process used for installation are in compliance with the design concept and contract documents. These include, but are not limited to, those items shown in paragraph 1.8 of this section. The following are examples of material approval data items:

a. Shop Drawings: As used in this Section, drawings, schedules, diagrams, and other data prepared specifically for this Contract, by the Contractor or through the Contractor by way of a subcontractor, manufacturer, supplier, distributor, or other lower tier contractor, to illustrate a portion of the work. Types are as listed in the paragraph 1.8, entitled "Schedule of Submittal Descriptions (SD)."

b. Product Data: Preprinted material such as illustrations, standard schedules, performance charts, instructions, brochures, diagrams, manufacturer's descriptive literature, catalog data, and other data to illustrate a portion of the work, but not prepared exclusively for this Contract. Types are as listed in the paragraph 1.8, entitled "Schedule of Submittal Descriptions (SD)."

c. Samples: Physical examples of products, materials, equipment, assemblies, or workmanship, physically identical to a portion of the work, illustrating a portion of the work or establishing standards for evaluating the appearance of the finished work or both. Types are as listed in the paragraph 1.8, entitled "Schedule of Submittal Descriptions (SD)."

NOTE: USE THE ATTACHED MINIMUM SUBMITTALS (File Name: AF Form 66 for 01 56 00 spec. Add additional rows to this spreadsheet for required submittals.}

1.3.2 Administrative and Closeout Submittals

Submittals of data for which review and approval will be to ensure that the administrative requirements of the contract are adequately met but not to ensure directly that the work is in accordance with the design concept and in compliance with the Contract documents. Submittals of this type include, but are not limited to, those items shown in paragraph 1.8 of this section.

SECTION 013300 Page 2

1.3.3 Approving Authority

The approving authority for all submittals shall be the Contracting Officer.

1.3.4 Work

As used in this Section, the construction required by the Contract documents, including labor necessary to produce the construction and materials, products, equipment, and systems incorporated or to be incorporated in such construction and including materials, products, equipment, and systems produced both on and off-site.

1.4 SUBMITTAL CLASSIFICATION

1.4.1 Government Approved (G)

Government approval is required for extensions of design, critical materials, variations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Government.

Government approval is required for any variations from the Solicitation or the

Accepted Proposal and for other items as designated by the Government.

Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, submittals are considered to be "shop drawings."

1.4.2 For Information Only

Submittals not requiring Government approval are classified as for information only.

Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are not considered to be "shop drawings." These submittals still have to be submitted to the Government but they are not subject to Government review.

1.5 PROCEDURES FOR ADMINISTRATIVE AND CLOSEOUT SUBMITTALS

1.5.1 Administrative and closeout submittals shall be provided as the work progresses in accordance with the time frames established within the contract for each item. Should a delivery date fall on a weekend or a holiday, the submittal shall be due the next working day thereafter.

1.5.2 Unless otherwise stated, the Government shall have fifteen (15) working days for review and acceptance of each administrative/closeout submittal.

1.5.3 All administrative/closeout submittals shall be submitted by letter to the

Contracting Officer. The format shall be as specified for each item at the point in the contract which establishes the requirement. If a format and applicable forms are not specified, the submittal may be made on 8 1/2" by 11" plain bond paper, double-sided. The item shall be neatly and legibly handwritten or typed.

1.5.4 Warranties and operating instructions are required at the completion of the contract work and shall be submitted no later than thirty (30) calendar days after work is deemed to be substantially performed or beneficial occupancy is taken. Four copies of all warranties and operating instructions shall be provided unless otherwise specified. The Government shall have thirty(30) calendar days for review and acceptance. Operation and maintenance manual data also shall include components required in the various technical sections of this specification.

SECTION 013300 Page 3

1.5.5 With the exception of as-built drawings, drawings included in an administrative or closeout submittal shall conform to the requirements of paragraph 1.8.3 of this section.

1.5.6 Unless otherwise stated, administrative and closeout submittals shall be submitted in quantities of four, one original and three copies.

1.6 PROCEDURES FOR MATERIAL SUBMITTALS

1.6.1 Limits and Constraints Regarding Material Submittals

a. Submittals shall be complete for each portion of the work; components of the work interrelated as a system shall be submitted at the same time.

b. When submittal acceptability is dependent on conditions, items, or materials included in separate subsequent submittals, the submittal will be returned without review.

c. Submittals of information not required as a submittal, or covering work for which the submittals have been returned as "approved" or "approved as noted," will be returned without review.

d. Approval of a separate material, product, or component does not imply approval of assembly in which the item functions.

e. The work shall conform to approved submittals as approved. In the event a previously approved submittal has an error or omission, the contractor shall revise the submittal and resubmit for approval. Government review, corrections or comments made on submittals do not relieve the contractor from compliance with the requirements of the drawings, specifications, addendums and contract documents. The government reserves the right to seek equitable compensation if submittals containing unnoted deviations are approved.

f. Approval of a submittal by the Contracting Officer shall not relieve the Contractor from the responsibility to provide materials which comply with project specifications.

g. All material submittals must be submitted on an AF Form 3000, entitled Material Approval's submittal.

Review of submittals by the government will not be construed as a complete check, but indicates only that the submittals are in general conformance with the design concept and with the information given in the Contract

Documents. This approval shall not relieve the contractor from responsibility for errors and omissions.

1.6.2 Scheduling of Material Submittals - SUBMITTAL REGISTER (AF FORM 66)

a. Material submittals requiring government review and/or approval are defined in each section of the specification. AF Form 66 contains a listing of items of equipment and materials for which submittals are required by the specifications; this list may not be all inclusive and additional submittals may be required. The contractor shall complete and submit the forms to the Contracting Officer for approval within 15 calendar days after Notice-to- Proceed or at the direction of the Contracting Officer. The approved submittal register will become the scheduling document and will be used to control submittals throughout the life of the contract. The submittal register and the progress schedule shall be coordinated. The Contractor shall carefully control his/her procurement operations to ensure that each

SECTION 013300 Page 4 individual submittal is made on or before the Contract scheduled submittal date shown on the approved “Submittal Register.” Approval must be obtained from the

Contracting Officer before the Contractor initiates any work for which material submittals are required. Submittals for critical items or long lead items shall be submitted individually to expedite processing.

c. The Contractor shall coordinate preparation and processing of submittals with performance of the work so that work will not be delayed by submittal processing. Also, coordinate and sequence different categories of submittals for same work and for interfacing units of work, so that one will not be delayed by coordination with another.

d. Except as otherwise specified, the Government will have fifteen (15) working days, beginning with receipt by the Contracting Officer, for review and approval of each material submittal. The period of review is the same for both the submittal and resubmittal.

e. For submittals requiring approval by the Fire Protection Engineer, the Government shall have, beginning with receipt by the Contracting Officer, 30 calendar days for review and approval of the submittal. The period of review is the same for both the submittal and resubmittal.

f. Resubmittals for disapproved items shall be made within the time specified on the AF Form 3000 by the Contracting Officer.

1.6.3 Contractor Responsibilities

a. Determine and verify field measurements, materials, field construction criteria; review each submittal; and check and coordinate each submittal with requirements of the work and Contract documents.

b. Ensure that material is clear and legible. Ensure required specialty stamps are affixed and signed.

c. Stamp each sheet of each submittal with the Contractor's certificating stamp, except that data submitted in bound volume or on one sheet printed on two sides may be stamped on the front of the first sheet only. Word the submittal stamp as follows:

"I hereby certify that the (equipment) (material) (article) shown and marked in this submittal is that proposed to be incorporated into Project Number

_, , is in compliance with the Contract drawings and specifications, can be installed in the allocated spaces, and is submitted for Government approval.

Certified by Date "

Note that this certification shall be placed on data attached to the AF Form

3000, not the AF Form 3000 itself.

d. Sign the Contractor's certification. The person signing the certification shall be one designated in writing by the Contractor as having that authority. The signature shall be in original ink. Stamped signatures are not acceptable.

e. Transmit submittals to the Contracting Officer in orderly sequence, to prevent project delays and delays in work by the Government or separate contractors.

SECTION 013300 Page 5

f. Proposed deviations from the contract requirements shall be clearly identified. Advise the Contracting Officer of submittals which include a proposed deviation requested by the Contractor, the reason for deviation shall be annotated on the submittal. The notification shall be inserted directly under the AF Form 3000 and shall clearly state that the submittal includes deviations from the specifications and drawings. Government review, corrections or comments made on submittals do not relieve the contractor from compliance with the requirements of the drawings, specifications, addendums and contract documents. The government reserves the right to seek equitable compensation if submittals containing unnoted deviations are approved

g. Correct and resubmit submittal as directed by the Contracting Officer. Direct specific attention, in writing or on resubmitted submittal, to revisions not requested by the Contracting Officer on previous submissions.

h. Retain a copy of approved submittals at the project site, including the Contractor's copy of approved samples.

i. Furnish additional copies of submittals if requested by Contracting Officer, limit of 5.

j. Ensure no work is begun until the submittals for that work have been returned as "approved" or "approved as noted," except to the extent that a portion of the work must be accomplished as a basis of the submittal.

k. If an “or equal” product is submitted for approval, the contractor shall identify in the submittal what features are the same as the brand name product and what differences exist between the equal product and the brand name product.

1.6.4 Approving Authority's Responsibilities

a. Submittals will be reviewed for approval with reasonable promptness and only for conformance with project design concepts and compliance with the Contract documents.

b. Submittals will be returned with one of the following notations:

(1) Submittals marked "approved" or "approved as submitted" authorize the Contractor to proceed with the work covered.

(2) Submittals marked "approved as noted" authorize the Contractor to proceed with the work as noted provided the Contractor takes no exception to the notations and complies with all notations.

(3) Submittals marked "disapproved" indicate the submittal does not comply with the design concept or the requirements of the Contract documents and shall be resubmitted with appropriate changes.

1.7 FORMAT AND QUANTITY OF MATERIAL SUBMITTALS

1.7.1 Transmittal Form

Use of Transmittal Form AF Form 3000 is required. Transmit each submittal, except sample installations and sample panels, to the office of the Contracting Officer.

1.7.2 Identifying Submittals

Identify submittals, except sample panel and sample installation, with the

SECTION 013300 Page 6 following information permanently adhered to or noted on each separate component of each submittal and noted on the transmittal form. Mark each copy of each submittal identically, with the following:

a. Project title and location.

b. Construction Contract number.

c. The Section and Paragraph number of the Specification Section in which the submittal is required.

d. Submittal number - Submittals shall be numbered sequentially by date submitted including re-submittals. Each submittal number shall be unique. A resubmittal shall be numbered in sequence as though an original submittal and shall include a reference to the submittal number for which the resubmittal is being made.

e. The name, address, and telephone number of the subcontractor, supplier, manufacturer and any other second tier contractor associated with the submittal.

f. Product identification and location in project.

g. All submitted documents or files pertaining to a certain item needs to reference the section and paragraph number in the file or document title.

Identify within the document by circling or highlighting all the requirements showing that it meets the specification and which item number it refers to.

1.7.3 Format and Quantity for Shop Drawings

a. For shop drawings presented on sheets larger than 8 1/2-inches by 14 inches, submit one reproducible and three prints of each required shop drawing prepared for this project.

(1) Transmit re-producibles rolled in mailing tubes.

(2) Include on each drawing the drawing title, number, date, and revision numbers and dates, in addition to the information "Identifying Submittals."

(3) After review, the approving authority will retain the prints and return only the reproducible with notation resulting from the review.

b. For shop drawings presented on sheets 8 1/2-inches by 14 inches or less, conform to the format and quantity requirements for product data, and present as a part of the bound volume for the submittals required by the Section.

c. Dimension drawings, except diagrams and schematic drawings; prepare dimensioned drawings to scale. Identify materials and products for work shown.

d. Shop drawings shall be not less than 8 1/2 by 11 inches nor more than 30 by 42 inches.

1.7.4 Format and Quantity for Product Data

a. Submit 3 copies of submittals of product data.

SECTION 013300 Page 7

b. Present product data submittals for each Section as a complete, bound volume. Include a table of contents listing page and catalog item numbers for product data.

c. Indicate, by prominent notation, each product which is being submitted;

indicate the Section and paragraph numbers to which it pertains.

d. Supplement product data with material prepared for the project to satisfy submittal requirements for which product data does not exist. Note that the material is developed specifically for the project.

1.7.5 Format and Quantity of Samples

a. Furnish samples in the sizes below, unless otherwise specified or unless the manufacturer has prepackaged samples of approximately the same size as specified:

(1) Sample of equipment or device: Full size.

(2) Sample of materials less than 2 by 3 inches: Built up to 8 1/2 by

11 inches.

(3) Sample of materials exceeding 8 1/2 by 11 inches: Cut down to 8

1/2 by 11 inches and adequate to indicate color, texture, and material variations.

(4) Sample of linear devices or materials, such as, conduit and handrails: 10-inch length or length to be supplied, if less than 10 inches.

(5) Sample of non-solid materials, such as, sand and paint.

(6) Color selection samples: 2 inches by 4 inches.

(7) Sample panel: 4 feet by 4 feet.

(8) Sample Installation: 100 square feet.

b. Samples showing range of variation: Where variations are unavoidable due to the nature of the materials, submit sets of samples of not less than three units showing the extremes and middle of the range.

c. Quantity, unless otherwise specified:

(1) Submit two samples, or two sets of samples showing range of variation, of each required item. One approved sample or set of samples will be retained by the approving authority and one will be returned to the Contractor.

(2) Submit one sample panel. include components listed in technical section, as required by specifications.

(3) Submit one sample installation, as required by specifications.

(4) Submit one sample of non-solid materials, as required by specifications.

d. Recording of sample installation: Note and preserve the notation of the area constituting the sample installation but remove the notation at

SECTION 013300 Page 8 the final clean up of the project.

e. When a color, texture or pattern is specified in naming a particular manufacturer and style, include one sample of that manufacturer and style, for comparison.

1.8 SCHEDULE OF SUBMITTAL DESCRIPTIONS

(SD) SD-AA, Progress Schedule

Schedule for performance of work for the project, Contract Progress Schedule. (A type of administrative or closeout submittal.)

SD-BB, Progress Reports

Bi-weekly progress reports on work completed, Progress Report. ( A type of administrative or closeout submittal.) SD-01, Data

Submittals which provide calculations, descriptions, or documentation regarding the work.

SD-01 Preconstruction Submittals

Submittals that are required prior to or commencing with the start of work on site. Submittals that are required prior to or at the start of construction

(work) or the next major phase of the construction on a multiphase contract. No demolition, construction, or any other type of work can start on the site until all pre-construction submittals have been approved.

Preconstruction Submittals include schedules and a tabular list of locations, features, and other pertinent information regarding products, materials, equipment, or components to be used in the work.

Certificates Of Insurance

Surety Bonds

List Of Proposed Subcontractors

List Of Proposed Products

Baseline Network Analysis Schedule (NAS)

Submittal Register

Schedule Of Prices Or Earned Value Report

Accident Prevention PlanHealth And Safety Plan

Work Plan

Quality Control (QC) plan

Environmental Protection Plan

SD-02 Shop Drawings

Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.

SECTION 013300 Page 9

Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.

Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.

SD-03 Product Data

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.

Samples of warranty language when the contract requires extended product warranties.

SD-04 Samples

Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.

Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.

Field samples and mock-ups constructed on the project site establish standards ensuring work can be judged. Includes assemblies or portions of assemblies that are to be incorporated into the project and those that will be removed at conclusion of the work.

SD-05 Design Data

Design calculations, mix designs, analyses or other data pertaining to a part of work.

Design submittals, design substantiation submittals and extensions of design submittals.

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.

Report that includes findings of a test required to be performed on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report that includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

Investigation reports

SECTION 013300 Page 10

Daily logs and checklists

Final acceptance test and operational test procedure

SD-07 Certificates

Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.

Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.

Confined space entry permits

Text of posted…