About this file

This document package includes an Architect-Engineer Past Performance Questionnaire and information on the related Southeast Regional Architect and Engineering solicitation. The Past Performance Questionnaire is a reference evaluation form to be completed by customers of entities responding to the solicitation. It requests ratings on quality, cost control, schedule compliance and management effectiveness. Entities must provide completed questionnaires from past customers by November 23, 2020.

The related solicitation seeks Architect-Engineer services for facility design, rehabilitation and development at multiple NASA locations. Services are needed across Kennedy Space Center, Johnson Space Center, Marshall Space Flight Center, Stennis Space Center, Michoud Assembly Facility, Vandenberg Air Force Base and other NASA assets worldwide. The regional multiple award contract will provide a flexible vehicle for participating centers.

View the file

Other files for this federal contract opportunity

Other files attached to Southeast Regional Architect and Engineering (SERAE), newest first.
File Type Posted
SERAE Govt Responses 10 Nov 2020.pdf PDF
80KSC021R0002-0002 signed.pdf PDF
80KSC019F0026-0002 sign.pdf PDF
80KSC021R0002-0001 signed.pdf PDF
Attach 3 Interested Vendor List.pdf PDF
Attach 1 - Govt Responses 4 November 2020.pdf PDF
Attach 2 - Additional Addendum Items.pdf PDF
Attach 2 AE FAR Provisions .pdf PDF
Attach 3 IDIQ Questions Form.xlsx XLSX spreadsheet
Attach 4 SF330.pdf PDF
SERAE Synopsis.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT 1

SYNOPSIS NUMBER: 80KSC021R0002

ARCHITECT-ENGINEER PAST PERFORMANCE QUESTIONNAIRE

INSTRUCTIONS AND RATING GUIDELINES

Instructions

This evaluation is to be completed as indicated below. The A-E team must provide one evaluation for each past performance customer contact identified in section F of SF 330. This package consists of the following:

SectionDescriptionWho Completes
Section IBasic Contract InformationArchitect & Engineer team
being evaluated.
Section IIEvaluator Identification InformationCustomer Evaluator
Section IIIA-E Past Performance QuestionnaireCustomer Evaluator

Past Performance Questionnaires will not be accepted directly from the A-E team. Customer Evaluators must send evaluations directly to the Contracting Officer. The Customer Evaluator must submit their completed questionnaires to the address listed below, to arrive no later than 2:00 pm Eastern Standard Time (EST) on November 23, 2020.

Name:Derrick A. Wade
Email Address:derrick.a.wade@nasa.gov
Mailing Address:NASA John F. Kennedy Space Center
Procurement Office Code: OP-CS

Kennedy Space Center, Florida 32899

Or

Name:Randall A. Gumke
Email Address:randall.a.gumke@nasa.gov
Mailing Address:NASA John F. Kennedy Space Center
Procurement Office Code: OP-CS
Kennedy Space Center, Florida 32899

Section I To be completed by the A-E team submitting a submission for evaluation.

A-E Team Name:

Contract Title:

Contract Number:

Contract Award Date:

Contract Completion Date:

Point of Contact (Customer Evaluator) Name/Address/Office Phone Number:

Brief Description of Work Performed:

Section II To be completed by Customer Evaluator.

NASA will NOT divulge the names of the individuals providing reference information about an A-E team’s past performance.

Name of A-E Contractor Being Evaluated:

A-E Contractor’s Status (Prime or Sub-Consultant):

A-E Contract Number:

Description of A-E Services Provided:

A-E Contract Period of Performance:

A-E Contract or Subcontract Value at Award:
$
A-E Contract or Subcontract Value at Completion:
$

For design contracts which were completed by the A-E team and awarded for construction

1) The final estimated construction contract award price

2) The actual construction award price

1) $

2) $

Evaluator’s Company/Agency Name:

Evaluator’s Name (Typed/Printed):

Evaluator’s Signature:

Phone Number:

Facsimile Number:

E-mail address:

Dates of Involvement in Contract:

Date Questionnaire Completed:

Section III

ARCHITECT-ENGINEER PAST PERFORMANCE REPORT

RATING DEFINITIONS

For each question below, please rate the contractor from Unsatisfactory to Excellent (as defined below) and please elaborate on the specifics of your rating in the Narrative Summary. A rating of Not Applicable should be used if either the question is not applicable or the answer is unknown. The Not Applicable rating is neutral and will have no impact on the assessment of Past Performance. The Contracting Officer may contact the respondent for additional information, if needed.

Quality of Work
Cost Control

& Estimating

Compliance with Performance Schedules
Management Effectiveness

Excellent

There were no quality problems.
There were no cost issues.
There were no delays.
Responses to inquiries, technical, service, and administrative issues were effective and responsive.

Good

Technical issues did not impact achievement of contract requirements.
Cost issues did not impact achievement of contract requirements.
Delays did not impact achievement of contract requirements.
Response to inquiries, technical, service, and administrative issues were usually effective and responsive.

Fair

Technical issues required minor Client resources to ensure achievement of contract requirements.
Cost issues required minor Client resources to ensure achievement of contract requirements.
Delays required minor Client resources to ensure achievement of contract requirements.
Response to inquiries, technical, service, and administrative issues were somewhat effective and responsive.

Poor

Technical issues required major Client resources to ensure achievement of contract requirements.
Cost issues required major Client resources to ensure achievement of contract requirements.
Delays required major Client resources to ensure achievement of contract requirements.
Response to inquiries, technical, service, and administrative issues were marginally effective and responsive.

Unsatisfactory

Non-conformances or technical issues compromised the achievement of contract requirements, despite use of Client’s resources.
Cost issues compromised performance of contract requirements.
Delays compromised the achievement of contract requirements, despite the use of Client’s resources.
Response to inquiries, technical, service, and administrative issues were not effective and not responsive.

Section III (Cont’d)

Item

FACTORS/RATINGS

Excellent
Good
Fair
Poor
Unsatisfactory
Not Applicable

Quality of Work

1
Overall skill level & technical competence of A-E’s personnel
2
Ability to identify risk factors and alternatives for alleviating risk
3
Ability to identify and solve problems expeditiously
4
Overall quality of delivered products

Cost Control

5
Ability to control contract cost (if the contract experienced an overrun, please comment in the Narrative Summary)
6
Ability to search for and apply cost efficient practices
7
Ability to provide accurate and complete cost estimates

Compliance with Performance Schedules

8
Ability to complete major tasks or key project milestones on schedule
9
Ability to provide timely reports and documentation submittals

Management Effectiveness

10
Ability to effectively coordinate, integrate & manage subcontractors
11
Ability of management team to show innovation and a proactive approach to problem identification and resolution
12
Ability to effectively interface with the Customer’s staff
13
Ability to respond to customer changes
14
Ability to meet project requirements
15
Ability to effectively communicate pertinent issues throughout the contract

Customer Satisfaction

16
How would you rate the A-E’s overall management performance on this contract
17
How would you rate the A-E’s overall technical performance on this contract
18
Would you use this A-E again? (If “No”, please comment in the Narrative Summary)
YES
No

Section III (Cont’d)

NARRATIVE SUMMARY (Use this section to elaborate on the specifics of the rating and to explain additional information not included above)

Item
Comments

PAST PERFORMANCE TRANSMITTAL LETTER - SAMPLE

This acquisition is for Architect-Engineer (A-E) Services for the Design and Other Professional Services Necessary to rehabilitate, modernize, and/or develop new systems for facilities, utilities, and ground support systems (GSS) across all of the following locations; Kennedy Space Center (KSC), Florida; Johnson Space Center (JSC), Sonny Carter Training Facility (SCTF), and Ellington Field located in Houston, TX and White Sands Test Facility (WSTF) located in Las Cruces, New Mexico; Marshall Space Flight Center (MSFC) Alabama, Michoud Assembly Facility (MAF) Louisiana; Stennis Space Center (SSC) Mississippi; Vandenberg Air Force Base (VAFB), California, and other NASA assets; and launch or landing sites worldwide. This regional multiple award contract will provide a highly flexible contracting vehicle for participating Centers. Combined Synopsis number 80KSC021R0002

A-E CONTRACTOR LETTER: FORMAT

[Date of Letter] [Name and Address of A-E’s Customer] Attention: [Name and Designation of Customer Evaluator]

Dear [Customer Contact Name]:

We are currently responding to the NASA, Kennedy Space Center Request synopsis 80KSC021R0002. NASA is requesting that customers of entities responding to the synopsis participate in the evaluation process. We have included our project for your company/agency as a past performance reference. An Architect-Engineer Past Performance Report is enclosed. We respectfully request that you complete Sections II and III of the enclosed evaluation and return the signed, completed questionnaire to the Contracting Officer at either address listed below. Your completed questionnaire must arrive no later than 2:00 pm Eastern Standard Time (EST) on November 23, 2020.

Name:Derrick A. Wade
Email Address:derrick.a.wade@nasa.gov
Mailing Address:NASA John F. Kennedy Space Center
Procurement Office Code: OP-CS

Kennedy Space Center, Florida 32899

Or

Name:Randall A. Gumke
Email Address:randall.a.gumke@nasa.gov
Mailing Address:NASA John F. Kennedy Space Center
Procurement Office Code: OP-CS
Kennedy Space Center, Florida 32899

In order to maintain the integrity of this process, DO NOT return the Past Performance Report to us. Return it to the email or mailing address listed above.

Please direct any questions to the Contracting Officer, Derrick A. Wade at (321) 867-8701.

Sincerely, [Name of Signer] [Designation of Signer]

File details come from the government source that posted it. Updated .