This document contains details regarding a federal contract solicitation for repair work on an airfield parking ramp. The scope of work involves milling and overlaying 15 parking spots, installing new pavement striping, sealing joints, and conducting concrete repairs. A pre-proposal site visit will be held on July 7th, 2020 at 9:00 AM EST at the Joint Base Charleston Air Base Visitor Control Center, where government transportation will be provided to the project site. All questions regarding the solicitation are due by July 10th, 2020 at 12:00 PM EST. The total performance time outlined for the project is 230 calendar days, with 140 days allocated for construction and weather delays. Liquidated damages will be calculated based on the 140-day construction requirement. The soliciting agency is the Department of the Air Force Air Mobility Command.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Time (Calendar Days)

Mobilization & Submittal Preparation – 60 days

Construction Days – 119 days

Inclement Weather During Construction Days – 21 days

Closeout – 30 Days

Total Performance Time: 230 Days

(Note that the total construction time including weather delays is 140 days.

Liquidated Damages will be calculated relative to this 140-day requirement.)