Attach 1 - PTS Kramatorsk 3 projects.pdf

PDF 8 MB Posted

Attached to
D-B Renovate Kindergarten, Hospital, and School in Kramatorsk, Ukraine
Solicitation number
N3319121R4007
Issued by

About this file

This solicitation is for a design-build contract to renovate a kindergarten, hospital, and school in Kramatorsk, Ukraine. The scope of work includes a complete reconstruction of the kindergarten building, construction of a new ambulance entrance and canopy at the hospital, and renovations to the dining room, food distribution room, and classrooms at the school. The base bid includes work at all three sites, while there is an optional contract line item to add a playground, canopy, fencing, and landscaping at the kindergarten. The Navy is the contracting agency, with a response due date of January 15, 2022 and period of performance expected to last one year. Offerors must visit the sites and are responsible for all design work and obtaining necessary permits to complete the renovations in accordance with Ukrainian regulations.

View the file

Other files

File Type Posted
N3319121R4007 Amendment 0002.pdf PDF
N3319121R4007 Amendment 0001.pdf PDF
Attach 8 - PPQ.docx DOCX document
Attach 3 - Price Schedule.doc DOC document
N3319121R4007 Solicitation.pdf PDF
Attach 6 - Contract Data Sheet.docx DOCX document
Attach 7 - Safety Checklist.docx DOCX document
Attach 2 - PPI.docx DOCX document
Attach 5 - Clause 252.229-7001.docx DOCX document
Attach 4 - Provision 52.204-26.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Kindergarten#89, Hospital#02, School#22 OHASIS ID-39193, 39196, 39198 Kramatorsk - Ukraine

VERSION-005

EUCOM Humanitarian Assistance Program

KRAMATORSK DESIGN/BUILD

Kindergarten#89 Full Renovation

Hospital#2 Ambulance Shelter and Entrance School#22 Dining Room Repairs

Ukraine

Kramatorsk, Ukraine OHASIS UP-HA-2020-39193, 39196 and 39198

Dec 2020 (Ver005)

Contents

1. TAXATION

2. GENERAL DESCRIPTION OF THE CONTRACT

2.1. GENERAL DESCRIPTION OF WORK

2.2. LOCATION OF KRAMATORSK – SAFETY ZONE

2.3. LEGAL AND TECHNICAL REQUIREMENTS

2.4. GENERAL CONTRACT DESCRIPTION

2.5. CONSTRUCTION PERMIT OR AUTHORIZATION

2.6. MEASUREMENTS AND QUANTITIES

2.7. CONSTRUCTION PHASE - GENERAL

3. CLIN0001 - DETAILED SCOPE OF WORK OF BASE-BID IN KINDERGARTEN#89

3.1. EXISTING KINDERGARTEN FACILITY

3.2. GENERAL SCOPE OF WORK

3.3. DEMOLITIONS

3.4. DEMOLITION OF ENTRANCE LOOBY

3.5. HIDRO INSULATION OF THE FOUNDATIONS

3.6. THERMALLY INSULATED FAÇADE AND SIDEWALKS

3.7. EXTERIOR LIGHTING

3.8. BALCONIES AND EMERGENCY EXITS FROM SECOND FLOOR

3.9. EXTERIOR WINDOWS

3.10. EXTERIOR DOORS

3.11. ROOF AND ROOF INSULATION

3.12. SCAFFOLDING – MANLIFTS – HARNESS – FALL PROTECTION

3.13. PICTURES TO CLARIFY THE EXTERIOR SCOPE OF WORK

3.14. FLOORS

3.15. WALLS

3.16. INTERIOR DOORS

3.17. CEILINGS

3.18. WATER LINES – HOT WATER

3.19. SEWER CONNECTION, SEWAGE INSTALLATION AND VENT PIPING

3.20. ELECTRICAL INSTALLATIONS

3.21. LIGHTING – LED TECHNOLOGY

3.22. TELEPHONE / INTERNET

3.23. FIRE ALARM

3.24. HEATING

3.25. AIR CONDITIONING (HEAT PUMP) IN TWO ROOMS

3.26. SPECIFIC REQUIREMENTS - BATHROOM FOR CHILDREN

3.27. SPECIFIC REQUIREMENTS - BATHROOM FOR ADULT - WHEELCHAIR

3.28. SPECIFIC REQUIREMENTS - STAIRWAYS

3.29. SPECIFIC REQUIREMENTS – MULTIPURPOSE ROOM

3.30. SPECIFIC REQUIREMENTS – ENTRANCE CHANGING ROOM

3.31. SPECIFIC REQUIREMENTS - STORAGE

3.32. SPECIFIC REQUIREMENTS - KITCHENETTES

3.33. PICTURES TO CLARIFY THE INTERNAL SCOPE OF WORKS

3.34. COMMEMORATIVE PLAQUE

4. CLIN0002 - DETAILED SCOPE OF WORK OF BASE-BID IN HOSPITAL#02

4.1. CONCEPT DESIGN

4.2. RENOVATION OF THE ENTRANCE ROOM

4.3. NEW PAVEMENT (MIN 250 M²)

4.4. PROTECTION FROM RAIN AND SNOW – AMBULANCE CANOPY (MIN 140 M²)

4.5. PICTURES TO CLARIFY THE SCOPE OF WORK IN HOSPITAL#02

5. CLIN0003 - DETAILED SCOPE OF WORK OF BASE-BID IN SCHOOL#22

5.1. DINING ROOM, ACCESS HALLWAY AND FOOD DISTRIBUTION ROOM

5.1.1. SPECIFIC REQUIREMENTS: FOOD DISTRIBUTION ROOM

5.1.2. SPECIFIC REQUIREMENTS: HAND WASHING AREA

5.2. ENGLISH LANGUAGE CLASSROOMS

5.3. PICTURES TO CLARIFY THE SCOPE OF WORK IN SCHOOL#22

6. CLIN0004 - DETAILED SOW OF CONTRACT OPTION-1 IN KINDERGARTEN#89

6.1. EXTERIOR CANOPY (MIN 200 M²)

6.2. PLAYGROUND AREA (11 X 16 M)

6.3. FENCE (280 METERS)

6.4. CLEANING/GRADING THE PLOT OF LAND

7. PROCEDURE AND GENERAL CONTRACT REQUIREMENTS AND GUIDELINES

7.1. PRINCIPLES

7.2. PROHIBITED ITEMS

7.3. PERMIT/AUTHORIZATIONS BEFORE AND DURING CONSTRUCTION

7.4. START OF CONSTRUCTION

7.5. RESPONSIBILITY FOR NEW MATERIALS

7.6. DESIGN

7.7. DESIGN-BUILD PROCEDURE

7.8. CONSTRUCTION/DESIGN SCHEDULE AND CONTRACTUAL MILESTONES

7.9. CONSTRUCTION SCHEDULE (BAR CHART IS AUTHORIZED)

7.10. SAFETY: ACCIDENT PREVENTION PLAN

7.11. SPECIAL SITE CONDITIONS

7.12. PHASING AND COORDINATION

7.13. LANGUAGE

7.14. SUBMITTALS – TECHNICAL INFORMATION

7.15. DELIVERABLE

7.16. RESPONSIBILITY AND OWNERSHIP OF REMOVED MATERIALS

7.17. PICTURES

7.18. CERTIFICATIONS, LICENSES, PERMITS, FEES, ETC

7.19. QUALITY CONTROL PLAN

7.20. CONSTRUCTION SIGN (3 UNITS)

7.21. PAYMENT

7.22. SCHEDULE OF PRICES

7.23. DAMAGES/IMPACT TO EXISTING FACILITIES

7.24. CLEANING

7.25. SPARE PARTS

7.26. WARRANTY AND TRAINING

7.27. CLOSE-OUT PROCEDURE

-/-/-/-/-/-/-/- END OF TECHNICAL SPECIFICATION -/-/-/-/-/-/-/-/-

1. TAXATION

In Accordance with Article 1 of the "Agreement Between the Government of Ukraine and the Government of the United States of America Regarding Humanitarian and Technical Economic Cooperation" prepared on 7 May 1992, regarding "Taxes and Other Charges", this project which is in connection with the United States assistance program, shall be free from any tariffs, dues, custom duties, import taxes and other similar taxes or charges imposed by Ukraine, or any subdivision thereof.

As such, this project will be awarded exempt from VAT taxes, and consequently the US Government will not pay any VAT taxes to the successful company who will get the award of the contract.

It shall be the contractor's responsibility to work directly with Ukrainian fiscal authorities on the implementation of the applicable tax exemption applicable for this assistance program. The Office of Defense Cooperation in Ukraine will provide the documents that may be requested by the contractor to certify that they are the company selected by the US Government to execute the necessary design and construction works included in this assistance contract. However, it is solely the contractor's responsibility to follow and implement the necessary procedures in strict compliance with Ukrainian regulations to exercise the free taxation agreement.

The US Government will not be responsible, nor will be financially liable for any mistakes or errors in the contractor's procedures for the correct implementation of the tax free agreement that applies to this United States assistance project.

2. GENERAL DESCRIPTION OF THE CONTRACT

2.1. General Description of Work

This contract includes works in three separate facilities within the city of Kramatorsk which are divided within 2 Contract Line Item Numbers (CLIN); or divided into Base-Bid and 1 additional contract option, which may, or may not, be awarded to the successful offeror. These items of work are distributed as follows:

Base-Bid (Including CLIN0001, CLIN0002 and CLIN0003): This is the minimum part of the contract that can be awarded. This includes the following works in the three sites:

CLIN0001 - Kindergarten#89: Complete renovation of the main kindergarten building. This includes the demolition of everything within the building, including windows, doors, plaster, wooded partitions, electrical installation, plumbing fixtures and piping, ventilation, roof, emergency escapes, and everything else that may be necessary in order to leave the building with exposed structure and bricks, as necessary to rebuild the entire kindergarten with same interior and exterior distribution as the existing one, but with perfectly leveled walls, with new installations, thermally insulated and with new finishes.

CLIN0002- Hospital#2 Construction of new Ambulance entrance, including new canopy or exterior covered area of minimum 100 m², minimum 150 m² of new exterior pavement and the renovation of the first room of approximately 36 m².

CLIN0003 - School#22: Renovation of ground floor dining room (approx.126 m²), food dispensing room (approx.13 m²), entrance hallway (approx. 20 m²) and the washing area. Renovation of 2 English Language classrooms

CLIN0004 or Contract Option-1: The US Government will unilaterally decide to award, or not to award, the works included in this part of the contract. All works in this part of the contract is included exclusively in Kindergarten#89.

CLIN0004 - Kindergarten#89: New playground area, canopy (min. 200 m²), cleaning and grading the plot of land, new access walkway and new perimeter fence

Design and construction for a new kindergarten playground area, a new canopy of minimum 200 m², cleaning and grading the plot of land, new access walkway and new perimeter fence

Demolition of everything within the kindergarten, to leave exposed bricks and structure, and complete reconstruction to provide a new kindergarten with same design, operations and layout as the existing one. Exterior works include the roof, façade, emergency escapes and 1 meter horizontal around the kindergarten building.

Weather protection for dual ambulance entrance and renovation of first room on ambulance entrance

- Renovation of ground floor dining room, food dispensing and hand washing areas.

- Renovation of 2 English language classrooms

2.2. Location of Kramatorsk – Safety Zone

The project has three separate sites, all located in the city of Kramatorsk. Kramatorsk is located in Donetsk Oblast as shown herein, and since 2014 Kramatorsk has been the provisional seat of the oblast, following the events surrounding the conflict in Donbass.

The city of Kramatorsk is located in the vicinity of the “Hostilities Zone” of East Ukraine. This area is within the Safety Zone as per the Anti-Terrorist Operation (ATO), currently renamed as Joint Forces Operation (JFO). Note: “ATO” is a term used by media, publicity and government of Ukraine as well OSCE and other foreign institutions to identify temporarily occupied territory of Ukraine of Donetsk and Luhansk oblasts, which are temporarily outside the control of Ukrainian government.

This “safety zone” has specific legislation which provides special authority to the Ukrainian Armed Forces and to the law enforcement officials, that the contractor needs to be familiar with.

The contractor shall be aware and familiar with these specific regulations at the time of preparation of their offers. The US Government is not responsible for any potential negative impact of the JFO specific restrictions to the normal progress of design and construction works.

Location of Kramatorsk

Location of Kramatorsk with respect to the “Hostilities Zone” (Source “liveuamap”, dated 14 November 2020)

Location of ATO or JFO zones (Kramatorsk is in the green area)

KINDERGARTEN#89

SCHOOL#22

HOSPITAL#2

2.3. Legal and Technical Requirements

The contract is based on the following general requirements:

- Strict compliance with American Federal Acquisition Regulations, including the contracting requirements of the Department of Defense, the US Navy and the US Naval Facilities Engineering Command (NAVFAC).

- Strict compliance with Ukrainian technical and legal regulations for design and construction work, as well for application of tax exemption.

- Strict compliance with Ukrainian Safety regulations, unless the US safety regulations (USACE EM 385-1-1) are more strict and not in conflict with Ukrainian safety regulations, in which case the US safety regulations shall be implemented.

- Compliance with technical and administrative requirements described in this document.

The project is based on the principle of strict compliance with Ukrainian technical and administrative regulations, with US Federal Acquisition Regulations and with Ukrainian Safety regulations, unless US regulations are more strict and not in conflict with Ukrainian safety regulations. In case of conflict between Ukrainian and US safety regulations, the contractor shall apply the Ukrainian regulations. If the US regulations are stricter and not contrary to the Ukrainian regulations, then the contractor shall apply the US regulation. The contractor shall inform the Contracting Officer Representative of any conflict between Ukrainian and US safety regulations.

The contractor shall hire the services of licensed architects/engineers/technicians in Ukraine to prepare the necessary designs and technical projects which are required for the scope of work included in this document.

The contractor shall hire the services of a licensed architect/engineers/technicians in Ukraine to:

- Make any necessary technical projects for the scope of work included in this project, as required by Ukrainian design and construction regulations in general; and as required by Ukrainian standards for renovations and improvements to schools in particular.

- Obtain the necessary construction/renovation permits for each one of the sites.

- Obtain formal approval from competent Ukrainian authorities for all completed works. This is a process designated as “formal expertise approval” which shall be managed and paid by the contractor, and which shall include all items of work. “Expertise” approval is required for all items of work included in this document, and it is the procedure by which the US Government will obtain formal confirmation of compliance with pertinent Ukrainian regulations.

Provide the final work as a complete and usable facility, including all items which are required by Ukraine regulations and which may not be described in this document. Technical details, items of work, permits or fees that are not explicitly described in this document, but which are necessary to provide fully operational and finished facilities shall be considered part of this contract.

2.4. General Contract Description

This is a design-build contract in which the US Government provides only some sketches and/or general basis of design.

The contractor is responsible to prepare all necessary design drawings and information, as it is required by Ukrainian regulations and as required for the contractor to show the Contracting Officer Representative the details of his proposed works.

This is a design-build contract. This means that the contractor is responsible to:

- Hire the services of licensed architects/engineers/technicians to make necessary design works. All design documents, including shop drawings shall be signed and stamped by the competent and pertinent licensed technical staff.

- Obtain the acceptance of those design works by the Contracting Officer Representative

- Obtain the formal approval of those design works by the competent Ukrainian authorities.

- Obtain the construction permit from Ukrainian authorities and the “Notice to Proceed” from the Contracting Officer.

- Execute the corresponding construction works.

- Provide supervision of construction activities by their architect/designer, who shall be responsible for their technical projects.

- Coordinates with the beneficiary the supervision of the construction by the designer and by the third party companies, which shall be financed by the contractor.

- Obtain the acceptance of NAVFAC and the formal approval of the competent and required

Ukrainian authorities for the executed construction works (Act of Acceptance). Obtain “expertise” approval for all items of work performed under this contract.

- The contractor is responsible to provide adequate verifiable certificate for each item of work to demonstrate that they performed the work as required by Ukrainian regulations. The Contracting Officer Representative may not approve any particular payment for an item of work that the contractor does not certify as in compliance with Ukrainian regulations. In Ukraine, these certificates are called “expertise certificate”, and the contractor shall provide all “expertise certificates” that shall be needed to prove and certify that each element of work included in this contract was performed as required by Ukrainian regulations.

In order to prepare the contractor’s bid, it is imperative that they visit the 3 sites. In order to visit the sites, the offerors shall coordinate with the Program Manager of the United States Office of Defense Cooperation (ODC) in Kyiv Ms. Lyudmyla Kyrylenko lyudmyla.v.kyrylenko.ln@mail.mil.

2.5. Construction Permit or Authorization

The contractor shall obtain formal written authorization from the competent Ukrainian authorities to perform the works included in the scope of work of these projects.

The contractor is required, as part of this contract, to prepare all documentation, designs, reports, information, drawings, coordination and approvals by experts or monitoring entities, and everything that may be necessary as required by Ukrainian regulations, in order to obtain these Permits or Authorizations. The contractor is responsible to pay for any third party inspection or expertise that may be required by Ukrainian regulations for the scope of work of this project. The contractor shall be familiar with these requirements in order to prepare their bids, regarding the obligatory administrative and technical procedures in Ukraine for public schools in particular. Formal expertise would be required as a minimum for the façade and roof works.

In addition to the legal requirements that are required because of the scope of work of this contract, the contractor shall provide a certified, signed and approved scaffolding project for any scaffolding system extending over 3 meters height.

2.6. Measurements and Quantities

This contract complies with the US Federal Acquisition Regulations, and as such, all measurements and quantities of materials provided shall be verified and measured on site by the contractor. The contractor needs to visit the job site in order to perform the necessary measurements and to observe the existing field conditions in order to prepare their cost proposal.

In order to visit the site during solicitation period, the contractor shall coordinate with the Program Manager of the United States Office of Defense Cooperation (ODC) in Kyiv Ms. Lyudmyla Kyrylenko lyudmyla.v.kyrylenko.ln@mail.mil

The US Government is not responsible for any mistake in the contractor’s measurements or assumptions of field conditions. The pictures included in this document represent the site conditions in February 2019. It is the contractor’s responsibility to visit the sites to see the real current conditions at the time of submission of the bids.

2.7. Construction Phase - General

Once the contractor completes the designs or sketches or shop drawing and they show evidence of formal authorization by the competent local authorities, and the contractor shows that they have completed other required administrative contract requirements (Accident Prevention Plan, Quality Control Plan, Construction Schedule,…), the Contracting Officer will inform the contractor that they may start the construction phase of this design-build contract. This notification is called Notice to Proceed (or NTP).

The construction shall follow the designs, technical projects, sketches or shop drawings prepared by the professionals hired by the contractor, accepted by the Contracting Officer Representative (COR) and approved by pertinent Ukrainian authorities, and for which the contractor shall obtain the pertinent Construction Permit or Formal Authorization.

Under this phase, the contractor shall provide all necessary work in order to provide complete works.

Elements that may not be explicitly included in this document, but which are absolutely necessary to provide complete and usable facilities as required by Ukrainian regulations shall be considered to be an integral part of the project, and therefore, shall be considered to be part of this contract. For example, if during the removal of a window to adjust it to the new façade finishes, the contractor damages the interior window sill or the interior wall, the contractor shall restore all internal surfaces to original conditions without any visual evidence of any construction work on the window or on the façade. Or if during renovation of the hand washing in the School#22, the drainage line is not operational, they shall perform the necessary repairs in that drainage line in order to provide a perfectly operational area.

The contractor shall familiarize with the requirements of Ukraine regulations regarding renovations of public schools, kindergartens and hospitals, as there may be required elements which are not specified in this document.

The architect/engineer/technician who signs and certifies the technical projects shall visit the site for every important and relevant phase of work, to partially accept the completed works. Despite the requirements of the Ukrainian regulations for the visits of the designer, once the works start, the architect shall visit the site as a minimum once every week. This includes the initial erection of the scaffolding system to verify compliance with Ukrainian and with contract requirements.

Two days in advance of the site visit, the contractor shall inform ODC Ukraine and the beneficiary of the planned arrival time to the job site.

In addition to these minimum weekly visits, the architect/engineer/technician shall visit the site when the COR visits the job sites, estimated at once every two months.

In addition to these visits, the third party experts that shall be required will visit the site as required by Ukraine regulations, and also when the NAVFAC COR visits the site.

Work will not be accepted until Final Expertise certificates are provided to certify that the works were performed as required by the project and as required by Ukrainian regulations.

Limitation on equipment under this contract: Tables, desks, chairs, computer, phones, beds, televisions, and other movable equipment are not part of this contract, unless otherwise indicated in these technical specifications. Only those elements that are fixed, permanently attached to the building or considered as an integral part of the facility, and specifically described in these contract specifications are included in this contract, unless otherwise indicated in this document.

Requirement for Ukraine Code and Regulation: The contractor shall request, process and pay for any permits that may be required in accordance with Ukraine Law for this type of construction works. The contractor shall provide a copy of the pertinent construction permit to be issued by the competent local authorities and approval by the Monitoring Entity of the design, before they are authorized to start work.

For each completed phase of work, the contractor shall provide the certificate of the third party monitoring entity and/or “expertise” in order to process payment for that particular phase of work.

Existing kindergarten in February 2019

3. CLIN0001 - DETAILED SCOPE OF WORK OF BASE-BID IN

KINDERGARTEN#89

The Base-Bid includes works in the kindergarten, in the school and in the hospital. This paragraph 3 corresponds to CLIN0001 which includes all elements of work included in the Base-Bid in Kindergarten#89, which corresponds to the largest portion of this contract. In general terms, CLIN0001 includes the complete reconstruction of the entire kindergarten building.

3.1. EXISTING KINDERGARTEN FACILITY

The kindergarten is made up of two large buildings. This contract includes the complete reconstruction of the main kindergarten building used by the children as indicated in the drawing in next page.

The site was visited in February 2019 and the following pictures reflect the condition of the building in February 2019. The contractor is responsible to visit the site to verify on-site conditions before preparing their proposal. It is the responsibility of the contractor to verify on-site conditions during the proposal development.

Kindergarten building to be reconstructured as part of this paragraph 3

Plot of land of kindergarten#89

Basement of the building to be reconstructed

Ground Floor of the building to be reconstructed

Basement of the building to be reconstructed

3.2. GENERAL SCOPE OF WORK

The contract includes the complete demolition of everything within the building, until it is left with exposed structure and bricks, as necessary, to provide a new kindergarten with the same internal distribution as the existing one.

The contractor shall hire the services of a Ukrainian licensed architect to prepare the full renovation project, using the following basis of design:

- Same layout as existing

- Reutilize recently installed PVC windows

- Preserve to the maximum extent possible the repair works done by the beneficiary in the last

5 years, which includes 2 rooms in the second floor, as shown in the pictures in this document.

- Everything else shall be reconstructed as required by Ukrainian regualtions for kindergarten facilities and as required by this document. This type of project is defined in Ukraine as “capital repairs”

3.3. DEMOLITIONS

Everything shall be demolished until the building is left with exposed bricks and structure, as necessary to provide perfectly leveled floors and walls. The contractor shall remove and/or demolish elements such as:

- Entrance lobby/annex

- Roof (asbestos containing materials to be removed by beneficiary)

- Roof structure

- Wooden windows

- Doors

- Exterior ladders to access the balconies

- Balconies

- Wooden structure along large balcony

- Water lines after the mater meter

- Sewer, drainage and vent pipes inside building

- Sewer lines from building to exterior manholes

- Heating pipes, radiators and all installation inside the building, including the main entrance valves.

- Electrical installation from electric meter

- Plumbing fixtures

- Wall tiles and all wall cover surfaces

- Floor tiles and all floor cover surfaces

- Plaster as necessary to provide perfectly leveled walls

- Floor bedding as necessary to provide perfectly leveled floors

- Ceiling cover (as in the front balcony)

- Ventilation

This is a contract for complete repairs or reconstruction of the kindergarten building.

Area estimated to be demolished and rebuild following current

Ukrainian norms and standards

3.4. DEMOLITION OF ENTRANCE LOOBY

This contract includes capital repairs to the kindergarten building. The building has an annex that is used as an entrance lobby or reception with approximately 15 m². It is estimated that this was an annex built without following the required codes and regulations. Consequently the basis of design includes to replace-by-replacement this construction.

3.5. HIDRO INSULATION OF THE FOUNDATIONS

The contractor shall excavate around the building and provide new hydro-insulation on the perimeter foundations. As a result of these excavations, the contractor shall provide new exposed concrete sidewalks around the entire building, provided with broom finishes, as described in the “flooring” section.

3.6. THERMALLY INSULATED FAÇADE AND SIDEWALKS

It is the general basis of design to provide thermal insulation to the façade of the building, The contractor shall hire the services of specialized and licensed technicians in Ukraine to design the new thermally insulated façade system for all exterior walls of the kindergarten building. This contract does not only include providing thermally insulated panels on the façade, but it includes a complete and properly designed thermal façade system, including the design and the final certificate, and including every item of work which shall be necessary to provide a fully operational and certified façade system.

This contract includes all exterior masonry sections of the building, as described in the pictures included in this document.

This is a design-build contract and therefore the contractor shall be responsible for the design and for the execution of the works.

Façade Design: The contractor shall provide a façade design (Façade Passport), signed and certified by a licensed architect in Ukraine, to be accepted by the Contracting Officer Representative (COR) and approved by the competent Ukrainian authorities after coordination of the design with the beneficiary. This design shall include as a minimum:

Typical section of thermal façade system

Special cover of the lowest section of thermal façade (natural stone for estimating purposes) for approximately 1.8 meters.

Color and finishes or “façade passport” with the new proposed finishes. Provide pattern and color as approved by competent local authorities and after coordination with beneficiary. The contractor’s architect shall provide several designs for the exterior appearance of the façade for the approval of the competent Ukrainian authorities. The design shall consist of a minimum combination of 4 colors, in addition to the different finishes required for the lowest section of the façade, which shall be provided with special exterior façade ceramic or natural stone tiles

Details of finishes of the thermal façade system in the top and bottom. In the top it is required to provide adequate finish with the new roof. In the bottom, it is required to provide adequate seal with the existing pavement or to provide new concrete sidewalk where there is none.

Details for special finishes and reinforcements in the corners and around the windows and doors.

The new thermal façade system shall include, but shall not be limited to:

- Water blasting the façade. Repair all façade defects, after removal of loose pieces of plaster, ceramic tiles, paint, bricks. Repair of any cracks on the facade. Providing leveling mortar as needed for the new thermal façade system. Correct any exposed reinforcing steel by epoxy based product, specifically designed for that purpose. Note that the façade has important defects in the balcony for the emergency exits from the second floor (as noted in the pictures) and consequently the contractor shall estimate that by the use of water blasting, a significant portion of the concrete of the balcony will be removed.

- Remove all wooden structures attached to the façade, such as the wooden structure used to close the balcony on the second floor.

- Provide thermal insulation panels, minimum of 8 cm thickness of wool rock (or any other thermal insulation product permitted by Ukrainian regulations with similar thermal insulation properties as 8 cm thick wool rock sheet), properly attached to the existing repaired and leveled façade, in accordance with manufacturer’s recommendations. Follow Ukrainian Fire Code. The contractor shall consult the latest Ukrainian regulations prior to submission of their bids. Only materials and installations in accordance with Ukrainian regulations in effect at the time of submission of the offers shall be authorized.

- Exterior Doors: All to be replaced with new.

- Window and sills. All exterior windows shall be new and installed in coordination with the new façade. The recently installed PVC windows can be reutilized. They shall be removed and reinstalled with new window sills.

- Sidewalks: The existing sidewalks, access steps and pavements shall be demolished in order to provide new hydro insulation of the foundations. The contractor shall restore all exterior surfaces to existing conditions, except within 1 meter of the building where the contractor shall provide new perimeter sidewalks.

- Protective plaster. There are several systems available in the market to cover the thermal insulation. The contractor shall apply over the rigid thermal insulation a protective plaster, designed to resist impact. Minimum of 1 cm thickness. This may require double netting prior to the application of the final coat of plaster. Apply in accordance with manufacturer’s recommendations. Testing shall be done by letting children play against one finished wall with a ball, tennis and basketball, for one week. After one week the wall shall not have any evidence of any damage.

- Natural stone: The lowest section of the façade shall be provided with a different cover over the thermal insulation. The height of this lowest section varies in different areas of the school#51small building, but the contractor shall estimate an average height of 1.8 meters.

This lowest section shall be provided with new leveled plaster covered with natural stone.

- Paint thermal façade system with 3 coats of paint rated for exterior use and recommended by the manufacturer of the thermal façade system. Provide artistic design with combination of colors for a kindergarten building.

- Final certificate: Once the thermal façade is complete, the contractor shall provide a copy of a certificate from the architect certifying that the thermal façade has been properly installed in accordance with their recommendations and in compliance with Ukrainian regulations.

Payment for thermal façade shall not be authorized until the contractor provides such certificate.

Example of acceptable design for the thermally insulated façade (from NAVFAC project in Ukraine)

Lowest section with natural stone cover for vandal protection.

Average 1.2 meters around all facility. Picture from NAVFAC project in central Ukraine.

Lowest natural stone over the thermal insulation, from a NAVFAC project in

Western Ukraine.

Façade Installations, Extensions and Other Exterior Surfaces

The contractor shall be responsible to reroute, remove and reinstall any of the accessories or installations that are currently anchored or supported by the existing façade which are to remain, including electrical poles, electric cables or conduits, road signs, building sign, grounding cables, security cameras, water pipes, telephone cables, gas pipes, ventilation ductwork, downspouts, and any other installation that may exist on the façade to be provided with new thermal insulation and new finishes. All works to be done in compliance with Ukrainian regulations and with approval or permit of the owner, in case it is owned by a third party. For example: if the electrical cable is owned by the electrical utility company, the contractor shall obtain the approval, or the assistance of the electrical company to remove and reinstall this cable. Or shall pay for the utility company to remove and reinstall. The contractor is responsible for all coordination and for all costs associated with this necessary work. Those installations on the façade that are not be reutilized shall be removed and disposed of by the contractor.

All cables currently supported by the existing façade and which shall remain on the façade shall be installed over new PVC channels.

The contract includes repairing the small concrete canopies attached to the façade.

It is the intent of this contract, and it is the scope of work of this contract, to provide the building with the exterior appearance of a new school building. For that reason, the contract includes the repairs of other exterior surfaces, which require repairs, but which do not require thermal insulation. These are defined in the pictures included in this document. All these surfaces shall be provided with finishes coordinated with the finishes of the new thermal façade system.

Typical façade cleaning with high pressure water.

Removing paint.

Typical façade high pressure cleaning. Removing plaster, as required for the balcony

Typical required “colorful” color combination for a kindergarten. The contractor’s architect shall propose several façade designs for the selection of the beneficiary and the acceptance of the Contracting Officer Representative.

Typical required sidewalks or walkways, which are required around the kindergarten, after providing new hydro-insulation to the foundations (under construction to the left)

Typical required finishes for the façade, from a recently completed NAVFAC project in Bulgaria (Klikach). The contractor shall use similar natural stone in the lowest section and adequate perimeter sidewalk all around the building and the new annex

Example of an acceptable Conceptual Design for a new façade. This is from a NAVFAC project awarded in Ukraine using exactly the same technical specification as the ones included in this contract.

Required exterior LED technology floodlights. Provide minimum 25 Watt each unit. Rated by continuous exterior use. With motion or light sensor.

Typical exterior LED lighting fixture with motion detection.

3.7. EXTERIOR LIGHTING

Replace the existing exterior lighting poles and fixtures attached to the building with 4 new LED lighting fixtures.

Lighting fixtures: Provide a total of 4 LED lighting fixtures. Exact location of the new exterior lighting fixtures to be indicated by the School Director. Each LED technology floodlights shall have minimum 25 Watts. Each floodlight shall be provided with its own individual switch to be located inside of the school building. Each one of the required 4 switches shall have 3 positions:

On: Always the lighting is on or functioning Off: Always the light is not working or off Automatic: The light turns on when motion is detected or when it is dark outside.

Each lighting fixture shall be provided with a motion sensor and/or a light sensor (so that it turns on automatically when it is dark outside). For estimating purposes the contractor shall estimate 6 motion detectors and 6 light sensors. All lighting fixtures to be rated for exterior use. All exterior electrical installation to be rated for exterior use.

Typical internal sill required for all windows

3.8. BALCONIES AND EMERGENCY EXITS FROM SECOND FLOOR

The previous paragraph describes the contract requirements for all installations and elements that are supported by the façade, which shall all be accounted by this contract. However, special attention needs to be paid for the emergency escapes. These include the exterior doors on the second floor, the concrete balconies and the metal stairways. The base of design is:

- Complete demolition of the concrete platforms, railing, and stairway

- Provide new platform, railing and stairway, in compliance with Ukrainian regulations for emergency escapes from kindergarten building.

The contractor’s architect shall design the necessary technical details, as to the materials to be used and the required dimensions.

3.9. EXTERIOR WINDOWS

The contractor shall completely replace the existing wooden windows with new PVC profile windows as specified herein. The recently PVC windows installed by the beneficiary shall be removed, and properly reinstalled to provide a perfect connection with the new façade and interior finishes.

The recently installed PVC windows SHALL NOT be used as the quality standard for the new ones.

The new windows shall be as required by this paragraph and not as the existing PVC windows.

Any internal window shall have similar profiles as the external windows but using a single glazing of minimum 8 mm thickness.

Provide aluminum insect screens in the exterior of all operational panels of all windows. The insect screens shall be removable and shall be provided by the manufacturer providing the new windows required by this project. Provide window blinds as in the picture in this paragraph, except in the bathrooms.

The new exterior windows shall be minimum of 5 chambered PVC profile with double glazing 6-16-6.

They shall be provided with the quality certificate that may be required for kindergartens. Provide with internal PVC sills and external aluminum or ceramic tile in coordination with the design of the thermal facade, with minimum 5% sloped away from the building. This is heavy glazing, required not only for thermal insulation but also for physical protection. The use of aluminum profiles is authorized given that the contractor shows similar of better thermal insulation characteristics.

The contractor shall include non-transparent glazing for the bathroom windows in the ground floor. The use of film to make the glazing non-transparent is not authorized.

Operational panels of the new windows shall open horizontally and vertically as shown in the picture in this paragraph. At least 50% of the window surfaces shall be made of operational panels.

Window operational leaves / panels to open horizontally and vertically

Provide window blinds, installed by the window manufacturer in all windows except in the bathrooms

Typical required PVC window profile with double glazing

Acceptable aluminum window profile with double glazing

Definition and description of break in thermal bridge

Example of acceptable design for the main entrance doors

Typical Anti-panic hardware

3.10. EXTERIOR DOORS

All exterior doors shall be replaced with new.

These exterior doors shall be designed and built with the minimum requirements specified herein:

- European standard aluminum profiles with break in the thermal bridge, and must have three rubber dust protection seals.

- With double glazing in the upper half, similar to the ones specified for the exterior windows.

- With required locks and anti-panic hardware, all made of stainless steel.

- Provided with door closers and door stops to avoid damages by users.

- Aluminum profiles shall be minimum 8 cm wide and minimum of 1.8 kg/m (heavy duty)

- As a minimum the emergency doors to be fire rated as required by Ukrainian regulations

All doors to be provided without bottom threshold, to avoid tripping hazards and movement of equipment on wheels.

The door for the basement room shall be an exception to the requirements above. The contractor may use a thermally insulated galvanized steel door with louver for ventilation.

Typical required metal door for the basement

Example of acceptable design for the main entrance doors (NAVFAC project in Romania)

Creative kindergarten main entrance door.

3.11. ROOF AND ROOF INSULATION

The contractor shall remove the existing roof of the kindergarten and provide a new preformed metal sheet roofing in order to provide a 10 year warrantee covering any roof water infiltration.

Basis of design:

Removal of all wooden elements from the roof, including the structure and the eaves. The contractor can reutilize any member of the roof structure after they are removed, cleaned, treated, inspected and accepted by the architect. Any reutilized structural member shall be physically stamped and signed by the architect in a visible location, for visual inspection by the COR. It is not only allowed but this contract, but it is a contract requirement to reutilize any existing roofing material that complies with Ukrainian regulations after it is removed, cleaned and treated, and stamped and signed by the architect.

Remove materials currently stored on the area under the roof (such as furniture) and move them to a location within the kindergarten plot of land, to be indicated by the kindergarten director.

Any asbestos containing materials shall be removed by the beneficiary. This contract does not include any asbestos handling or abatement. If any asbestos containing materials are found, the contractor shall notify the beneficiary with a minimum of 45 days advance notice of when these materials would need to be removed. It is estimated that the roof cover is made up of corrugated asbestos containing roof sheets and that there are numerous pieces of broken asbestos containing pieces of roof sheets on the floor of the roof. Although the contractor is not responsible to remove the asbestos containing materials, they are responsible to provide safe access to the roof areas in which the asbestos containing materials are found. For this reason, the contractor shall estimate that they will need to provide a certified scaffolding safe access to the roof areas from the exterior of the building. This safe access shall be made with the use of a scaffolding stairway system

Provide new perimeter beam (wood, metal or concrete) over the perimeter enclosure walls of the building in which to support the new roof structure

Provide new gutters around the entire perimeter of the kindergarten. Provide the necessary downspouts over the new façade surface.

Works includes all necessary works in order to provide a certified roof cover for the entire kindergarten. Those elements which may be necessary, but which are not described in this document, are included part of this project. For example, if snow stops are required but not specified, the contractor shall provide them. Or if for example, it is necessary according to Ukrainian standards to have a permanent access ladder, which is not specified anywhere, the contractor shall include in the contract a new permanent access ladder. Or if for example, it is required to have new lightning protection and new pertinent grounding system for the lightning protection, the contractor shall provide this new lightning and grounding systems as if perfectly detailed in this document. All elements which are required by Ukrainian regulations for the roof to be certified in compliance with Ukrainian regulations shall be considered part of this contract.

Thermally insulated. The new roofing system shall be thermally insulated. The contractor shall choose the material and place for installation, but the thermal insulation shall be similar to the

Conceptual definition of roof dormer thermal insulation that would be provided by the application of 8 cm of extruded polystyrene foam on the flat flooring under the roof.

The contractor shall provide a new roof cover in order to provide a 10 year warrantee covering any roof water infiltration.

Design of the new roofing system shall be done to maximize the use of natural light. This means that the contractor shall need to provide a minimum of 2 roof dormers with fully operational PVC windows to close in the winter and to open in the summer.

Provide electrical lighting system.

Design to be prepared by architect/engineer, as required by Ukrainian regulations, and certified by Ukrainian roof expertise, regardless of the requirements of Ukrainian regulations.

Typical required type of roof in a NAVFAC project under construction in Moldova

Typical required type of roof structure required (picture from current NAVFAC project in Montenegro)

Typical scaffolding stairways as the one that the contractor shall need to provide for the beneficiary to remove the asbestos containing materials from the roof

Same as to the left.

Roof Access

In addition to all other safety requirements, for the beneficiary to be able to access the roof to remove any asbestos containing material, the contractor shall prepare a safe scaffolding access similar to the ones shown in the pictures below. All scaffolding systems to be used in this project shall be European rated and certified as described in the next paragraph, and the beneficiary’s access to the roof shall not be an exception.

Required type of scaffold and main components

3.12. SCAFFOLDING – MANLIFTS – HARNESS – FALL PROTECTION

To perform the works in this contract, the contractor shall be required to install scaffolding or to use manlifts. The contractor is required to provide a scaffolding design to be signed and certified by a licensed Ukrainian engineer or other technician authorized by Ukrainian regulations.

Despite the scaffolds that may be authorized by Ukrainian regulations, the contractor is only authorized to utilize European Standard scaffolds similar to the ones shown in pictures below. These scaffolds shall be installed and used in accordance with manufacturer’s recommendations. In case the contractor needs to access the façade at any particular point without the need to install scaffolds, the contractor shall use a CE certified self-propelled man-lift, similar to the one shown in pictures below. The use of other type of scaffolds, other non CE certified man-lifts, or any type of ladders for façade or roof work, IS NOT AUTHORIZED. This is applicable for all works in this contract.

In addition to all other previously described safety requirements, for any scaffolding over 3 meters of height, the contractor shall prepare a scaffolding project, to be signed and stamped by a licensed architect or engineer in Ukraine and to be certified by a licensed safety expertise in Ukraine. If this is not required by Ukrainian regulations, it is part of this contract, and consequently no scaffolding shall be installed without this approved and certified project. Additionally, no person shall use the scaffolding until it is certified on site by the expert who approved the project.

Despite the requirements of Ukrainian Law for Fall Protection, any contractor employee working on the roof shall be protected with an approved harness properly tied to an approved lifeline.

All other requirements of EM385-1-1 (Safety manual of US Army Corps of Engineers) and of Ukrainian Law applies for every work activity included in this project.

Acceptable man-lift

Required type of scaffold

Required type of scaffold

Required harness and lifelines

Required harness and lifeline

Required type of scaffold

3.13. PICTURES TO CLARIFY THE EXTERIOR SCOPE OF WORK

The following pictures do not include or describe all requirements of the contract, but all requirements described in the pictures are part of the contract

Provide new bituminous or galvanized metal to cover the roof parapet

Provide new access hatch which shall be embossed into the new perimeter sidewalk or walkway

Replace all wooden and metal windows and doors

To be repaired-by-replacement

New construction to be provided with entrance canopy as the existing one to be demolsihed

Existing roof dormer. New roof to have 2 new ro0of dormer windows for lighting and ventilation

To be repaired by replacement

New perimeter sidewalks or walkways

Repair by replacement the emergency escapes from the second floor

Existing conditions

Lighting poles to be replaced with new LED lighting fixtures

Partition wall with wooden structural elements to be demolished and replaced with new PVC, as per contractor’s architect design.

All wooden elements to be

Provide new perimeter sidewalk or walkway around the entire building.

Balcony to be repaired by replacement. PVC windows can be reutilized.

Provide new canopies on all building entrances

Recently installed new pavement shall be to existing conditions after hydro-insulation of foundations

PVC windows can be reutilized

Emergency escape from second floor to be repaired by replacement in order to have an emergency escape as required by Ukrainian regulations

New sidewalks

General condition of the roof. All to be demolished. The structural members that can be reutilized shall be removed from the roof, cleaned and treated and certified by the architect as in accordance with Ukrainian regulations. They shall be stamped and signed by the architect for COR inspection.

Providing broom finish to exposed concrete surfaces

Typical acceptable broom finish for exposed concrete

Typical acceptable striped finish for exposed concrete

3.14. FLOORS

This paragraph and the following ones, include general requirements for the interior of the building.

Following the general basis of design, everything shall be repaired and provided with new finishes.

There shall be 4 types of floor:

- Exposed concrete (exclusively for the basement and the perimeter sidewalks or walkways)

- Homogeneous linoleum or vinyl - in classrooms and in sleeping rooms. (Minimum 380 m²)

- AC6 laminate in multipurpose room

- Porcelain stoneware – in all other areas

Floor Surfaces – Exposed concrete

For the basement (including the access steps) and the sidewalks around the building, the contractor shall provide reinforced concrete pavement. The contractor shall provide all exposed concrete surfaces with necessary slope and pattern to provide anti-slippery finishes.

Typical homogeneous linoleum in combination of two colors as required for the classroom.